Plan Review Stops For Permit 15051119 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
2 |
Status |
P |
Date |
2015-07-27 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2015-07-27 |
Time |
07:45 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2015-07-27 |
Time |
07:45 |
Sent To |
|
|
Notes |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
F |
Date |
2015-06-26 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2015-06-26 |
Time |
07:32 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2015-06-26 |
Time |
07:31 |
Sent To |
|
|
Notes |
2015-06-26 07:33:50 | PLAN | | REVIEW COMMENTS | | | | 1ST REVIEW: FBC 2010 | | ROBERT MCDOUGAL, CBO | | COMMERCIAL COMBINATION PLANS EXAMINER | | (561) 805-6714 | | [email protected] | | | | DENIED BY BUILDING | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | | 1) SUBMIT TWO COPIES OF AN UP TO DATE SURVEY AS | | REQUESTED BY ZONING REVIEW. FBC 107.2.1 |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
1 |
Status |
P |
Date |
2015-06-26 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2015-06-26 |
Time |
07:35 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2015-06-26 |
Time |
07:35 |
Sent To |
|
|
Notes |
2015-06-26 07:56:20 | APPROVED WITH EXCEPTION. THIS PLAN HAS BEEN APPROVED | | PROVISIONALLY. FAILURE TO CORRECT THE LISTED | | DEFICIENCIES IN THIS PLAN PRIOR TO INSPECTION WILL | | RESULT IN FAILED INSPECTION(S) AND ASSESSMENT OF | | RE-INSPECTION FEE(S). | | 1) AN ELECTRICAL PERMIT IS REQUIRED. FBC 105.1 | | 2) THE NEW POOL EQUIPMENT AND DECK IS REQUIRED TO BE | | BONDED IN ACCORDANCE WITH 2008 NEC 680.26. | | |
|
|
Review Stop |
G |
GAS REVIEW |
Rev No |
1 |
Status |
N |
Date |
2015-06-04 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2015-06-04 |
Time |
09:10 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2015-06-04 |
Time |
09:10 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
3 |
Status |
N |
Date |
2015-07-30 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2015-07-30 |
Time |
14:15 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2015-07-30 |
Time |
14:15 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2015-07-27 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2015-07-27 |
Time |
07:45 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2015-07-07 |
Time |
13:14 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2015-06-26 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2015-06-26 |
Time |
07:35 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2015-05-28 |
Time |
17:05 |
Sent To |
|
|
Notes |
2015-06-03 08:18:45 | 6/3 TO POOL BOX | | | 2015-05-28 17:05:19 | 5/28 TO ZONING | | (DISREGARD PREVIOUS NOTE) | 2015-05-27 18:33:55 | SENT TO ELECTRICAL UNDER $5000 SHELF FOR REVIEW. JG. |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
3 |
Status |
P |
Date |
2015-07-30 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2015-07-30 |
Time |
14:16 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2015-07-30 |
Time |
14:15 |
Sent To |
|
|
Notes |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
2 |
Status |
F |
Date |
2015-07-27 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2015-07-27 |
Time |
08:16 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2015-07-27 |
Time |
08:16 |
Sent To |
|
|
Notes |
2015-07-27 08:18:05 | NONE OF THE PLUMBING REVIEW COMMENTS FROM THE PREVIOUS | | REVIEW DONE ON 6/4/15 HAVE BEEN ADDRESSED. SEE BELOW. | | | | THE WORK INVOICE NOTES " INSTALL EQUIPMENT (EQUIPMENT | | SUPPLIED). INDICATE IF THIS IS THE REMOVAL AND | | REINSTALLING THE EXISTING EQUIPMENT OR IF THIS IS THE | | REPLACEMENT OF THE EXISTING WITH NEW. INDICATE IF A | | POOL HEATER WILL BE INSTALLED.IF A NEW PUMP IS BEING | | INSTALLED, INDICATE IF IT IS THE SAME SIZE, IF IT IS A | | LARGER PUMP, SUBMIT MANUFACTURER'S SPEC SHEETS AND A | | COPY OF THE PUMP CURVE FOR TOTAL DYNAMIC HEAD AND GPM | | FLOW.SUBMIT DETAILS OF THE PIPNG FOR THE MAIN DRAINS | | (PIPE SIZES). THE FLOW THROUGH THE SYSTEM SHALL COMPLY | | W/ FBC-RESIDENTIAL. SEC.R4101.6.3. | | | | | | PLUMBING PLAN REVIEW | | TIM LARGE | | CHIEF PLUMBING INSPECTOR | | 561-805-6692 | | [email protected] | | |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
1 |
Status |
F |
Date |
2015-06-04 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2015-06-04 |
Time |
09:10 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2015-06-04 |
Time |
09:00 |
Sent To |
|
|
Notes |
2015-06-04 09:10:04 | 1) THE WORK INVOICE NOTES " INSTALL EQUIPMENT | | (EQUIPMENT SUPPLIED). INDICATE IF THIS IS THE REMOVAL | | AND REINSTALLING THE EXISTING EQUIPMENT OR IF THIS IS | | THE REPLACEMENT OF THE EXISTING WITH NEW. INDICATE IF A | | POOL HEATER WILL BE INSTALLED.IF A NEW PUMP IS BEING | | INSTALLED, INDICATE IF IT IS THE SAME SIZE, IF IT IS A | | LARGER PUMP, SUBMIT MANUFACTURER'S SPEC SHEETS AND A | | COPY OF THE PUMP CURVE FOR TOTAL DYNAMIC HEAD AND GPM | | FLOW.SUBMIT DETAILS OF THE PIPNG FOR THE MAIN DRAINS | | (PIPE SIZES). THE FLOW THROUGH THE SYSTEM SHALL COMPLY | | W/ FBC-RESIDENTIAL. SEC.R4101.6.3. | | | | PLUMBING PLAN REVIEW | | TIM LARGE | | CHIEF PLUMBING INSPECTOR | | 561-805-6692 | | [email protected] | | |
|
|
Review Stop |
Z |
ZONING |
Rev No |
2 |
Status |
P |
Date |
2015-07-10 |
|
|
Cont ID |
|
Sent By |
sgraham |
Date |
2015-07-10 |
Time |
09:27 |
Rev Time |
0.00 |
Received By |
sgraham |
Date |
2015-07-10 |
Time |
09:27 |
Sent To |
B |
|
Notes |
|
|
Review Stop |
Z |
ZONING |
Rev No |
1 |
Status |
F |
Date |
2015-06-02 |
|
|
Cont ID |
|
Sent By |
sgraham |
Date |
2015-06-02 |
Time |
08:53 |
Rev Time |
0.00 |
Received By |
sgraham |
Date |
2015-06-02 |
Time |
08:53 |
Sent To |
B |
|
Notes |
2015-06-02 08:54:44 | 6/2/15 ZONING FAILED | | | | 1. SUBMIT TWO UP TO DATE SURVERYS SHOWING LOCATION OF | | ALL EQUIPMENT |
|
|