Plan Review Details - Permit 14110286
Plan Review Stops For Permit 14110286
Review Stop E ELECTRICAL
Rev No 1 Status N Date   Cont ID  
Sent By   Date   Time 07:00 Rev Time 0.00
Received By dhayes Date   Time 06:58 Sent To  
Notes
2015-01-26 12:59:24ELECTRICAL REVIEWED UNDER PERMIT NUMBER 14110284
2014-11-25 08:41:14 
  

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2014-12-17 Cont ID  
Sent By tklarge Date 2014-12-17 Time 08:24 Rev Time 0.00
Received By tklarge Date 2014-12-17 Time 08:24 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status   Date 2014-12-16 Cont ID  
Sent By tklarge Date 2014-12-16 Time 09:42 Rev Time 0.00
Received By tklarge Date 2014-12-16 Time 07:06 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2014-12-16 Cont ID  
Sent By skennedy Date 2014-12-12 Time 07:06 Rev Time 0.00
Received By skennedy Date 2014-12-09 Time   Sent To  
Notes
2014-12-10 14:49:19INCOMING TO TK LARGE DESK.

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date   Cont ID  
Sent By   Date 2014-11-12 Time   Rev Time 0.00
Received By   Date   Time   Sent To  
Notes
2014-11-06 14:37:47ROUTED TO PLUMBING $5000 AND UNDER

Review Stop P PLUMBING
Rev No 4 Status P Date 2014-12-17 Cont ID  
Sent By tklarge Date 2014-12-17 Time 08:24 Rev Time 0.00
Received By tklarge Date 2014-12-17 Time 08:24 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 3 Status F Date 2014-12-16 Cont ID  
Sent By tklarge Date 2014-12-16 Time 09:42 Rev Time 0.00
Received By tklarge Date 2014-12-16 Time 09:42 Sent To  
Notes
2014-12-16 09:51:04TWO COPIES OF SHT. P.2 ARE REQUIRED. ONLY ONE SHEET HAS
 BEEN SUBMITTED.WPB AMEND.TO 2010 FBC SEC.107.1. 3RD
 REQUEST.

Review Stop P PLUMBING
Rev No 2 Status F Date 2014-12-11 Cont ID  
Sent By tklarge Date 2014-12-11 Time 14:29 Rev Time 0.00
Received By tklarge Date 2014-12-11 Time 14:27 Sent To  
Notes
2014-12-11 14:29:481) SUBMIT TWO COPIES OF ALL PLANS PER WPB AMEND.TO 2010
 FBC SEC.107.1. 2ND REQUEST. (THERE IS ONLY ONE SHEET OF
 P.2, LANDSCAPE LIGHTING PLANS AND HARDSCAPE PLANS.)
 2) A MINIMUM A DOUBLE CHECK VALVE ASSEMBLY IS REQUIRED
 ON THE FILL LINE TO THE FOUNTAIN PER CITY OF WPB
 ORD.SEC. 90-33 AND THE CITY'S CROSS CONNECTION CONTROL
 MANUAL. 2ND. REQUEST.
 3) PLANS SHOW A GAS SUPPLIED FIRE PIT. GAS SHALL BE
 UNDER A SEPARATE PERMIT. NOTE THIS ON THE PLANS.
  
 PLUMBING PLAN REVIEW
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 561-805-6692
 [email protected]
  

Review Stop P PLUMBING
Rev No 1 Status F Date 2014-11-12 Cont ID  
Sent By tklarge Date 2014-11-12 Time 05:36 Rev Time 0.00
Received By tklarge Date 2014-11-12 Time 05:24 Sent To  
Notes
2014-11-12 05:31:201) SUBMIT TWO COPIES OF ALL PLANS PER WPB AMEND.TO 2010
 FBC SEC.107.1
 2) THERE ARE PLANS INCLUDED FOR LANDSCAPE LIGHTING AND
 HARDSCAPE PLANS. THE VALUE OF ALL THIS WORK SHALL BE
 INCLUDED IN THE VALUE OF THIS PERMIT AND INCLUDE THIS
 SCOPE OF WORK UNDER THE DESCIPTION SECTION ON THE
 APPLICATION.
 3) A MINIMUM A DOUBLE CHECK VALVE ASSEMBLY IS REQUIRED
 ON THE FILL LINE TO THE FOUNTAIN PER CITY OF WPB
 ORD.SEC. 90-33 AND THE CITY'S CROSS CONNECTION CONTROL
 MANUAL.
  
 PLUMBING PLAN REVIEW
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 561-805-6692
 [email protected]
  


Account Summary | Usage Policy | Privacy Policy