Plan Review Stops For Permit 13100366 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
2 |
Status |
P |
Date |
2013-11-21 |
|
|
Cont ID |
|
Sent By |
jwitmer |
Date |
2013-11-21 |
Time |
13:17 |
Rev Time |
0.00 |
Received By |
jwitmer |
Date |
2013-11-21 |
Time |
12:30 |
Sent To |
|
|
Notes |
2013-11-15 14:10:17 | JW STAMP ONLY |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
P |
Date |
2013-10-23 |
|
|
Cont ID |
|
Sent By |
jwitmer |
Date |
2013-10-23 |
Time |
06:28 |
Rev Time |
0.00 |
Received By |
jwitmer |
Date |
2013-10-23 |
Time |
06:05 |
Sent To |
|
|
Notes |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
2 |
Status |
P |
Date |
2013-12-03 |
|
|
Cont ID |
|
Sent By |
albarran |
Date |
2013-12-03 |
Time |
10:13 |
Rev Time |
0.00 |
Received By |
albarran |
Date |
2013-12-03 |
Time |
10:02 |
Sent To |
I |
|
Notes |
2013-12-03 10:14:23 | CORRECTIONS SUBMITTED AS REQUESTED. |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
1 |
Status |
F |
Date |
2013-11-06 |
|
|
Cont ID |
|
Sent By |
albarran |
Date |
2013-11-06 |
Time |
13:30 |
Rev Time |
0.00 |
Received By |
albarran |
Date |
2013-11-06 |
Time |
13:06 |
Sent To |
I |
|
Notes |
2013-11-06 13:36:13 | THE FOLLOWING ITEMS WERE NOTED AND NEED CORRECTION FOR | | THE ELECTRICAL PLANS REVIEW. | | 1. PAGE CVR MAKES REFERENCE TO NEC 2005 RATHER THAN THE | | 2008 NOW IN EFFECT. | | 2. THE LIGHTING CONTROL DIAGRAM DOES NOT MEET | | FBC-ENERGY CONSERVATION. NO OVER RIDE PROVISIONS | | INDICATED. | | 3. THOUGH THE RISER DIAGRAMS SHOW THE TRANSFORMER, IT | | DOES NOT APPEAR ON THE FLOOR PLANS | | 4. THE ELECTRICAL RISER DIAGRAM SHOWN ON PAGE E@ DOES | | NOT MATCH THE ON SHOWN ON PAGE E3. | | | | PLEASE CORRECT THE ABOVE MENTIONED DEFICIENCIES AND | | RESUBMIT FOR REVIEW. | | | | SENT TO SH DESK |
|
|
Review Stop |
FIRE |
FIRE DEPARTMENT |
Rev No |
2 |
Status |
P |
Date |
2013-11-19 |
|
|
Cont ID |
|
Sent By |
scaldero |
Date |
2013-11-19 |
Time |
15:23 |
Rev Time |
0.00 |
Received By |
scaldero |
Date |
2013-11-19 |
Time |
15:23 |
Sent To |
|
|
Notes |
2013-11-15 14:11:46 | TO STAMP ONLY PG CVR |
|
|
Review Stop |
FIRE |
FIRE DEPARTMENT |
Rev No |
1 |
Status |
P |
Date |
2013-10-23 |
|
|
Cont ID |
|
Sent By |
scaldero |
Date |
2013-10-23 |
Time |
16:45 |
Rev Time |
0.00 |
Received By |
scaldero |
Date |
2013-10-23 |
Time |
16:45 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2013-12-03 |
|
|
Cont ID |
|
Sent By |
skennedy |
Date |
2013-12-03 |
Time |
11:03 |
Rev Time |
0.00 |
Received By |
skennedy |
Date |
2013-11-15 |
Time |
14:12 |
Sent To |
|
|
Notes |
2013-12-03 10:14:52 | SENT TO SK FOR PROCESSING | 2013-11-15 16:28:59 | B11 |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2013-11-06 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2013-11-06 |
Time |
17:35 |
Rev Time |
0.00 |
Received By |
shill |
Date |
2013-10-10 |
Time |
11:29 |
Sent To |
|
|
Notes |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
2 |
Status |
P |
Date |
2013-10-31 |
|
|
Cont ID |
|
Sent By |
mricard |
Date |
2013-10-31 |
Time |
13:33 |
Rev Time |
0.00 |
Received By |
mricard |
Date |
2013-10-31 |
Time |
13:33 |
Sent To |
|
|
Notes |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
1 |
Status |
F |
Date |
2013-10-25 |
|
|
Cont ID |
|
Sent By |
mricard |
Date |
2013-10-25 |
Time |
08:13 |
Rev Time |
0.00 |
Received By |
mricard |
Date |
2013-10-25 |
Time |
08:06 |
Sent To |
|
|
Notes |
2013-10-25 08:21:02 | PROVIDE ENERGY CALC,S FOR THE SPACE IN QUESTION. | | INCLUDE CONDENSATE AND HANGING DETAILS |
|
|