Plan Review Stops For Permit 11100336
Review Stop ENG ENGINEERING CSD
Rev No 1 Status P Date 2011-10-21 Cont ID  
Sent By BRM Date 2011-10-21 Time 07:44 Rev Time  
Received By bmoree Date 2011-10-21 Time   Sent To Z
Notes
2011-10-21 07:48:30DRIVEWAY MUST BE CONSTRUCTION FROM MATERIAL APPROVED BY
 THE CITY. THE PLAN DOES NOT SPECIFY THE CONSTRUCTION
 MATERIAL (CONCRETE, PAVER BRICK, ETC.)
 PRE-POUR INSPECTION REQUIRED.

Review Stop Z ZONING
Rev No 1 Status P Date 2011-10-21 Cont ID  
Sent By ajones Date 2011-10-21 Time 08:18 Rev Time 0.00
Received By ajones Date 2011-10-21 Time 08:18 Sent To  
Notes
***NONE***