Plan Review Details - Permit 15040853
Plan Review Stops For Permit 15040853
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2015-07-07 Cont ID  
Sent By skennedy Date 2015-07-07 Time 17:10 Rev Time 0.00
Received By skennedy Date 2015-07-07 Time 17:10 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2015-05-04 Cont ID  
Sent By jwitmer Date 2015-05-04 Time 13:33 Rev Time 0.00
Received By jwitmer Date 2015-05-04 Time 10:20 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2015-07-07 Cont ID  
Sent By skennedy Date 2015-07-07 Time 17:11 Rev Time 0.00
Received By skennedy Date 2015-07-07 Time 17:11 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2015-05-12 Cont ID  
Sent By rlecky Date 2015-05-12 Time 13:53 Rev Time 0.00
Received By rlecky Date 2015-05-12 Time 13:49 Sent To  
Notes
2015-05-12 13:50:58SCOPE OF ELECTRICAL WORK NOT PROVIDED. SEE NOTE #9 ON
 PLANS. RL

Review Stop ENG ENGINEERING CSD
Rev No 2 Status N Date 2015-07-16 Cont ID  
Sent By cranford Date 2015-07-16 Time 08:00 Rev Time 0.00
Received By cranford Date 2015-07-15 Time 08:56 Sent To  
Notes
2015-07-16 08:00:421. WORK WITHIN RIGHT OF WAY TO BE AUTHORIZED UNDER
 DRIVEWAY PERMIT.
  
 2. PARKING AREA STRIPING TO BE AUTHORIZED UNDER PAVING
 PERMIT.
  
 KELLY CRANFORD, P.E.
 LAND DEVELOPMENT ENGINEER
 PUBLIC WORKS DEPARTMENT
 CITY OF WEST PALM BEACH
 [email protected]
 561-494-1098 (OFFICE)

Review Stop ENG ENGINEERING CSD
Rev No 1 Status F Date 2015-05-07 Cont ID  
Sent By cranford Date 2015-05-07 Time 12:33 Rev Time 0.00
Received By cranford Date 2015-05-07 Time 11:47 Sent To Z
Notes
2015-05-07 12:33:08PUBLIC WORKS DEPT.
 LAND DEVELOPMENT
  
 1. APPLICANTS FOR DEMOLITION AND/OR BUILDING PERMITS TO
 PERFORM LAND DISTURBING CONSTRUCTION AND LAND
 DEVELOPMENT ACTIVITIES SHALL SUBMIT A BOND OR DEPOSIT
 IN AN AMOUNT COVERING THE COST ASSOCIATED WITH
 IMPLEMENTATION OF THE SWPPP LAND STABILIZATION OF THE
 SITE. PLEASE SUBMIT A COPY OF THE AUTOCALC CERTIFIED
 COST ESTIMATE FORM AND A BOND FOR THE LAND
 STABILIZATION OF THE SITE.
 HTTP://WPB.ORG/ENGINEERING/FORMS-AND-PUBLICATIONS/ THE
 BOND WILL BE RELEASED UPON APPROVED INSPECTION OF
 TIE-BEAMS OR SIMILAR VERTICAL CONSTRUCTION. (CITY CODE
 SECTION 94-450)
  
 2. A STORMWATER POLLUTION PREVENTION PLAN (SWPPP) MUST
 BE SUBMITTED. THE PLAN WILL NEED TO ADDRESS PREVENTING
 TURBID WATER, DIRT, DUST AND OTHER CONSTRUCTION DEBRIS
 FROM LEAVING THE SITE EXCEPT IN SEALED CONTAINERS.
 (SECTION 94-450 OF THE CODE OF ORDINANCES)
  
 KELLY CRANFORD, P.E.
 LAND DEVELOPMENT ENGINEER
 PUBLIC WORKS DEPARTMENT
 CITY OF WEST PALM BEACH
 [email protected]
 561-494-1098 (OFFICE)
  
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status P Date 2015-07-07 Cont ID  
Sent By skennedy Date 2015-07-07 Time 17:11 Rev Time 0.00
Received By skennedy Date 2015-07-07 Time 17:11 Sent To ENG
Notes
2015-07-07 17:12:14STAMPED FOR PL TO EXPEDITE.

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2015-04-27 Cont ID  
Sent By pleduc Date 2015-04-27 Time   Rev Time 0.00
Received By pleduc Date 2015-04-27 Time 12:48 Sent To  
Notes
2015-04-27 13:00:33THIS PLAN WAS REVIEWED AND APPROVED BY PETER LEDUC,
 FIRE MARSHAL, WITH THE FOLLOWING COMMENTS:
  
 PLEASE CONSIDER THE FOLLOWING AS PROVISO:
  
 THE FIRE INSPECTOR WILL CONFIRM THE LOCATION OF SMOKE
 DETECTORS AND FIRE EXTINGUISHERS AT FINAL FIRE
 INSPECTION.

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2015-07-21 Cont ID  
Sent By skennedy Date 2015-07-21 Time 09:15 Rev Time 0.00
Received By skennedy Date 2015-07-06 Time 15:17 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2015-05-27 Cont ID  
Sent By tklarge Date 2015-05-27 Time 06:59 Rev Time 0.00
Received By tklarge Date 2015-04-23 Time 14:13 Sent To  
Notes
2015-04-23 14:13:18B37
  
  

Review Stop P PLUMBING
Rev No 2 Status P Date 2015-07-07 Cont ID  
Sent By skennedy Date 2015-07-07 Time 17:11 Rev Time 0.00
Received By skennedy Date 2015-07-07 Time 17:11 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status F Date 2015-05-27 Cont ID  
Sent By tklarge Date 2015-05-27 Time 06:55 Rev Time 0.00
Received By tklarge Date 2015-05-27 Time 05:18 Sent To  
Notes
2015-05-27 06:53:261) SHT.A0.2 - DEMOLITION NOTE #10 REFERS TO THE REMOVAL
 OF AN EXISTING GAS LINE TO BE CUT AND CAPPED BELOW THE
 EXISTING FLOOR LINE. THIS IS VAGUE AND MORE INFORMATION
 IS REQUIRED. INDICATE ON THE PLAN EXACTLY WHERE THIS
 EXISTING LINE WILL BE REMOVED AND "CAPPED"; PIPING
 CANNOT BE CAPPED OR RUN UNDER A BUILDING SLAB EXCEPT
 WHERE THE INSTALLATION COMPLIES WITH FGC SEC.404.12.
 CLARIFY. SECTION 406.7 OF THE 2010 FUEL GAS CODE
 REQUIRES THAT THE GAS SUPPLY SHALL BE SHUT OFF AND THE
 LINE PRESSURE VENTED TO THE OUTDOORS. THE REMAINING GAS
 IN THE SECTION OF PIPE IS TO BE PURGED WITH AN INERT
 GAS AS REQUIRED BY TABLE 406.7.1.SUBMIT ADDITIONAL
 INFORMATION AND DETAILS AS TO EXACTLY WHAT IS GOING TO
 BE CAPPED, WHERE, HOW, ETC. AIR CANNOT BE USED TO PURGE
 PIPING BECAUSE IT CONTAINS OXYGEN. WPB AMEND. TO FBC
 SEC. 107.2.1.
 2) SHOW THE DIMENSIONS OF THE NEWLY CREATED SHOWER ON
 SHT. A1.0. THE ROLL -IN SHOWER DIMENSIONS SHALL COMPLY
 WITH FAC SEC.608.2.2.
  
 PLUMBING PLAN REVIEW
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 561-805-6692
 [email protected]
  
  
  

Review Stop Z ZONING
Rev No 2 Status P Date 2015-07-20 Cont ID  
Sent By sgraham Date 2015-07-20 Time 15:25 Rev Time 0.00
Received By sgraham Date 2015-07-20 Time 15:25 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status F Date 2015-05-08 Cont ID  
Sent By sgraham Date 2015-05-08 Time 12:17 Rev Time 0.00
Received By sgraham Date 2015-05-08 Time 12:17 Sent To  
Notes
2015-05-08 12:19:085/8/15 ZONING FAILED
  
 1. SUBMIT PARKING LOT LAYOUT SHOWING THE DIMENSION OF
 EACH PARKING SPACE