2014-07-31 14:56:02 | RESIDENTIAL (R3) ALTERATION, BUILDING REVIEW COMMENTS. |
| CODE: 2010 FBC. |
| |
| 1- VALUATION DECLARED IN THE PERMIT APPLICATION IS TOO |
| LOW. SEC. 109.3 CITY AMENDMENTS TO FBC. VALUATION TO |
| INCLUDE ALL LABOR, MATERIALS AND CONTRACTOR'S OVERHEAD |
| AND PROFIT. UPDATE VALUATION AS REQUIRED. |
| |
| 2- PROVIDE ACCORDION SHUTTERS COMPLETE INSTALLATION |
| SCHEDULE. INSTALLATION SCHEDULE SUBMITTED IS |
| INCOMPLETE. NEED TO FILL THE INFORMATION IN ALL THE |
| COLUMNS TO VERIFY COMPLIANCE WITH THE DESIGN PRESSURES |
| OF SEC. R301 OF 2010 FBC-RESIDENTIAL. |
| |
| 3- PAGE 14 OF 16 OF ACCORDION SHUTTERS DRAWINGS |
| SUBMITTED ARE FOR DETAIL 10T TOP INSTALLATION AND |
| DETAIL 10B BOTTOM INSTALLATION. CLARIFY HOW INSTALLING |
| THE ACCORDION SHUTTERS PER DETAIL 10T TOP INSTALLATION. |
| WHERE IS THE 1/8" X 4" ALUMINUM PLATE ATTACHED TO?. |
| ACCORDING TO ELEVATIONS SUBMITTED, THERE ARE NOT |
| CONDITIONS SHOWING A 10T TYPE OF INSTALLATION. REVISE |
| AS REQUIRED. SEC. 107.2.1 CITY AMENDMENTS TO FBC. |
| |
| 4-PERMIT APPLICATION CALL S FOR "INSTALL SHUTTERS (AND |
| REMOVABLE)" . PLEASE CLARIFY HOW ACHIEVING THIS. |
| ACCORDION SHUTTERS ARE TYPICALLY PERMANENT |
| INSTALLATION. SEC. 107.2.1 CITY AMENDMENTS TO FBC. |
| ***NOTE: IF REMOVABLE PANELS ARE GOING TO BE INSTALLED, |
| THEN PROVIDE PRODUCT APPROVAL (2 COPIES) AS REQUIRED BY |
| DCA RULE 9N-3. AND, PROVIDE COMPLETE INSTALLATION |
| SCHEDULE. SEC. 107.2.1 CITY AMENDMENTS TO FBC. |
| |
| IF YOU HAVE ANY QUESTIONS, PLEASE CALL |
| JULIO GOMEZ |
| COMMERCIAL COMBINATION PLANS EXAMINER |
| DEVELOPMENT SERVICES DEPARTMENT |
| (561)805-6712 |
| [email protected] |