Plan Review Details - Permit 13100420
Plan Review Stops For Permit 13100420 |
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2013-11-01 |
|
|
Cont ID |
|
Sent By |
jwitmer |
Date |
2013-11-01 |
Time |
14:19 |
Rev Time |
0.00 |
Received By |
jwitmer |
Date |
2013-10-25 |
Time |
15:16 |
Sent To |
|
|
Notes |
2013-10-25 15:17:20 | SENT TO MECHANICAL BOX. JW |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2013-10-25 |
|
|
Cont ID |
|
Sent By |
jwitmer |
Date |
2013-10-17 |
Time |
15:16 |
Rev Time |
0.00 |
Received By |
jwitmer |
Date |
2013-10-11 |
Time |
08:42 |
Sent To |
|
|
Notes |
2013-10-12 08:43:08 | SENT TO MECHANICAL BOX |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
3 |
Status |
P |
Date |
2013-11-01 |
|
|
Cont ID |
|
Sent By |
jwitmer |
Date |
2013-11-01 |
Time |
14:19 |
Rev Time |
0.00 |
Received By |
jwitmer |
Date |
2013-11-01 |
Time |
14:19 |
Sent To |
Z |
|
Notes |
2013-11-01 14:25:44 | REVIEWED NEW REV # 1 SHEETS WITH UNITS ON ROOF OF FIRST | | FLOOR, HUNG OFF OF THE SECOND STORY SIDE WALL, NOTE | | WHEN WITHIN 10'-0" OF THE EDGE OF THE ROOF : | | PROVISO: | | 2010 FBC-B 1013.5 MECHANICAL EQUIPMENT. | | GUARDS SHALL BE PROVIDED WHERE APPLIANCES, EQUIPMENT, | | FANS, ROOF HATCH OPENINGS OR OTHER COMPONENTS THAT | | REQUIRE SERVICE ARE LOCATED WITHIN 10 FEET (3048 MM) OF | | A ROOF EDGE OR OPEN SIDE OF A WALKING SURFACE AND SUCH | | EDGE OR OPEN SIDE IS LOCATED MORE THAN 30 INCHES (762 | | MM) ABOVE THE FLOOR, ROOF OR GRADE BELOW. THE GUARD | | SHALL BE CONSTRUCTED SO AS TO PREVENT THE PASSAGE OF A | | SPHERE 21 INCHES (533 MM) IN DIAMETER. THE GUARD SHALL | | EXTEND NOT LESS THAN 30 INCHES (762 MM) BEYOND EACH END | | OF SUCH APPLIANCE, EQUIPMENT, FAN OR COMPONENT. | | | | JAMES A. WITMER CBO | | SENIOR COMMERCIAL COMBINATION PLANS EXAMINER | | TEL: 561-805-6715 | | FAX: 561-805-6676 | | E-MAIL: [email protected] |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
2 |
Status |
F |
Date |
2013-10-31 |
|
|
Cont ID |
|
Sent By |
mricard |
Date |
2013-10-31 |
Time |
15:17 |
Rev Time |
0.00 |
Received By |
mricard |
Date |
2013-10-31 |
Time |
15:17 |
Sent To |
|
|
Notes |
2013-10-31 15:18:48 | QUESTION FROM FIRST REVIEW HAVE NOT BEEN ANSWERED |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
1 |
Status |
F |
Date |
2013-10-17 |
|
|
Cont ID |
|
Sent By |
hmoser |
Date |
2013-10-17 |
Time |
11:42 |
Rev Time |
0.00 |
Received By |
hmoser |
Date |
2013-10-17 |
Time |
11:42 |
Sent To |
|
|
Notes |
2013-10-17 11:49:57 | SECOND STORY CU#2 CHECK WORK AREA AROUND UNIT AND THE | | PLACEMENT OF RAILINGS. | | SECOND FLOOR DUCT APPEARS TO BE COOLING THE EXTERIOR OF | | THE BUILDING |
|
|
Review Stop |
Z |
ZONING |
Rev No |
1 |
Status |
P |
Date |
2013-11-04 |
|
|
Cont ID |
|
Sent By |
llouie |
Date |
2013-11-04 |
Time |
17:16 |
Rev Time |
0.00 |
Received By |
llouie |
Date |
2013-11-04 |
Time |
17:16 |
Sent To |
|
|
Notes |
|
|
|
Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved |
 |
 |