Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2015-01-27 Cont ID  
Sent By JWITMER Date 2015-01-27 Time 11:52 Rev Time 0.00
Received By jwitmer Date 2015-01-27 Time 11:12 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2014-12-03 Cont ID  
Sent By jwitmer Date 2014-12-03 Time 10:29 Rev Time 0.00
Received By jwitmer Date 2014-12-03 Time 10:20 Sent To  
Notes
2014-12-03 10:25:27WHEN RESUBMITTING PLANS PLEASE INDICATE THE REVISION &
 REMOVE ANY VOIDED SHEETS & REPLACE ANY PAGES AS
 NECESSARY. A TRANSMITTAL LETTER LISTING THE ORIGINAL
 REVIEW COMMENT NUMBER, WITH A DESCRIPTION OF THE
 REVISION MADE, IDENTIFYING THE SHEET OR SPECIFICATION
 PAGE WHERE THE CHANGES CAN BE FOUND WILL HELP TO
 EXPEDITE YOUR PERMIT. THANK YOU FOR YOUR ANTICIPATED
 COOPERATION.
  
 TO REVIEW PERMIT STATUS OR ALL REVIEWS YOU MAY LOG ONTO
 HTTP://ONESTOPSHOP.WPBGOV.COM/EGOVPLUS/PERMIT/PERM_STA
 TUS.ASPX FOR PERMIT STATUS.
  
 JAMES A. WITMER CBO
 SENIOR COMMERCIAL COMBINATION PLANS EXAMINER
 TEL: 561-805-6715
 FAX: 561-805-6676
 E-MAIL: [email protected]
2014-11-13 09:34:40NEW SHEET SUBMITTED. JG.

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2014-10-17 Cont ID  
Sent By jwitmer Date 2014-10-17 Time 14:40 Rev Time 0.00
Received By jwitmer Date 2014-10-17 Time 14:40 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2014-10-28 Cont ID  
Sent By rlecky Date 2014-10-28 Time 12:41 Rev Time 0.00
Received By rlecky Date 2014-10-28 Time 12:32 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2014-10-14 Cont ID  
Sent By pleduc Date 2014-10-14 Time   Rev Time 0.00
Received By pleduc Date 2014-10-14 Time 13:43 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2015-01-27 Cont ID  
Sent By jwitmer Date 2015-01-27 Time 11:52 Rev Time 0.00
Received By jwitmer Date 2015-01-13 Time 08:25 Sent To  
Notes
2015-01-14 08:28:07C28

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2014-12-03 Cont ID  
Sent By jwitmer Date 2014-12-03 Time 10:25 Rev Time 0.00
Received By jwitmer Date 2014-11-12 Time 09:33 Sent To  
Notes
2014-11-13 09:34:03RE-SUBMITTAL SENT TO C28 SHELF FOR REVIEW. JG.

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2014-10-29 Cont ID  
Sent By tklarge Date 2014-10-29 Time 04:37 Rev Time 0.00
Received By tklarge Date 2014-10-06 Time 14:30 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2014-12-02 Cont ID  
Sent By rbergsma Date 2014-12-02 Time   Rev Time 0.75
Received By rbergsma Date 2014-12-02 Time   Sent To  
Notes
2014-12-02 15:14:59PAGE M2.3 CORRECTED BY MECHANICAL PROCESSOR TO REMOVE
 SANITARY OPTION FOR A/C DRAIN IN ELEVATOR CONTROL
 CLOSET

Review Stop M MECHANICAL (A/C)
Rev No 1 Status F Date 2014-10-10 Cont ID  
Sent By rbergsma Date 2014-10-10 Time   Rev Time 0.50
Received By rbergsma Date 2014-10-10 Time   Sent To  
Notes
2014-10-10 10:47:41307.2.1 CONDENSATE DISPOSAL.
 CONDENSATE FROM ALL COOLING COILS AND EVAPORATORS SHALL
 BE CONVEYED FROM THE DRAIN PAN OUTLET TO AN APPROVED
 PLACE OF DISPOSAL. SUCH PIPING SHALL MAINTAIN A MINIMUM
 HORIZONTAL SLOPE IN THE DIRECTION OF DISCHARGE OF NOT
 LESS THAN ONE-EIGHTH UNIT VERTICAL IN 12 UNITS
 HORIZONTAL (1-PERCENT SLOPE). CONDENSATE SHALL NOT
 DISCHARGE INTO A STREET, ALLEY OR OTHER AREAS SO AS TO
 CAUSE A NUISANCE.

Review Stop P PLUMBING
Rev No 3 Status P Date 2015-01-24 Cont ID  
Sent By TKLARGE Date 2015-01-24 Time 06:55 Rev Time 0.00
Received By tklarge Date 2015-01-24 Time 06:14 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 2 Status F Date 2014-11-25 Cont ID  
Sent By tklarge Date 2014-11-25 Time 07:30 Rev Time 0.00
Received By tklarge Date 2014-11-25 Time 07:01 Sent To  
Notes
2014-11-25 07:08:521) THERE WAS A PROVISO PLACED ON THE ORIGINAL PLANS
 THAT AN OIL SEPARATOR IS REQUIRED FOR THE DISCHARGE
 FROM THE ELEVATOR SUMP PER THE 2010 FPC SEC.1003.4. THE
 REVISED PLANS DO NOT SHOW AN OIL SEPARATOR NOR DO I SEE
 ANY VERIFICATION OF THIS INSTALLATION MEETING THE
 EXCEPTION TO SEC. 1003.4. CLARIFY.
 2) THE NEW SHEETS SHALL BE INSERTED INTO THE PLANS.
  
 PLUMBING PLAN REVIEW
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 561-805-6692
 [email protected]
  

Review Stop P PLUMBING
Rev No 1 Status F Date 2014-10-29 Cont ID  
Sent By tklarge Date 2014-10-29 Time 04:37 Rev Time 0.00
Received By tklarge Date 2014-10-29 Time 04:33 Sent To  
Notes
2014-10-29 04:37:161) SHT. A002 - BACKING FOR GRAB BARS AT THE TUB BACK
 WALL SHALL BE 48 INCHES LONG MINIMUM.SHOW THE WIDTH OF
 THE BACKING.
 2) SUPPLY A NARRATIVE THAT EXPLAINS THE CHANGES TO THE
 WATER AND SANITARY SYSTEMS.
 3) SUBMIT REVISED SANITARY AND WATER RISERS THAT
 REFLECT THE CHANGES.
 WPB AMEND. TO 2010 FBC SEC. 107.2.1.
  
 PLUMBING PLAN REVIEW
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 561-805-6692
 [email protected]
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved