Plan Review Stops For Permit 15020880 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
P |
Date |
2015-02-26 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2015-02-26 |
Time |
11:50 |
Rev Time |
0.00 |
Received By |
shill |
Date |
2015-02-26 |
Time |
11:50 |
Sent To |
|
|
Notes |
2015-02-26 11:51:44 | SPOKE WITH CONTR - HE WILL INSTALL 30# COVERED WITH | | PAPERBACK LATH TO COMPLY W/BOND BREAK REQUIREMENT | | CONTRACTOR WILL SCHEDULE A MISCELLANEOUS INSPECTION | | PRIOR TO COMMENCEMENT FOR INSPECTOR TO VERIFY SUBSTRATE | | AND TO DISCUSS ANY OTHER INSPECTION REQUIREMENTS | | | | |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2015-02-26 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2015-02-26 |
Time |
11:50 |
Rev Time |
0.00 |
Received By |
shill |
Date |
2015-02-26 |
Time |
11:50 |
Sent To |
|
|
Notes |
|
|
|