Plan Review Details - Permit 15030959
Plan Review Stops For Permit 15030959
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2015-04-20 Cont ID  
Sent By skennedy Date 2015-04-20 Time 13:12 Rev Time 0.00
Received By skennedy Date 2015-04-20 Time 13:12 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2015-04-15 Cont ID  
Sent By skennedy Date 2015-04-15 Time 22:15 Rev Time 0.00
Received By skennedy Date 2015-04-15 Time 22:12 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 4 Status P Date 2015-05-14 Cont ID  
Sent By dhayes Date 2015-05-14 Time 16:18 Rev Time 0.00
Received By dhayes Date 2015-05-14 Time 14:55 Sent To  
Notes
2015-05-14 15:01:105/14/2015
 PROJECT: LAUNDRY
 PERMIT#: 15030959
 CODE: 2008 EDITION OF THE NEC, 2010 EDITION OF THE FBC
 ,2010 WPB AMENDMENTS TO THE FBC, CHAPTER 1,
 ADMINISTRATION, 2012 FBC SUPPLEMENTS.
 4TH ELECTRICAL PLAN REVIEW
 ACTION: APPROVED WITH EXCEPTION. THE PLANS HAVE BEEN
 APPROVED PROVISIONALLY. FAILURE TO CORRECT THE LISTED
 DEFICIENCIES PRIOR TO INSPECTION WILL RESULT IN FAILED
 INSPECTION(S) AND THE ASSESSMENT OF RE-INSPECTION
 FEE(S).
  
 1) IDENDIFY THE SCALE. WPB AMENDMENTS TO THE FBC
 107.2.1 THROUGH 107.2.5
  
 2)THE BRANCH CIRCUIT FEEDING THE UNIT EQUIPMENT SHALL
 BE THE SAME BRANCH CIRCUIT AS THAT SERVING THE NORMAL
 LIGHTING IN THE AREA AND CONNECTED AHEAD OF ANY LOCAL
 SWITCHES. NEC 700.12(F)
  
 3) VERIFY THE ALLOWABLE AMPACITY OF EACH CONDUCTOR
 SHALL BE REDUCED AS SHOWN IN TABLE 310.15(B)(2)(A). SEE
 ANNEX B
  
 4) BOXES AND CONDUIT BODIES SHALL BE OF SUFFICIENT SIZE
 TO PROVIDE FREE SPACE FOR ALL ENCLOSED CONDUCTORS. IN
 NO CASE SHALL THE VOLUME OF THE BOX, AS CALCULATED IN
 314.16(A), BE LESS THAN THE FILL CALCULATION AS
 CALCULATED IN 314.16(B). THE MINIMUM VOLUME FOR CONDUIT
 BODIES SHALL BE AS CALCULATED IN 314.16(C). NEC 314.16
  
 5) USE ANNEX C, THE CONDUIT AND TUBING FILL TABLES TO
 DETERMINE THE MAXIMUM FILL CAPACITY FOR CONDUCTORS AND
 FIXTURE WIRES OF THE SAME SIZE IN CONDUIT OR TUBING
 USED.
  
 DAVID HAYES, ELECTRICAL PLANS EXAMINER, PX3421,
 561-805-6717 OR [email protected]
  

Review Stop E ELECTRICAL
Rev No 3 Status F Date 2015-05-12 Cont ID  
Sent By dhayes Date 2015-05-12 Time 15:34 Rev Time 0.00
Received By dhayes Date 2015-05-12 Time 15:34 Sent To  
Notes
2015-05-12 16:04:15REVISE YOUR PLANS IN RESPONSE TO THE FOLLOWING REVIEW
 COMMENTS:
  
 1) "B PHASE 208V TO GROUND ON A 120/240 DELTA HI LEG
 ELECTRICAL DISTRIBUTION SYSTEM. THERE SHOULD BE NO
 SINGLE POLE 120V BREAKERS INSERTED INTO ANY "B" PHASE
 SLOTS IN ANY 3 PHASE DELTA PANEL BOARDS.
  
 2) ACCESS TO EXITS SHALL BE MARKED BY APPROVED, READILY
 VISIBLE SIGNS IN ALL CASES WHERE THE EXIT OR WAY TO
 REACH THE EXIT IS NOT READILY APPARENT TO THE
 OCCUPANTS. NFPA 101 SECTION 7.10.1.5.1
  
 3) EMERGENCY ILLUMINATION SHALL INCLUDE ALL REQUIRED
 MEANS OF EGRESS LIGHTING, ILLUMINATED EXIT SIGNS, AND
 ALL OTHER LIGHTS SPECIFIED AS NECESSARY TO PROVIDE
 REQUIRED ILLUMINATION. EMERGENCY LIGHTING SYSTEMS SHALL
 BE DESIGNED AND INSTALLED SO THAT THE FAILURE OF ANY
 INDIVIDUAL LIGHTING ELEMENT, SUCH AS THE BURNING OUT OF
 A LAMP, CANNOT LEAVE IN TOTAL DARKNESS ANY SPACE THAT
 REQUIRES EMERGENCY ILLUMINATION. NEC 700.16
  
 4) THE BRANCH CIRCUIT FEEDING THE UNIT EQUIPMENT SHALL
 BE THE SAME BRANCH CIRCUIT AS THAT SERVING THE NORMAL
 LIGHTING IN THE AREA AND CONNECTED AHEAD OF ANY LOCAL
 SWITCHES. THE BRANCH CIRCUIT THAT FEEDS UNIT EQUIPMENT
 SHALL BE CLEARLY IDENTIFIED AT THE DISTRIBUTION PANEL.
 EMERGENCY LUMINAIRES THAT OBTAIN POWER FROM A UNIT
 EQUIPMENT AND ARE NOT PART OF THE UNIT EQUIPMENT SHALL
 BE WIRED TO THE UNIT EQUIPMENT AS REQUIRED BY 700.9 AND
 BY ONE OF THE WIRING METHODS OF NEC CHAPTER 3. NEC
 700.12(F)
  
 5) VERIFY CONDUIT AND BOX FILL AS WELL AS CONDUCTOR
 DERATING.
  
 6) CORRECT THE SCALE THE PLAN IS DESIGNED TO.
  
 7) CORRECT THE SIZE OF THE ARCHITACT'S SEAL.
  
 DAVID HAYES, ELECTRICAL PLANS EXAMINER, PX3421,
 561-805-6717 OR [email protected]

Review Stop E ELECTRICAL
Rev No 2 Status F Date 2015-05-07 Cont ID  
Sent By dhayes Date 2015-05-07 Time 16:42 Rev Time 0.00
Received By dhayes Date 2015-05-07 Time 16:42 Sent To  
Notes
2015-05-07 16:55:014/6/2015
 PROJECT: LAUNDRY
 PERMIT#: 15030959
 CODE: 2008 EDITION OF THE NEC, 2010 EDITION OF THE FBC
 ,2010 WPB AMENDMENTS TO THE FBC, CHAPTER 1,
 ADMINISTRATION, 2012 FBC SUPPLEMENTS.
 2ND ELECTRICAL PLAN REVIEW
 ACTION: DENIED
  
 REVISE YOUR PLANS IN RESPONSE TO THE FOLLOWING REVIEW
 COMMENTS:
  
 1) NEW PANEL "C" INDICATES A 90 AMP TOTAL CONNECTED
 LOAD AT THE PANEL SCHEDULE YET IS FED BY ONLY A 70AMP
 OCPD IN THE MAIN PANEL.
  
 2) WPB AMENDMENTS TO THE FBC 107.3.2
 A) INDICATE ALL CIRCUITRY ON THE FLOOR PLAN. INDICATE
 WHAT IS EXISTING TO REMAIN AND WHAT IS PROPOSED TO BE
 NEW.
 B) INDICATE THE REQUIRED MEANS OF DISCONNECT FOR ALL
 FIXED IN PLACE APPLIANCES. NEC 422
  
 3) NEC 700.12, 700.16
 THE BRANCH CIRCUIT FEEDING THE UNIT EQUIPMENT SHALL BE
 THE SAME BRANCH CIRCUIT AS THAT SERVING THE NORMAL
 LIGHTING IN THE AREA AND CONNECTED AHEAD OF ANY LOCAL
 SWITCHES. THE BRANCH CIRCUIT THAT FEEDS EMERGENCY AND
 EXIT LIGHTING EQUIPMENT SHALL BE CLEARLY IDENTIFIED AT
 THE DISTRIBUTION PANEL. NEC 700.12
 EMERGENCY LIGHTING SHALL BE DESIGNED AND INSTALLED SO
 THAT THE FAILURE OF ANY INDIVIDUAL LIGHTING ELEMENT,
 SUCH AS THE BURNING OUT OF A LAMP, CANNOT LEAVE IN
 TOTAL DARKNESS ANY SPACE THAT REQUIRES EMERGENCY
 ILLUMINATION. INDICATE THE REQUIRED EMERGENCY AND EXIT
 LIGHTING ON THE LIGHTING PLAN. NEC 700.16
  
 5) NEC110.26
 INDICATE THE REQUIRED CLEARANCES FOR ELECTRICAL
 EQUIPMENT.
  
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM. SEE LINK:
 HTTP://WPB.ORG/DEVELOPMENT/WP-CONTENT/UPLOADS/SITES/33/
 2013/09/APPLICATION_RESUBMITTAL_FORM_04132010.PDF
  
 ADDITIONALLY, IT IS REQUIRED TO INSERT THE CORRECTED
 PAGES INTO THE DENIED SUBMITTAL PACKAGE. VOID THE
 PREVIOUSLY REVIEWED SHEETS AND LEAVE FOR COMPARATIVE
 REVIEW.
  
 DAVID HAYES, ELECTRICAL PLANS EXAMINER, PX3421,
 561-805-6717 OR [email protected]
  

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2015-04-06 Cont ID  
Sent By dhayes Date 2015-04-06 Time 10:59 Rev Time 0.00
Received By dhayes Date 2015-04-06 Time 10:39 Sent To  
Notes
2015-04-06 12:03:034/6/2015
 PROJECT: LAUNDRY
 PERMIT#: 15030959
 CODE: 2008 EDITION OF THE NEC, 2010 EDITION OF THE FBC
 ,2010 WPB AMENDMENTS TO THE FBC, CHAPTER 1,
 ADMINISTRATION, 2012 FBC SUPPLEMENTS.
 1ST ELECTRICAL PLAN REVIEW
 ACTION: DENIED
  
 1) WPB AMENDMENTS TO THE FBC 107.3.2
 ADDITIONAL INFORMATION IS REQUIRED. THE ELECTRICAL PLAN
 SUBMITTED ON SHEET E-1 INDICATES ALL ELECTRICAL
 CIRCUITRY IS EXISTING. HOWEVER, SHEET A-1 INDICATES THE
 INSTALLATION OF 3 NEW DRYERS AND 17 NEW WASHERS,
 A) PROVIDE A RISER DIAGRAM TO INDICATE THE ELECTRICAL
 SERVICE ENTRANCE, ALL MAIN OCPD(S) AND PANELS.
 B) PROVIDE PANEL SCHEDULES INCLUDING THE OCPD(S) AND
 WIRE SIZES FOR ALL AFFECTED CIRCUITRY AND FEEDERS.
 C) PROVIDE LOAD CALCULATIONS FOR THE PANELS AND FOR THE
 ELECTRICAL SERVICE.
  
 2) WPB AMENDMENTS TO THE FBC 107.3.2
 A) ADDITIONAL CLARIFICATION IS REQUIRED. INDICATE ALL
 CIRCUITRY ON THE FLOOR PLAN. INDICATE WHAT IS EXISTING
 TO REMAIN AND WHAT IS PROPOSED TO BE NEW.
 B) INDICATE THE REQUIRED MEANS OF DISCONNECT FOR ALL
 FIXED IN PLACE APPLIANCES. NEC 422
  
 3) NEC 700.12, 700.16
 THE BRANCH CIRCUIT FEEDING THE UNIT EQUIPMENT SHALL BE
 THE SAME BRANCH CIRCUIT AS THAT SERVING THE NORMAL
 LIGHTING IN THE AREA AND CONNECTED AHEAD OF ANY LOCAL
 SWITCHES. THE BRANCH CIRCUIT THAT FEEDS EMERGENCY AND
 EXIT LIGHTING EQUIPMENT SHALL BE CLEARLY IDENTIFIED AT
 THE DISTRIBUTION PANEL. NEC 700.12
 EMERGENCY LIGHTING SHALL BE DESIGNED AND INSTALLED SO
 THAT THE FAILURE OF ANY INDIVIDUAL LIGHTING ELEMENT,
 SUCH AS THE BURNING OUT OF A LAMP, CANNOT LEAVE IN
 TOTAL DARKNESS ANY SPACE THAT REQUIRES EMERGENCY
 ILLUMINATION. INDICATE THE REQUIRED EMERGENCY AND EXIT
 LIGHTING ON THE LIGHTING PLAN. NEC 700.16
  
 4)NEC 422.60
 PROVIDE EQUIPMENT MANUFACTURER DOCUMENTATION FOR ALL
 NEW EQUIPMENT INDICATING LISTING REQUIREMENTS AND
 ELECTRICAL CHARACTERISTICS SUCH AS LOAD, VOLTAGE AND
 FREQUENCY. NEC 422.60
  
 5) WPB AMENDMENTS TO THE FBC 107.3.2
 IDENTIFY ROOM DESIGNATIONS ON THE FLOOR PLAN AND
 INDICATE THE LOCATIONS FOR THE ELECTRICAL SERVICE
 ENTRANCE METER/MAINS EQUIPMENT AND PANELS.
  
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM. SEE LINK:
 HTTP://WPB.ORG/DEVELOPMENT/WP-CONTENT/UPLOADS/SITES/33/
 2013/09/APPLICATION_RESUBMITTAL_FORM_04132010.PDF
  
 ADDITIONALLY, IT IS REQUIRED TO INSERT THE CORRECTED
 PAGES INTO THE DENIED SUBMITTAL PACKAGE. VOID THE
 PREVIOUSLY REVIEWED SHEETS AND LEAVE FOR COMPARATIVE
 REVIEW.
  
 DAVID HAYES, ELECTRICAL PLANS EXAMINER, PX3421,
 561-805-6717 OR [email protected]
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status P Date 2015-04-29 Cont ID  
Sent By pleduc Date 2015-04-29 Time   Rev Time 0.00
Received By pleduc Date 2015-04-27 Time 16:50 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2015-03-25 Cont ID  
Sent By pleduc Date 2015-03-25 Time   Rev Time 0.00
Received By pleduc Date 2015-03-25 Time 15:57 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 3 Status P Date 2015-05-12 Cont ID  
Sent By tklarge Date 2015-05-12 Time 12:22 Rev Time 0.00
Received By tklarge Date 2015-05-12 Time 12:19 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 2 Status F Date 2015-05-06 Cont ID  
Sent By tklarge Date 2015-05-06 Time 14:19 Rev Time 0.00
Received By tklarge Date 2015-05-06 Time 13:21 Sent To  
Notes
2015-05-06 14:18:581) SHT. PM2 - GAS RISER - THE DRYERS ARE SHOWN AS 96
 CFH EACH BUT IN THE GAS LOAD TABLE THEY ARE SHOWN AS 90
 MBH.CLARIFY.
 2) THE TOTAL CFH/MBH LOAD ON THE SYSTEM THAT I
 CALCULATED IS 1,547 CFH.YOU HAVE CLCULATED 1469 MBH.
 PLEASE RE-CHECK YOUR CALCULATIONS.
 3) THERE ARE 7 DIFFERENT CFH LOADS ON THE GAS RISER
 DIAGRAM WHERE THERE ARE NO INCREASES IN THE NUMBER OF
 APPLIANCES. CLARIFY.
 4) THE GAS SIZING TABLES YOU HAVE LISTED (A2-2, 2-4,
 5-1, 5-2, & 3-4) ARE NOT LISTED IN THE 2010 FBC-FUEL
 GAS CODE. HOW CAN 5 DIFFERENT SIZING TABLES BE UTILIZED
 FOR ONE TYPE OF PIPING MATERIAL AT A SET DEVELOPED
 LENGTH? CLARIFY. THE SYSTEM SHALL BE SIZED PER THE
 SIZING TABLES IN CHAPTER 4 OF THE 2010 FBC-FUEL GAS
 CODE.
 5) THE PLAN SHOWS THE PIPING MATERIAL AS COPPER. COPPER
 SHALL NOT BE USED IF THE GAS CONTAINS MORE THAN AN
 AVERAGE OF 0..3 GRAINS OF HYDROGEN SULFIDE PER 100
 STANDARD CUBIC FEET OF GAS PER THE 2010 FGC
 SEC.403.4.3, 403.5.2. SINCE THIS IS A SAFETY ISSUE
 DOCUMENTATION FROM FLORIDA PUBLIC UTILITIES WILL BE
 REQUIRED STATING THE CONTENT OF HYDROGEN SULFIDE IN
 THEIR LINES.
 6) EXPLAIN HOW THE CALCULATIONS FOR THE REQUIRED
 COMBUSTION AIR WERE DONE. I DO NOT UNDERSTAND YOUR
 CALCULATIONS. THE RESULTING VALUE IS 16.29 OF WHAT?
 NOTHING IS IDENTIFIED. CLARIFY.THESE CALCULATIONS DO
 NOT APPEAR TO COMPLY WITH CHAPTER 304 OF THE 2010
 FGC.SEE THE MANUF. SPECS FOR THE DRYER FOR THE MIN.
 REQD. MAKE-UP AIR.
 7) THE PLANS STATE THAT THE VENTS SHALL BE A MIN. OF 28
 GAUGE.ARE THESE SINGLE WALL VENTS? IF SO, THE MINIMUM
 THICKNESS SHALL GALVANIZED SHEET STEEL NOT LESS THAN
 0.0304 INCH THICK. INDICATE THE THICKNESS OF THE 28
 GAUGE VENT PIPE PER THE 2010 FGC SEC.503.7.
 8) INDICATE ON THE PLANS IF THE DRYERS WILL BE
 INDIVIDUALLY VENTED THROUGH THE ROOF OR INTERCONNECTED
 WITH OTHER DRYERS.THE MANUF. SPECS RECCOMMEND
 INDIVIDUAL VENTING.IF THE FLUES ARE INTERCONNECTED,
 THEN THE VENTING SHALL COMPLY WITH THE VENTING TABLES
 IN CHAPT. 304 OF THE 2010 FGC.
  
 I SUGGEST THE DESIGN PROFESSIONAL CONTACT ME TO SET UP
 AN APPOINTMENT TO REVIEW MY PLAN REVIEW COMMENTS.
  
 PLUMBING PLAN REVIEW
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 561-805-6692
 [email protected]
  
  

Review Stop G GAS REVIEW
Rev No 1 Status F Date 2015-04-03 Cont ID  
Sent By tklarge Date 2015-04-03 Time 06:53 Rev Time 0.00
Received By tklarge Date 2015-04-03 Time 06:25 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2015-05-14 Cont ID  
Sent By dhayes Date 2015-05-14 Time 16:18 Rev Time 0.00
Received By dhayes Date 2015-05-13 Time 09:01 Sent To  
Notes
2015-05-14 09:02:28RE-SUBMITTAL SENT TO DAVID HAYES FOR REVIEW. JG.

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2015-05-07 Cont ID  
Sent By dhayes Date 2015-05-07 Time 16:55 Rev Time 0.00
Received By dhayes Date 2015-04-16 Time 17:39 Sent To  
Notes
2015-04-16 17:40:05****EXPEDITED****
 C38
  

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2015-04-15 Cont ID  
Sent By skennedy Date 2015-04-15 Time 22:15 Rev Time  
Received By skennedy Date 2015-03-23 Time   Sent To  
Notes
2015-03-23 14:26:08INCOMING SENT TO C-03.

Review Stop M MECHANICAL (A/C)
Rev No 3 Status P Date 2015-04-27 Cont ID  
Sent By hmoser Date 2015-04-27 Time 15:09 Rev Time 0.00
Received By hmoser Date 2015-04-27 Time 15:09 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 2 Status F Date 2015-04-25 Cont ID  
Sent By hmoser Date 2015-04-25 Time 10:06 Rev Time 0.00
Received By hmoser Date 2015-04-25 Time 09:56 Sent To  
Notes
2015-04-25 10:05:59PLAN DENIED
 THE INSTALLATION INSTRUCTIONS IN THE PACKAGE ARE FOR
 A T- 50 X 2 EXPRESS STACK DRYER. PLAN SHOWS A
 T- 900 DRYER. PLEASE PROVIDE INFORMATION ON THE
 DRYER BEING USED FOR THE JOB OR REVISE THE PLAN.
  
 PLAN REVIEW BY HAROLD MOSER
 [email protected]
 OFFICE 561-805-6732
 FAX 561-805-6676

Review Stop M MECHANICAL (A/C)
Rev No 1 Status F Date 2015-04-04 Cont ID  
Sent By hmoser Date 2015-04-04 Time 07:39 Rev Time 0.00
Received By hmoser Date 2015-04-04 Time 07:12 Sent To E
Notes
2015-04-04 07:38:59PLAN DENIED
 1) REFER TO SECTION 304.1 GENERAL PROVIDE
 MANUFACTURER'S INSTALLATION INSTRUCTIONS
 FOR THE CLOTHS DRYERS 2010 FBC (M)
 2) PROVIDE MECHANICAL PLAN SHOWING DRYER EXHAUST. PER
 SECTION 107 FBC 2010
  
 PLAN REVIEW BY HAROLD MOSER
 [email protected]
 OFFICE 561-805-6732
 FAX 561-805-6676

Review Stop P PLUMBING
Rev No 2 Status P Date 2015-05-06 Cont ID  
Sent By tklarge Date 2015-05-06 Time 13:21 Rev Time 0.00
Received By tklarge Date 2015-05-06 Time 10:30 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status F Date 2015-04-03 Cont ID  
Sent By tklarge Date 2015-04-03 Time 06:24 Rev Time 0.00
Received By tklarge Date 2015-04-03 Time 03:52 Sent To  
Notes
2015-04-03 06:06:171) THE WASHERS AND DRYERS SHALL COMPLY WITH THE FL.
 ACCESSIBILITY CODE SECS. 611.3 FOR THE LOCATION OF
 OPERABLE PARTS OF THE MACINES AND 611.4 FOR THE HEIGHT
 REQUIREMENTS FOR MACHINE DOORS FOR THE TOP LOADING AND
 FRONT LOADING MACHINES.SHOW ALL THE DIMENSIONS ON THE
 PLANS.
 2) THE PLANS SHOW 3 NEW DRYERS. ACTUALLY ALL THE
 EXISTING DRYERS HAVE BEEN REPLACED.INDICATE THIS ON THE
 PLANS. IDENTIFY ALL DRYERS ON THE PLANS AND NOTE THAT
 THEY ARE BEING REPLACED. WPB AMEND. TO 2010 FBC
 SEC.107.2.1.
 3) SHT. A-2 ELEVATION B-B DOES NOT CORRELATE WITH A-1.
 SHOW THE ALCOVE (NEW DRYER AREA) WALLS, ETC.
 4) NOTE ON THE PLAN IF THE EXISTING TOILET ROOM IS
 UNDERGOING ANY ALTERATION. IF SO, IT SHALL COMPLY
 W/2010 FL. ACCESSIBILITY CODE.
 5) THE PLAN SHOWS MOST OF THE DRAINAGE PIPING AND WATER
 PIPING AS EXISTING. ACTUALLY, MOST OF THIS PIPING WAS
 REMOVED WITHOUT PERMITS. THE PLANS SHALL CLARLY REFLECT
 THE ENTIRE SCOPE OF WORK TO BE DONE AND EXACTLY WHAT IS
 NEW PIPING TO BE INSTALLED.WPB AMEND. TO 2010 FBC
 SEC.107.2.1.
 6) THE SANITARY RISER SHOWS 5" DRAINAGE PIPE. THIS IS
 AN ODD SIZE PIPE. CLARIFY.
 7) THE WAY THE SANITARY RISER IS DESIGNED AND DRAWN IS
 EXTREMELY CONFUSING AND IS NOT CODE COMPLIANT.SUBMIT A
 SANITARY RISER THAT CLEARLY REFLECTS THE INSTALLATION.
 SIZE ALL VENTS, STANDPIPES, AND ALL SECTIONS OF THE
 HORIZONTAL DRAIN. INDICATE THE PITCH OF THE SANITARY
 LINES. SOME SANITARY LINES ARE SHOWN AS 2 3/8". THIS IS
 NOT A STANDARD SIZE.WPB AMEND. TO 2010 FBC SEC.
 107.3.5.1.3.
 8) CLEANOUTS ARE REQUIRED IN THE BASE OF ALL STACKS PER
 FPC SEC.708.3.4 AND AT EACH CHANGE OF DIRECTION GREATER
 THAN 45 DEGREES .FPC SEC.708.3.3.
 9) THE SANITARY RISER SHOWS A 5" LINE CONNECTING INTO
 ANOTHER 5" LINE. CLARIFY.
 10) SIZE ALL SECTIONS OF THE WATER AND SANITARY RISERS
 WHEN THEY ARE RESUBMITTED.
 11) THE HOT WATER LINE ON THE RISER CONNECTS TO
 NOTHING. THE DROP IS NOT CONNECTED TO ANYTHING.
 12) SHOW ON THE PLANS HOW THE WATER AND DRAINAGE LINES
 WILL BE SUPPORTED. SUPPORT SPACING SHALL COMPLY WITH
 TABLE 308.5 OF THE 2010 FPC.
 13) INDICATE THE TYPE OF PIPE MATERIAL FOR THE WATER
 AND DRAINAGE LINES. WPB AMEND.TO 2010 FPC SEC.107.2.1.
 140 SUBMIT MANUF. SPECIFICATION SHEETS FOR THE WASHERS.
 WASHERS SHALL COMPLY W/ ASSE 1007.
  
 GAS
 14) SIZE ALL THE NEW AND EXISTING GAS PIPING AND
 VENTS.WPB AMEND. TO 2010 FBC SEC.107.2.1.
 15) INDICATE THE TOTAL DEVELOPED LENGTH OF THE GAS
 PIPING FROM THE POINT OF DELIVERY TO THE MOST REMOTE
 GAS OUTLET.INDICATE THE PSI OF THE GAS SYSTEM,THE TYPE
 OF PIPE BEING INSTALLED, AND THE TOTAL LOAD OF THE
 SYSTEM.
 16) INDICATE THE GAS SIZING TABLE THAT IS BEING USED TO
 SIZE THE SYSTEM.INDICATE ON THE PLAN IF THE GAS IS LP
 OR NATURAL GAS.
 17) INDICATE ON THE PLAN IF THE DRYERS ARE STACKED
 DRYERS. IF SO, THE GAS RISER SHALL SHOW THE GAS
 CONNECTIONS TO ALL DRYERS.
 18) SUBMIT MANUF. SPECIFICATION SHEETS FOR THE GAS
 DRYERS. DRYERS SHALL BE LISTED AND LABELED PER THE 2010
 FGC SEC. 301.3.
 19) SUBMIT CALCULATIONS FOR COMBUSTION AIR FOR ALL GAS
 APPLIANCES PER 2010 FGC SEC. 304.1.
 20) SUBMIT DETAILS FOR THE GAS VENTS. INDICATE TYPE OF
 VENT, SIZE OF VENT, BTU LOAD ON THE VENT.
 22) THERE WERE A NUMBER OF EXISTING GAS VALVES THAT
 WERE NOT CONNECTED TO AN APPLIANCE. ANY GAS VALVES NOT
 CONNECTED TO AN APPLIANCE SHALL BE EQUIPPED WITH A
 VALVE AND CAPPED.INDICATE THESE ON THE GAS RISER.
 230 THE GAS PIPING SHALL BE PROPERLY BONDED PER THE
 2010 FGC SEC.310.1.
 A THOROUGH REVIEW COULD NOT BE DONE DUE TO THE LACK OF
 INFORMATION ON THE DRAWINGS. ADDITIONAL COMMENTS MAY BE
 GENERATED UPON THE RE-REVIEW OF THE DOCUMENTS.
  
 PLUMBING PLAN REVIEW
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 561-805-6692
 [email protected]
  
  
  
  
  
  
  
  
  

Review Stop Z ZONING
Rev No 1 Status P Date 2015-03-27 Cont ID  
Sent By ajones Date 2015-03-27 Time 10:24 Rev Time 0.00
Received By ajones Date 2015-03-27 Time 10:24 Sent To  
Notes
***NONE***