Plan Review Details - Permit 14070113
Plan Review Stops For Permit 14070113
Review Stop B BUILDING (STRUCTURAL)
Rev No 4 Status P Date 2014-08-14 Cont ID  
Sent By jgomez Date 2014-08-14 Time 14:57 Rev Time 0.00
Received By jgomez Date 2014-08-14 Time 14:57 Sent To  
Notes
2014-08-14 14:58:51PROVISO:
 PROVIDE DRAWINGS SHOWING ROOF DRAINS REVISION AND SPECS
 FOR ROOF REPAIRS.

Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status F Date 2014-08-04 Cont ID  
Sent By jgomez Date 2014-08-04 Time 09:45 Rev Time 0.00
Received By jgomez Date 2014-08-04 Time 09:45 Sent To  
Notes
2014-08-04 10:08:27RE-ROOF BUILDING REVIEW SECOND CHECKLIST.
 CODE: 2010 FBC.
  
 1- PER MEETING WITH CONTRACTOR ON 7/14/14:
  
 EXISTING ROOF DRAINS ARE GOING TO BE REMOVED. NEED TO
 PROVIDE PLANS SHOWING COMPLIANCE WITH THE ROOF DRAINAGE
 SEC. 1503.4 OF 2010 FBC-BUILDING. ***NOTE: PERMIT
 OBTAINED BY THE GENERAL CONTRACTOR TO DO THE DAYCARE
 RENOVATION DOESN'T INCLUDE REMOVAL OF THE ROOF DRAINS
 AND DOESN'T INCLUDE THE STRUCTURAL ROOF REPAIRS. NEED
 TO PROVIDE COMPLETE DRAWINGS AND SPECIFICATIONS UNDER A
 REVISION TO PERMIT 13100594 (OR APPLY FOR NEW PERMIT)
 SHOWING THE ROOF DRAINS REMOVAL AND THE SPECIFICATIONS
 FOR THE STRUCTURAL ROOF REPAIRS. (COMMENT NOT
 ADDRESSED).
  
 2- TAS 105 REPORT SHOWS AREAS WITH "BAD DECK". PROVIDE
 COMPLETE DETAILS/ SPECIFICATIONS AS A REVISION TO
 PERMIT #13100594 OR APPLY FOR NEW PERMIT FOR DECK
 REPAIRS. SEC. 107.2.1 CITY AMENDMENTS TO FBC. (***NOTE:
 COORDINATE WITH ITEM #1 ABOVE). CONTRACTOR DOING THE
 DECK REPAIRS TO HAVE PROPER LICENSE AS REQUIRED BY SEC.
 489.113 FLORIDA STATUTES.
  
 ******ADDITIONAL COMMENTS TO ENGINEER DETAILS SUBMITTED
 FOR THE ROOF REPAIRS:
 (A) ENGINEER TO PROVIDE NAME AND LICENSE NUMBER AS
 REQUIRED BY CHAPTER 471 FLORIDA STATUTES.
  
 (B) ENGINEER TO COORDINATE ROOF DECK MATERIALS WITH THE
 PRODUCT APPROVAL AND FIELD WITHDRAWAL RESISTANCE TEST
 (TAS 105) SUBMITTED. IS IT LIGHT WEIGHT CONCRETE DECK
 OR GYPSUM DECK?. REVISE AS REQUIRED TO MATCH. SEC.
 107.2.1 CITY AMENDMENTS TO FBC.
  
  
 3- ROOF NEEDS POSITIVE DRAINAGE AS REQUIRED BY
 EXCEPTION ON SEC. 611.1 OF 2010 FBC-EXISTING BUILDING
 CODE. (COMMENT NOT ADDRESSED. COORDINATE WITH ITEM #1
 ABOVE).
  
  
 IF YOU HAVE ANY QUESTIONS, PLEASE CALL
 JULIO GOMEZ
 COMMERCIAL COMBINATION PLANS EXAMINER
 DEVELOPMENT SERVICES DEPARTMENT
 (561)805-6712
 [email protected]

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2014-07-14 Cont ID  
Sent By jgomez Date 2014-07-14 Time 14:46 Rev Time 0.00
Received By jgomez Date 2014-07-14 Time 14:46 Sent To  
Notes
2014-07-14 14:54:297/14/14
 ADDITIONAL COMMENTS AFTER MEETING WITH CONTRACTOR TO GO
 OVER COMMENTS.
  
 (1) EXISTING ROOF DRAINS ARE GOING TO BE REMOVED. NEED
 TO PROVIDE PLANS SHOWING COMPLIANCE WITH THE ROOF
 DRAINAGE SEC. 1503.4 OF 2010 FBC-BUILDING. ***NOTE:
 PERMIT OBTAINED BY THE GENERAL CONTRACTOR TO DO THE
 DAYCARE RENOVATION DOESN'T INCLUDE REMOVAL OF THE ROOF
 DRAINS AND DOESN'T INCLUDE THE STRUCTURAL ROOF REPAIRS.
 NEED TO PROVIDE COMPLETE DRAWINGS AND SPECIFICATIONS
 UNDER A REVISION TO PERMIT 13100594 OR PROVIDE COMPLETE
 INFORMATION UNDER SEPARATE BUILDING AND PLUMBING
 PERMITS.
  
  
 BELOW ARE THE ORIGINAL COMMENTS DATED 7/7/14:
  
  
 RE-ROOF BUILDING REVIEW COMMENTS.
 CODE: 2010 FBC.
  
 1- TAS 105 FASTENER WITHDRAWAL TEST REPORT SUBMITTED:
 A) ROOF SKETCH SUBMITTED DOESN'T MATCH ACTUAL ROOF DECK
 SHOWN ON THE PROPERTY APPRAISAL WEBSITE. REVISE AS
 REQUIRED. SEC. 107.2.1 CITY AMENDMENTS TO FBC AND SEC.
 10.1.9 OF TAS 105-11.
  
 B) NEED AT LEAST 3 TESTS TO BE PERFORMED IN THE CORNER
 AREA AS REQUIRED BY SEC. 8.1 OF TAS 105-11. THE FIELD
 WITHDRAWAL RESISTANCE TEST RECORDING SHEET SHOWS ONLY
 TWO TEST DONE IN THE CORNER AREA. BUT, THE ROOF SKETCH
 SHOWING THE TEST LOCATIONS ONLY SHOW ONE TEST IN THE
 CORNER AREA (TEST T-2). ALSO, TEST #4 IS NOT IN A
 CORNER AREA. REVISE EVERYTHING AS REQUIRED TO MATCH.
  
 C) IF MORE THAN 25% OF THE ROOF SYSTEM IS TO BE
 RE-ROOF, THEN, ENTIRE ROOF NEEDS TO BE RE-ROOFED. SEC.
 611.1.1 OF 2010 FBC-EXISTING BUILDING CODE. ALSO,
 NUMBER OF PULL OUT TEST SHALL BE CONDUCTED ACCORDINGLY.
 SEC. 8 OF TAS 105-11.
  
 D) CONTRACTOR SPECIFIED ON PERMIT APPLICATION RE-ROOF
 WITH TAMKO PONDING WATER SPECS. TEST NEED TO IDENTIFY
 THE PONDING WATER LOCATIONS AS REQUIRED BY SEC. 8.4 OF
 TAS 105-11.
  
 2) TAS 105 REPORT SHOWS AREAS WERE THE ROOF DECK IS
 BAD. NEED STRUCTURAL SUB-PERMIT TO PERFORM THE DECK
 REPAIRS. PROVIDE COMPLETE DETAILS/ SPECIFICATIONS FOR
 DECK REPAIRS. SEC. 107.2.1 CITY AMENDMENTS TO FBC.
 CONTRACTOR DOING THE DECK REPAIRS TO HAVE PROPER
 LICENSE AS REQUIRED BY SEC. 489.113 FLORIDA STATUTES.
  
 3- RAS 117 CALCULATIONS SUBMITTED: ENGINEER TO REVISE
 THE SPACING OF THE NAILS AT THE SIDE LAP. NEED TO MATCH
 THE SPACING SHOWING ON OPTION #3 OF PAGE 11 OF THE NOA
 12-0716.14 SUBMITTED. REVISE CALCULATIONS ACCORDINGLY.
 THIS IS REQUIRED BY SEC. 8.1 OF RAS 117.
  
 4- ROOF NEEDS POSITIVE DRAINAGE AS REQUIRED BY
 EXCEPTION ON SEC. 611.1 OF 2010 FBC-EXISTING BUILDING
 CODE.
  
 ***NOTES:
 **** MOISTURE SURVEY TEST MAY BE REQUIRED. SEE ITEM
 1(D) ABOVE.
  
 IF YOU HAVE ANY QUESTIONS, PLEASE CALL
 JULIO GOMEZ
 COMMERCIAL COMBINATION PLANS EXAMINER
 DEVELOPMENT SERVICES DEPARTMENT
 (561)805-6712

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2014-07-07 Cont ID  
Sent By jgomez Date 2014-07-07 Time 16:33 Rev Time 0.00
Received By jgomez Date 2014-07-07 Time 14:24 Sent To  
Notes
2014-07-07 16:58:37RE-ROOF BUILDING REVIEW COMMENTS.
 CODE: 2010 FBC.
  
 1- TAS 105 FASTENER WITHDRAWAL TEST REPORT SUBMITTED:
 A) ROOF SKETCH SUBMITTED DOESN'T MATCH ACTUAL ROOF DECK
 SHOWN ON THE PROPERTY APPRAISAL WEBSITE. REVISE AS
 REQUIRED. SEC. 107.2.1 CITY AMENDMENTS TO FBC AND SEC.
 10.1.9 OF TAS 105-11.
  
 B) NEED AT LEAST 3 TESTS TO BE PERFORMED IN THE CORNER
 AREA AS REQUIRED BY SEC. 8.1 OF TAS 105-11. THE FIELD
 WITHDRAWAL RESISTANCE TEST RECORDING SHEET SHOWS ONLY
 TWO TEST DONE IN THE CORNER AREA. BUT, THE ROOF SKETCH
 SHOWING THE TEST LOCATIONS ONLY SHOW ONE TEST IN THE
 CORNER AREA (TEST T-2). ALSO, TEST #4 IS NOT IN A
 CORNER AREA. REVISE EVERYTHING AS REQUIRED TO MATCH.
  
 C) IF MORE THAN 25% OF THE ROOF SYSTEM IS TO BE
 RE-ROOF, THEN, ENTIRE ROOF NEEDS TO BE RE-ROOFED. SEC.
 611.1.1 OF 2010 FBC-EXISTING BUILDING CODE. ALSO,
 NUMBER OF PULL OUT TEST SHALL BE CONDUCTED ACCORDINGLY.
 SEC. 8 OF TAS 105-11.
  
 D) CONTRACTOR SPECIFIED ON PERMIT APPLICATION RE-ROOF
 WITH TAMKO PONDING WATER SPECS. TEST NEED TO IDENTIFY
 THE PONDING WATER LOCATIONS AS REQUIRED BY SEC. 8.4 OF
 TAS 105-11.
  
 2) TAS 105 REPORT SHOWS AREAS WERE THE ROOF DECK IS
 BAD. NEED STRUCTURAL SUB-PERMIT TO PERFORM THE DECK
 REPAIRS. PROVIDE COMPLETE DETAILS/ SPECIFICATIONS FOR
 DECK REPAIRS. SEC. 107.2.1 CITY AMENDMENTS TO FBC.
 CONTRACTOR DOING THE DECK REPAIRS TO HAVE PROPER
 LICENSE AS REQUIRED BY SEC. 489.113 FLORIDA STATUTES.
  
 3- RAS 117 CALCULATIONS SUBMITTED: ENGINEER TO REVISE
 THE SPACING OF THE NAILS AT THE SIDE LAP. NEED TO MATCH
 THE SPACING SHOWING ON OPTION #3 OF PAGE 11 OF THE NOA
 12-0716.14 SUBMITTED. REVISE CALCULATIONS ACCORDINGLY.
 THIS IS REQUIRED BY SEC. 8.1 OF RAS 117.
  
 4- ROOF NEEDS POSITIVE DRAINAGE AS REQUIRED BY
 EXCEPTION ON SEC. 611.1 OF 2010 FBC-EXISTING BUILDING
 CODE.
  
 ***NOTES:
 **** MOISTURE SURVEY TEST MAY BE REQUIRED. SEE ITEM
 1(D) ABOVE.
  
 IF YOU HAVE ANY QUESTIONS, PLEASE CALL
 JULIO GOMEZ
 COMMERCIAL COMBINATION PLANS EXAMINER
 DEVELOPMENT SERVICES DEPARTMENT
 (561)805-6712

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2014-08-14 Cont ID  
Sent By jgomez Date 2014-08-14 Time 14:58 Rev Time 0.00
Received By jgomez Date 2014-08-14 Time 14:58 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2014-08-04 Cont ID  
Sent By jgomez Date 2014-08-04 Time 09:45 Rev Time 0.00
Received By jgomez Date 2014-08-04 Time 09:45 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2014-07-14 Cont ID  
Sent By jgomez Date 2014-07-14 Time 14:45 Rev Time 0.00
Received By jgomez Date 2014-07-14 Time 14:45 Sent To  
Notes
2014-07-14 14:46:017/14/14 MET W/ CONTRACTOR TO GO OVER COMMENTS. JG.

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2014-07-07 Cont ID  
Sent By jgomez Date 2014-07-07 Time 14:25 Rev Time 0.00
Received By jgomez Date 2014-07-07 Time 14:25 Sent To  
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved