Plan Review Stops For Permit 14010109 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
P |
Date |
2014-01-15 |
|
|
Cont ID |
|
Sent By |
tmoore |
Date |
2014-01-15 |
Time |
16:21 |
Rev Time |
0.00 |
Received By |
tmoore |
Date |
2014-01-15 |
Time |
16:18 |
Sent To |
|
|
Notes |
2014-01-15 16:21:01 | PASSED WITH PROVISO. | | NO DIRECT TO CONCRETE ATTACHMENT OPTION IN APPLICATION. | | IF FIELD CONDITION IS DIRECTLY TO CONCRETE, PROVIDE | | REVISED ATTACHMENT DETAIL FOR FIELD INSPECTOR. |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2014-01-15 |
|
|
Cont ID |
|
Sent By |
tmoore |
Date |
2014-01-15 |
Time |
16:23 |
Rev Time |
0.00 |
Received By |
tmoore |
Date |
2014-01-15 |
Time |
16:23 |
Sent To |
|
|
Notes |
2014-01-04 11:58:21 | TO ZONING | | |
|
|
Review Stop |
Z |
ZONING |
Rev No |
1 |
Status |
P |
Date |
2014-01-10 |
|
|
Cont ID |
|
Sent By |
avann |
Date |
2014-01-10 |
Time |
13:23 |
Rev Time |
0.00 |
Received By |
ajones |
Date |
2014-01-06 |
Time |
15:39 |
Sent To |
|
|
Notes |
2014-01-06 15:40:08 | 1/6/14 - ZONING RECEIVED. SENT TO AV FOR REVIEW. LL |
|
|
|