Plan Review Stops For Permit 14080903 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
5 |
Status |
|
Date |
|
|
|
Cont ID |
|
Sent By |
|
Date |
|
Time |
|
Rev Time |
0.00 |
Received By |
|
Date |
|
Time |
|
Sent To |
|
|
Notes |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
4 |
Status |
F |
Date |
2015-01-29 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2015-01-29 |
Time |
15:02 |
Rev Time |
0.00 |
Received By |
shill |
Date |
2015-01-21 |
Time |
09:00 |
Sent To |
|
|
Notes |
2015-01-29 15:24:06 | 4TH REVIEW: FBC 2010 | | | | IN THIS RE-SUBMITTAL, THE APPLICANT HAS PROVIDED A DCA | | PLAN MDS007344. THE DCA COVER LETTER WAS NOT PROVIDED, | | AND THE PLANS DO NOT HAVE THE DCA STAMP ON THEM. I WAS | | UNABLE TO LOCATE THE PLAN ON FLORIDABUILDING.ORG. IT IS | | UNCLEAR HOW THIS PLAN RELATES TO THE INSIGNAI | | PREVIOUSLY PROVIDED. | | | | THE PLAN SUBMITTED IS FOR EDUCATIONAL OCCUPANCY; | | THEREFORE, THIS HAS BEEN REVIEWED FOR EDUCATIONAL USE | | ONLY. PLEASE ADDRESS. NO INFORMATION WAS PROVIDED | | REGARDING THE PROPOSED USE OF THIS STRUCTURE. ALTHOUGH | | APPLICATION STATES THIS IS "EXISTING" IT IS NOT | | CONSIDERED "EXISTING" IF A PERMIT WAS NOT OBTAINED. IT | | APPEARS THAT THIS WAS INSTALLED AFTER 2012. | | | | FROM PREVIOUS LISTS, BE ADVISED THAT THE FOUNDATION | | PLAN DOES NOT COMPLY WITH FBC R403.1.4 MINIMUM DEPTH. | | ALL EXTERIOR FOOTINGS SHALL BE PLACED AT LEAST 12 | | INCHES (305 MM) BELOW THE UNDISTURBED GROUND SURFACE. | | NO ADDITIONAL INFORMATION WAS PROVIDED. | | | | ELECTRICAL IS SHOWN ON THE MODULAR PLAN, AS WELL AS AN | | OPTIONAL BATHROOM, BUT NO INFORMATION PROVIDED | | REGARDING ELECTRICAL CONNECTION OR PLUMBING CONNECTION | | FOR REVIEW. PLANS WILL BE ROUTED FOR ELECTRICAL AND | | PLUMBING REVIEWS AFTER THIS INFORMATION IS SUBMITTED. | | | | FROM PREVIOUS THREE REVIEWS, FBC 109.3 BUILDING PERMIT | | VALUATION. FOR PERMITTING PURPOSES, VALUATION OF | | BUILDINGS AND SYSTEMS SHALL BE TOTAL REPLACEMENT VALUE | | TO INCLUDE STRUCTURAL, ELECTRIC, PLUMBING, MECHANICAL, | | INTERIOR FINISH, RELATIVE SITE WORK, ARCHITECTURAL AND | | DESIGN FEES, MARKETING COSTS, OVERHEAD AND PROFIT; | | EXCLUDING ONLY LAND VALUE. VALUATION REFERENCES MAY | | INCLUDE THE LATEST PUBLISHED DATA OF NATIONAL | | CONSTRUCTION COST ANALYSIS SERVICES (MARSHALL-SWIFT, | | MEANS, ETC.), AS PUBLISHED BY INTERNATIONAL CODE | | CONGRESS. FINAL BUILDING PERMIT VALUATION SHALL BE SET | | BY THE BUILDING OFFICIAL. | | | | NO IMPACT PROTECTION SHOWN FOR THE MODULAR, PLEASE | | ADDRESS FBC 2010 RESIDENTIAL 301.2.1.2, FBC 1609.1.4. | | (OCCUPANCY CLASSIFICATION HAS NOT BEEN DETERMINED.) IF | | REMOVABLE SHUTTERS ARE PROPOSED, PROVIDE PRODUCT | | APPROVALS AND THE SAMPLE INSTALLATION SCHEDULE (OR ALL | | INFORMATION IN ANOTHER FORMAT): | | | | HTTP://WPB.ORG/DEVELOPMENT/WP-CONTENT/UPLOADS/SITES/33/ | | 2013/09/SCHEDULE_FOR_INSTALLATION.PDF | | | | WHEN RESUBMITTING, PLEASE PROVIDE A RESPONSE LETTER | | STATING HOW EACH ITEM WAS ADDRESSED (THIS MAY BE DONE | | BY CONTRACTOR). ENGINEER IS TO ACKNOWLEDGE RECEIPT OF | | THE STRUCTURAL COMMENT. | | | | SAMANTHA M. HILL | | BUILDING PLANS EXAMINER | | 561-805-6724 | | [email protected] | | |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
3 |
Status |
F |
Date |
2014-12-30 |
|
|
Cont ID |
|
Sent By |
skennedy |
Date |
2014-12-30 |
Time |
08:02 |
Rev Time |
0.00 |
Received By |
skennedy |
Date |
2014-12-30 |
Time |
08:02 |
Sent To |
|
|
Notes |
2014-12-30 09:31:59 | 3RD REVIEW: FBC 2010 | | | | IN THIS RE-SUBMITTAL, THE APPLICANT HAS PROVIDED ONLY A | | LEGACY DCA INSIGNIA # IVE-002378 FOR THE MODULAR | | BUILDING. I COULD NOT LOCATE THE PLAN ON | | FLORIDABUILDING.ORG. PLEASE UPDATE THE VALUE OF THE | | IMPROVEMENT AND PROVIDE THE PLAN. ADDITIONALLY, BE | | ADVISED THAT THE FOUNDATION PLAN DOES NOT COMPLY WITH | | FBC R403.1.4 MINIMUM DEPTH. ALL EXTERIOR FOOTINGS SHALL | | BE PLACED AT LEAST 12 INCHES (305 MM) BELOW THE | | UNDISTURBED GROUND SURFACE. | | | | THE BELOW COMMENTS FROM THE SECOND REVIEW ARE NOT | | ADDRESSED. | | | | THE SUBMITTED PLAN IS ONLY A FOUNDATION PLAN AND SURVEY | | SHOWING AN UNIDENTIFIED 36'X23.5 MODULAR BUILDING. | | PROVIDE A PLAN FOR THE BUILDING.PROVIDE ANY OTHER PLANS | | SUCH AS ELECTRICAL, PLUMBING, AIR CONDONDITIONING AS | | MAY BE NEEDED. | | | | PROVIDE PLANS PER FBC 107. | | | | FBC 109.3 BUILDING PERMIT VALUATION. FOR PERMITTING | | PURPOSES, VALUATION OF BUILDINGS AND SYSTEMS SHALL BE | | TOTAL REPLACEMENT VALUE TO INCLUDE STRUCTURAL, | | ELECTRIC, PLUMBING, MECHANICAL, INTERIOR FINISH, | | RELATIVE SITE WORK, ARCHITECTURAL AND DESIGN FEES, | | MARKETING COSTS, OVERHEAD AND PROFIT; EXCLUDING ONLY | | LAND VALUE. VALUATION REFERENCES MAY INCLUDE THE LATEST | | PUBLISHED DATA OF NATIONAL CONSTRUCTION COST ANALYSIS | | SERVICES (MARSHALL-SWIFT, MEANS, ETC.), AS PUBLISHED BY | | INTERNATIONAL CODE CONGRESS. FINAL BUILDING PERMIT | | VALUATION SHALL BE SET BY THE BUILDING OFFICIAL. | | | | STEVEN KENNEDY, CBO | | CHIEF PLANS EXAMINER | | (561) 805-6710 | | [email protected] | | | | | | |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
2 |
Status |
F |
Date |
2014-10-05 |
|
|
Cont ID |
|
Sent By |
skennedy |
Date |
2014-10-05 |
Time |
12:11 |
Rev Time |
0.00 |
Received By |
skennedy |
Date |
2014-10-05 |
Time |
12:11 |
Sent To |
|
|
Notes |
2014-10-05 12:18:15 | 2ND REVIEW: FBC 2010 | | | | THE SUBMITTED PLAN IS ONLY A FOUNDATION PLAN AND SURVEY | | SHOWING AN UNIDENTIFIED 36'X23.5 MODULAR BUILDING. | | PROVIDE A PLAN FOR THE BUILDING.PROVIDE ANY OTHER PLANS | | SUCH AS ELECTRICAL, PLUMBING, AIR CONDONDITIONING AS | | MAY BE NEEDED. | | | | PROVIDE PLANS PER FBC 107. | | | | FBC 109.3 BUILDING PERMIT VALUATION. FOR PERMITTING | | PURPOSES, VALUATION OF BUILDINGS AND SYSTEMS SHALL BE | | TOTAL REPLACEMENT VALUE TO INCLUDE STRUCTURAL, | | ELECTRIC, PLUMBING, MECHANICAL, INTERIOR FINISH, | | RELATIVE SITE WORK, ARCHITECTURAL AND DESIGN FEES, | | MARKETING COSTS, OVERHEAD AND PROFIT; EXCLUDING ONLY | | LAND VALUE. VALUATION REFERENCES MAY INCLUDE THE LATEST | | PUBLISHED DATA OF NATIONAL CONSTRUCTION COST ANALYSIS | | SERVICES (MARSHALL-SWIFT, MEANS, ETC.), AS PUBLISHED BY | | INTERNATIONAL CODE CONGRESS. FINAL BUILDING PERMIT | | VALUATION SHALL BE SET BY THE BUILDING OFFICIAL. | | | | STEVEN KENNEDY, CBO | | CHIEF PLANS EXAMINER | | (561) 805-6710 | | [email protected] | | | | | | |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
F |
Date |
2014-08-22 |
|
|
Cont ID |
|
Sent By |
skennedy |
Date |
2014-08-22 |
Time |
14:30 |
Rev Time |
|
Received By |
skennedy |
Date |
|
Time |
|
Sent To |
|
|
Notes |
2014-08-22 14:33:10 | 1ST REVIEW: FBC 2010 | | | | PROVIDE PLANS PER FBC 107. | | | | FBC 109.3 BUILDING PERMIT VALUATION. FOR PERMITTING | | PURPOSES, VALUATION OF BUILDINGS AND SYSTEMS SHALL BE | | TOTAL REPLACEMENT VALUE TO INCLUDE STRUCTURAL, | | ELECTRIC, PLUMBING, MECHANICAL, INTERIOR FINISH, | | RELATIVE SITE WORK, ARCHITECTURAL AND DESIGN FEES, | | MARKETING COSTS, OVERHEAD AND PROFIT; EXCLUDING ONLY | | LAND VALUE. VALUATION REFERENCES MAY INCLUDE THE LATEST | | PUBLISHED DATA OF NATIONAL CONSTRUCTION COST ANALYSIS | | SERVICES (MARSHALL-SWIFT, MEANS, ETC.), AS PUBLISHED BY | | INTERNATIONAL CODE CONGRESS. FINAL BUILDING PERMIT | | VALUATION SHALL BE SET BY THE BUILDING OFFICIAL. | | | | STEVEN KENNEDY, CBO | | CHIEF PLANS EXAMINER | | (561) 805-6710 | | [email protected] | | | | | | |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
1 |
Status |
|
Date |
|
|
|
Cont ID |
|
Sent By |
|
Date |
|
Time |
|
Rev Time |
0.00 |
Received By |
|
Date |
|
Time |
|
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
5 |
Status |
|
Date |
|
|
|
Cont ID |
|
Sent By |
|
Date |
|
Time |
|
Rev Time |
0.00 |
Received By |
|
Date |
2015-02-06 |
Time |
|
Sent To |
|
|
Notes |
2015-02-24 08:38:27 | R22 | | | 2015-02-07 06:33:49 | INCOMING SENT TO S. HILLS' DESK. |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
4 |
Status |
N |
Date |
2015-01-29 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2015-01-29 |
Time |
15:24 |
Rev Time |
0.00 |
Received By |
shill |
Date |
2015-01-09 |
Time |
08:45 |
Sent To |
|
|
Notes |
2015-01-21 09:00:42 | 1/21 TO SH DESK FOR BUILDING REVIEW | | | | |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
3 |
Status |
N |
Date |
2014-12-30 |
|
|
Cont ID |
|
Sent By |
skennedy |
Date |
2014-12-30 |
Time |
09:34 |
Rev Time |
0.00 |
Received By |
skennedy |
Date |
2014-12-29 |
Time |
09:37 |
Sent To |
|
|
Notes |
2014-12-29 09:38:03 | TO SAK DESK | | |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2014-10-05 |
|
|
Cont ID |
|
Sent By |
skennedy |
Date |
2014-10-05 |
Time |
12:11 |
Rev Time |
0.00 |
Received By |
skennedy |
Date |
2014-09-24 |
Time |
|
Sent To |
|
|
Notes |
2014-09-26 15:42:53 | TO MISC 2 BOX. | 2014-09-24 14:03:23 | ZONING | | |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2014-08-22 |
|
|
Cont ID |
|
Sent By |
skennedy |
Date |
2014-08-22 |
Time |
14:33 |
Rev Time |
0.00 |
Received By |
skennedy |
Date |
2014-08-22 |
Time |
07:26 |
Sent To |
|
|
Notes |
2014-08-22 07:26:28 | INCOMING SENT TO ZONING. JW |
|
|
Review Stop |
IMPACT |
COUNTY IMPACT FEES |
Rev No |
1 |
Status |
|
Date |
|
|
|
Cont ID |
|
Sent By |
|
Date |
|
Time |
|
Rev Time |
0.00 |
Received By |
|
Date |
|
Time |
|
Sent To |
|
|
Notes |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
1 |
Status |
|
Date |
|
|
|
Cont ID |
|
Sent By |
|
Date |
|
Time |
|
Rev Time |
0.00 |
Received By |
|
Date |
|
Time |
|
Sent To |
|
|
Notes |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
1 |
Status |
F |
Date |
2015-03-01 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2015-03-01 |
Time |
08:15 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2015-02-28 |
Time |
11:24 |
Sent To |
|
|
Notes |
2015-03-01 08:14:55 | 1)THE OCCUPANCY NOTED ON THE PLANS IS SHOWN AS | | EDUCATIONAL. TABLE 403.1 OF THE FL. PLUMBING CODE | | REQUIRES SEPARATE FACILITIES FOR THE MALES AND FEMALES. | | A MINIMUM OF ONE WATER CLOSET AND ONE LAVATORY SHALL BE | | PROVIDED FOR THE MALES AND ALSO THE FEMALES. A SERVICE | | SINK IS ALSO REQUIRED AND A DRINKING FOUNTAIN. | | 2) A MINIMUM OF TWO DRINKING FOUNTAINS SHALL BE | | SUPPLIED IN ACCORDANCE WITH THE 2010 FL. ACCESSIBILITY | | CODE SEC. 211.2 | | 3) THE BUILDING SHALL COMPLY WITH FL. STATUTE 553.415 | | AND SECTION 428 OF THE 2010 FL. BUILDING CODE. APPROVED | | PLANS AND SPECIFICATIONS SHALL BE EVIDENCED BY A LETTER | | OF CERTIFICATION FROM THE AGENCY AUTHORIZED TO PERFORM | | INSPECTIONS OF OR REVIEW PLANS FOR MANUFACTURED | | BUILDINGS AS PROVIDED IN FL. ADMIN. RULE 9B-1 PER THE | | 2010 FBC SEC.428.2, 428.4.2. | | 4) SHT. A1 SHOWS A CITY WATER CONNECTION TO THE TRAILER | | AND THERE IS ALSO AN 8 1/2' X 11' DRAWING STAPLED TO | | THE PLAN SHOWING THE SOURCE OF WATER BEING A RAIN | | BARREL. CLARIFY. IF A RAIN BARREL WILL BE THE WATER | | SOURCE, SUBMIT A COMPLETE PIPNG PLAN INCLUDING THE PUMP | | SHOWING HOW THE WATER WILL BE PIPED TO THE TRAILER AND | | HOW THE PRESSURE WILL BE MAINTAINED. WPB AMEND. TO 2010 | | FBC SEC. 107.2.1. | | 5) ONLY POTABLE WATER SHALL BE SUPPLIED TO PLUMBING | | FIXTURES THAT PROVIDE WATER FOR DRINKING , BATHING, OR | | CULINARY PURPOSES PER THE 2010 FPC SEC. 602.2. SIGNS | | SHALL BE POSTED AT ANY FIXTURE UTILIZING NON-POTABLE | | WATER THAT THE WATER IS NON-POTABLE AND NOT FOR DRINING | | PURPOSES. | | | | PLUMBING PLAN REVIEW | | TIM LARGE | | CHIEF PLUMBING INSPECTOR | | 561-805-6692 | | [email protected] | | |
|
|
Review Stop |
Z |
ZONING |
Rev No |
4 |
Status |
|
Date |
|
|
|
Cont ID |
|
Sent By |
|
Date |
|
Time |
|
Rev Time |
0.00 |
Received By |
|
Date |
|
Time |
|
Sent To |
|
|
Notes |
|
|
Review Stop |
Z |
ZONING |
Rev No |
3 |
Status |
P |
Date |
2014-12-22 |
|
|
Cont ID |
|
Sent By |
aaponte |
Date |
2014-12-22 |
Time |
16:09 |
Rev Time |
0.00 |
Received By |
aaponte |
Date |
2014-12-22 |
Time |
16:09 |
Sent To |
|
|
Notes |
|
|
Review Stop |
Z |
ZONING |
Rev No |
2 |
Status |
F |
Date |
2014-09-26 |
|
|
Cont ID |
|
Sent By |
aaponte |
Date |
2014-09-26 |
Time |
15:38 |
Rev Time |
0.00 |
Received By |
aaponte |
Date |
2014-09-26 |
Time |
15:38 |
Sent To |
|
|
Notes |
2014-09-26 15:42:21 | 1. PLEASE SUBMIT DRAWINGS WITH NEW STRUCTURE ON SITE. | | IS THE USE A RESIDENTIAL UNIT? | | 2. A NEW PARKING SPACE SHALL BE PROVIDED FOR THE NEW | | UNIT. | | 3. WHAT IS THE VALUE OF THE NEW STRUCTURE ON SITE? | | 4. LANDSCAPE REQUIREMENTS MAY BE TRIGGERED BY THE NEW | | STRUCTURE ON SITE. TO BE DETERMINED BY VALUE | | INFORMATION. | | FOR ADDITIONAL INFORMATION PLEASE CONTACT ANA MARIA | | APONTE AT 561-822-1439. |
|
|
Review Stop |
Z |
ZONING |
Rev No |
1 |
Status |
F |
Date |
2014-08-22 |
|
|
Cont ID |
|
Sent By |
sgraham |
Date |
2014-08-22 |
Time |
09:18 |
Rev Time |
0.00 |
Received By |
sgraham |
Date |
2014-08-22 |
Time |
09:18 |
Sent To |
B |
|
Notes |
2014-08-22 09:19:14 | 8/22/14 ZONING FAILED | | | | 1.NO PLANS INCLUDED WITH PERMIT APPLICATION. |
|
|