Plan Review Stops For Permit 15050170 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
4 |
Status |
P |
Date |
2015-12-05 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2015-12-05 |
Time |
12:39 |
Rev Time |
0.00 |
Received By |
shill |
Date |
2015-12-05 |
Time |
12:38 |
Sent To |
|
|
Notes |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
3 |
Status |
F |
Date |
2015-11-13 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2015-11-13 |
Time |
11:56 |
Rev Time |
0.00 |
Received By |
shill |
Date |
2015-11-13 |
Time |
11:56 |
Sent To |
|
|
Notes |
2015-11-13 12:02:06 | ****CORRECTIONS**** | | | | SAMANTHA HILL | | BUILDING PLANS EXAMINER | | [email protected] | | 561-805-6724 | | | | 1. REVISE SITE PLAN TO SHOW DISTANCE TO PROPERTY LINES | | AND TO OTHER STRUCTURES, FBC TABLE 602. | | | | ENGINEER'S RESPONSE LETTER STATES THAT THIS WAS | | ADDRESSED. I AM UNABLE TO LOCATE THE DIMENSION FROM THE | | PROPOSED STRUCTURE TO THE SOUTH PROPERTY LINE, THE | | BUILDING TO THE NORTH, OR THE PROPERTY LINE TO THE | | WEST. ALSO, IF THE DISTANCE TO THE EXISTING BUILDING IS | | LESS THAN 60', SHOW THE ASSUMED PROPERTY LINE AND | | DISTANCE FROM EACH STRUCTURE TO THE ASSUMED PROPERTY | | LINE, FBC 5TH EDITION 705.3. | | | | 2. CONFLICTING INFORMATION PREVENTS PROVIDING AN | | ACCURATE REVIEW AT THIS TIME. OCCUPANCY IS F3, BUT NO | | INFORMATION PROVIDED REGARDING THE FACTORY OPERATIONS | | WHICH ARE TO TAKE PLACE IN THE PROPOSED STRUCTURE. THE | | RESPONSE LETTER FOR FIRE STATES THAT THIS WILL BE | | STORAGE. | | | | THE PLAN IS THE OFFICIAL PERMIT RECORD. PROVIDE MORE | | INFORMATION REGARDING THE FACTORY USE OF THE SPACE, | | MATERIALS TO BE USED, CHEMICALS TO BE STORED, ETC. ALSO | | PROVIDE A PLAN WHICH SHOWS COMPLIANCE WITH FBC | | ACCESSIBILITY OR INCORPORATE APPLICABLE EXCEPTIONS INTO | | THE PLAN. | | | | SEE DESCRIPTION OF F3 - "SHALL INCLUDE, AMONG OTHERS, | | THE OCCUPANCIES LISTED IN THIS SECTION: STEEL MILLS, | | PAPER PLANTS AND GENERATING PLANTS." | | | | 3. NOT ENOUGH INFORMATION PROVIDED REGARDING THE DOOR: | | | | THE ELEVATION DIFFERENCE AT THE DOORS WAS NOT SHOWN. DO | | THE DOORS HAVE A THRESHOLD, OR IS IT A VERTICAL PIECE | | OF METAL AT THE BOTTOM? 1008.1.7 | | REVISE PLAN TO SHOW COMPLIANCE WITH SEE FBC 1003.3, | | 1003.5, 1008.1.3, 1008.1.1 (4' MAX DOOR WIDTH), | | 1008.1.9. | | PROVIDE DOOR HEIGHT, 1008. | | PROVIDE HARDWARE INFORMATION - 1008.1.9. ALSO PROVIDE | | INFORMATION ON HOW DOES THE DOOR OPEN FROM THE INSIDE? | | | | ANY EXCEPTIONS USED ARE TO BE INCORPORATED INTO THE | | PLAN. | | | | 4. REVISE PLAN TO INCLUDE OCCUPANT LOAD, FBC 1004. | | | | 5. IMPACT FEE ASSESSMENT BY PALM BEACH COUNTY REQUIRED. | | CONTACT 561-233-5025 FOR MORE INFORMATION. | | | | | | |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
2 |
Status |
F |
Date |
2015-07-08 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2015-07-08 |
Time |
13:43 |
Rev Time |
0.00 |
Received By |
shill |
Date |
2015-07-08 |
Time |
13:43 |
Sent To |
|
|
Notes |
2015-07-08 13:46:46 | ****CORRECTIONS**** | | | | SAMANTHA HILL | | BUILDING PLANS EXAMINER | | [email protected] | | 561-805-6724 | | | | 1. THE PLANS ARE FOR A STORAGE CONTAINER. CONTRACTOR'S | | RESPONSE STATES THAT THIS IS EXEMPT AS A CONSTRUCTION | | TRAILER. | | | | REVISE THE PLAN TO STATE THAT THIS IS A TEMPORARY | | CONSTRUCTION TRAILER FOR STORAGE USE ONLY (NO OFFICE). | | | | COMMENTS FROM PREVIOUS LIST WERE NOT ENTIRELY ADDRESSED | | BUT ARE NOT APPLICABLE IF THIS IS A TEMPORARY | | CONSTRUCTION TRAILER FOR CONSTRUCTION STORAGE ONLY. | | | | 2. PROVIDE THE PERMIT NUMBER FOR THE CONSTRUCTION FOR | | WHICH THIS TEMPORARY CONSTRUCTION TRAILER WILL SERVE, | | FBC 102. | | | | | | | | | | | | | 2015-06-19 16:00:38 | 6/19/15 ZONING FAILED | | | | 1. SUBMIT A COMPLETE AND UP TO DATE SITE PLAN SHOWING | | THE LOCATION OF THE CONTAINER. THE CONTAINER CAN NOT | | TAKE ANY REQUIRED PARKING, ONLY LOCATION ON THE | | PROPERTY WOULD BE IN | | THE REAR OF THE BUILDDING. |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
F |
Date |
2015-06-03 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2015-06-03 |
Time |
14:34 |
Rev Time |
0.00 |
Received By |
shill |
Date |
2015-06-03 |
Time |
14:34 |
Sent To |
|
|
Notes |
2015-06-03 14:36:57 | ****CORRECTIONS**** | | | | SAMANTHA HILL | | BUILDING PLANS EXAMINER | | [email protected] | | 561-805-6724 | | | | 1. REVISE PLAN TO INCLUDE CONSTRUCTION TYPE, FBC | | CHAPTER 5, TABLE 601. | | | | 2. REVISE SITE PLAN TO SHOW DISTANCE TO PROPERTY LINES | | AND TO OTHER STRUCTURES, FBC TABLE 602. | | | | 3. FBC CHAPTER 3, DECLARE OCCUPANCY CLASSIFICATION FOR | | THIS STRUCTURE. | | | | 4. FBC CHAPTER 10, PROVIDE A LIFE SAFETY PLAN. NO | | INFORMATION REGARDING EXITING (DOORS) WAS PROVIDED. | | | | 5. IMPACT FEE ASSESSMENT BY PALM BEACH COUNTY REQUIRED. | | CONTACT 561-233-5025 FOR MORE INFORMATION. | | | | | | |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
2 |
Status |
P |
Date |
2015-11-05 |
|
|
Cont ID |
|
Sent By |
ppetty |
Date |
2015-11-05 |
Time |
13:20 |
Rev Time |
0.00 |
Received By |
ppetty |
Date |
2015-11-05 |
Time |
13:20 |
Sent To |
|
|
Notes |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
1 |
Status |
P |
Date |
2015-05-06 |
|
|
Cont ID |
|
Sent By |
|
Date |
2015-05-06 |
Time |
16:30 |
Rev Time |
0.00 |
Received By |
dhayes |
Date |
2015-05-06 |
Time |
16:30 |
Sent To |
Z |
|
Notes |
|
|
Review Stop |
FIRE |
FIRE DEPARTMENT |
Rev No |
4 |
Status |
P |
Date |
2015-12-03 |
|
|
Cont ID |
|
Sent By |
pleduc |
Date |
2015-12-03 |
Time |
|
Rev Time |
0.00 |
Received By |
pleduc |
Date |
2015-12-03 |
Time |
14:45 |
Sent To |
|
|
Notes |
|
|
Review Stop |
FIRE |
FIRE DEPARTMENT |
Rev No |
3 |
Status |
P |
Date |
2015-11-04 |
|
|
Cont ID |
|
Sent By |
pleduc |
Date |
2015-11-04 |
Time |
|
Rev Time |
0.00 |
Received By |
pleduc |
Date |
2015-11-04 |
Time |
15:16 |
Sent To |
|
|
Notes |
|
|
Review Stop |
FIRE |
FIRE DEPARTMENT |
Rev No |
2 |
Status |
F |
Date |
2015-07-07 |
|
|
Cont ID |
|
Sent By |
pleduc |
Date |
2015-07-07 |
Time |
|
Rev Time |
0.00 |
Received By |
pleduc |
Date |
2015-07-07 |
Time |
09:14 |
Sent To |
B |
|
Notes |
2015-07-07 10:26:00 | THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE | | MARSHAL, WITH THE FOLLOWING COMMENTS: | | | | 1) BASED ON YOUR RESPONSE THAT THE TRAILER WILL BE | | INSTALLED FOR A PERIOD OF TWO YEARS IT IS CLASSIFIED AS | | A PERMANANT STRUCTURE PER NFPA 101, 3.3.271.9 AND | | 3.3.271.8. | | | | 2) THE STRUCTURE IS INDICATED AS A STORAGE OCCUPANCY. | | WILL THE STRUCTURE BE OCCUPIED AS AN OFFICE SPACE AND | | WHAT IS THE OCCUPANCY LOAD? | | | | 3) WHAT IS THE HAZARD CLASSIFICATION. WILL THE STORAGE | | OF FLAMMABLE LIQUID OR GASES, IE. GASOLINE, PROPANE, | | ACETYLENE, ETC. | | | | 4) A LIFE SAFETY PLAN WAS NOT ATTACHED. | | | | 5) EXIT SIGNS WERE NOT INDICATED. | | | | 6) EMERGENCY LIGHTING WAS NOT INDICATED. | | | | 7) THE SUBMITTED PLAN DOES NOT INDICATED ANY DOORS | | AND/OR DOOR SIZES, HARDWARE, ETC. | | | | 8) THE STROAGE HAZARD WAS NOT INDICATED. | | | | 9) FIRE EXTINGUSIHERS WERE NOT INDICATED. | | | | |
|
|
Review Stop |
FIRE |
FIRE DEPARTMENT |
Rev No |
1 |
Status |
F |
Date |
2015-05-28 |
|
|
Cont ID |
|
Sent By |
pleduc |
Date |
2015-05-28 |
Time |
16:09 |
Rev Time |
0.00 |
Received By |
pleduc |
Date |
2015-05-28 |
Time |
15:56 |
Sent To |
B |
|
Notes |
2015-05-28 16:08:12 | THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE | | MARSHAL, WITH THE FOLLOWING COMMENTS: | | | | PROVIDE A BRIEF WRITTEH STATEMENT ADRESSING THE BELOW | | CONCERNS. | | | | 1) PROVIED THE PURPOSE OF THE CONTAINOR, CONSTRUCTION | | OR GENRAL USE. | | | | 2) HOW LONG IS THE CONTAINOR PROPOSED TO BE AT THE | | SITE? | | | | 3) WHAT IS THE PROPOSED STORAGE COMMODITY? |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
5 |
Status |
N |
Date |
2015-12-08 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2015-12-08 |
Time |
11:31 |
Rev Time |
0.00 |
Received By |
shill |
Date |
2015-12-07 |
Time |
10:01 |
Sent To |
|
|
Notes |
2015-12-08 10:01:44 | IMPACT FEES GIVEN TO SHILL |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
4 |
Status |
N |
Date |
2015-12-07 |
|
|
Cont ID |
|
Sent By |
ccole |
Date |
2015-12-07 |
Time |
12:01 |
Rev Time |
0.00 |
Received By |
ccole |
Date |
2015-12-02 |
Time |
12:45 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
3 |
Status |
N |
Date |
2015-11-17 |
|
|
Cont ID |
|
Sent By |
ccole |
Date |
2015-11-17 |
Time |
09:32 |
Rev Time |
0.00 |
Received By |
ccole |
Date |
2015-10-28 |
Time |
15:04 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2015-07-08 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2015-07-08 |
Time |
14:21 |
Rev Time |
0.00 |
Received By |
shill |
Date |
2015-06-19 |
Time |
15:06 |
Sent To |
|
|
Notes |
2015-07-08 09:05:46 | 7/8 TO SH DESK | | | 2015-07-06 08:45:19 | 7/6 TO FIRE BOX | | | 2015-06-19 15:18:02 | ROUTED TO ZONING/PLEASE FORWARD TO FIRE OR BUILDING | | AFTER REVIEW/CC |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2015-06-03 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2015-06-03 |
Time |
14:38 |
Rev Time |
0.00 |
Received By |
shill |
Date |
2015-05-06 |
Time |
16:30 |
Sent To |
|
|
Notes |
2015-05-27 11:54:59 | 5/27 TO FIRE | | |
|
|
Review Stop |
IMPACT |
COUNTY IMPACT FEES |
Rev No |
3 |
Status |
P |
Date |
2015-12-08 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2015-12-08 |
Time |
11:30 |
Rev Time |
0.00 |
Received By |
shill |
Date |
2015-12-08 |
Time |
11:30 |
Sent To |
|
|
Notes |
2015-12-08 11:31:31 | $0 FEE DUE; 280 SF STORAGE CONTAINER AT SHOPPING CENTER | | | | |
|
|
Review Stop |
IMPACT |
COUNTY IMPACT FEES |
Rev No |
2 |
Status |
F |
Date |
2015-11-13 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2015-11-13 |
Time |
11:56 |
Rev Time |
0.00 |
Received By |
shill |
Date |
2015-11-13 |
Time |
11:56 |
Sent To |
|
|
Notes |
2015-11-13 11:56:27 | SEE BUILDING REVIEW | | |
|
|
Review Stop |
IMPACT |
COUNTY IMPACT FEES |
Rev No |
1 |
Status |
F |
Date |
2015-06-03 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2015-06-03 |
Time |
14:37 |
Rev Time |
0.00 |
Received By |
shill |
Date |
2015-06-03 |
Time |
14:37 |
Sent To |
|
|
Notes |
2015-06-03 14:37:53 | CONTACT 561-233-5025 FOR MORE INFORMATION | | SEE BUILDING COMMENTS | | |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
2 |
Status |
N |
Date |
2015-12-07 |
|
|
Cont ID |
|
Sent By |
ccole |
Date |
2015-12-07 |
Time |
12:01 |
Rev Time |
0.00 |
Received By |
ccole |
Date |
2015-12-07 |
Time |
12:01 |
Sent To |
|
|
Notes |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
1 |
Status |
F |
Date |
2015-11-17 |
|
|
Cont ID |
|
Sent By |
ccole |
Date |
2015-11-17 |
Time |
09:23 |
Rev Time |
0.00 |
Received By |
ccole |
Date |
2015-11-17 |
Time |
09:23 |
Sent To |
|
|
Notes |
2015-11-17 09:26:29 | 1ST REVIEW: FBC 2014 MECHANICAL | | PERMIT #15050170 | | 11/17/15 | | | | 1) PLEASE PROVIDE A MEANS OF VENTILATION AND A | | VENTILATION CALCULATION FOR THE F-3 STRUCTURE - REFER | | TO SECTION 401.2 FBC-14 MECHANICAL. | | | | CHRISTOPHER L. COLE | | MECHANICAL PLANS EXAMINER | | 561-805-6719 | | [email protected] | | |
|
|
Review Stop |
Z |
ZONING |
Rev No |
3 |
Status |
P |
Date |
2015-11-12 |
|
|
Cont ID |
|
Sent By |
sgraham |
Date |
2015-11-12 |
Time |
14:16 |
Rev Time |
0.00 |
Received By |
sgraham |
Date |
2015-11-12 |
Time |
14:16 |
Sent To |
|
|
Notes |
|
|
Review Stop |
Z |
ZONING |
Rev No |
2 |
Status |
F |
Date |
2015-06-19 |
|
|
Cont ID |
|
Sent By |
sgraham |
Date |
2015-06-19 |
Time |
15:57 |
Rev Time |
0.00 |
Received By |
sgraham |
Date |
2015-06-19 |
Time |
15:57 |
Sent To |
B |
|
Notes |
|
|
Review Stop |
Z |
ZONING |
Rev No |
1 |
Status |
F |
Date |
2015-05-08 |
|
|
Cont ID |
|
Sent By |
sgraham |
Date |
2015-05-08 |
Time |
12:27 |
Rev Time |
0.00 |
Received By |
sgraham |
Date |
2015-05-08 |
Time |
12:27 |
Sent To |
B |
|
Notes |
2015-05-08 12:28:56 | 5/8/15 ZONING FAILED | | | | 1. STORAGE CONTAINER CAN NOT BE IN THE REQUIRED PARKING | | SPACES. |
|
|