Plan Review Details - Permit 10100268
Plan Review Stops For Permit 10100268
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2010-10-26 Cont ID  
Sent By jwitmer Date 2010-10-26 Time 10:24 Rev Time 0.55
Received By jwitmer Date 2010-10-26 Time 10:24 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2010-10-19 Cont ID  
Sent By shill Date 2010-10-19 Time 18:02 Rev Time 0.00
Received By shill Date 2010-10-19 Time 18:02 Sent To  
Notes
2010-10-19 18:03:39OK PER JOHN DICKINSON CONTRACT PLAN REVIEWER LICENSE
 NUMBER PX3182

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2010-10-19 Cont ID  
Sent By mcarsill Date 2010-10-19 Time 13:20 Rev Time 0.00
Received By mcarsill Date 2010-10-19 Time 13:20 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2010-11-17 Cont ID  
Sent By shill Date 2010-11-17 Time 10:54 Rev Time 0.00
Received By shill Date 2010-10-13 Time 09:05 Sent To  
Notes
2010-10-14 09:06:11B-11

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2010-11-02 Cont ID  
Sent By hmoser Date 2010-11-02 Time 10:11 Rev Time 0.00
Received By hmoser Date 2010-11-02 Time 10:11 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status P Date 2010-10-22 Cont ID  
Sent By lwagner Date 2010-10-22 Time 10:38 Rev Time 0.00
Received By lwagner Date 2010-10-22 Time 09:08 Sent To  
Notes
2010-10-22 10:20:18*******PROVISO*****
  
 504.6 REQUIREMENTS FOR DISCHARGE PIPING. THE DISCHARGE
 PIPING SERVING A PRESSURE RELIEF VALVE, TEMPERATURE
 RELIEF VALVE OR COMBINATION THEREOF SHALL:
  
 1. NOT BE DIRECTLY CONNECTED TO THE DRAINAGE SYSTEM.
 2. DISCHARGE THROUGH AN AIR GAP LOCATED IN THE SAME
 ROOM AS THE WATER HEATER.
 3. NOT BE SMALLER THAN THE DIAMETER OF THE OUTLET OF
 THE VALVE SERVED AND SHALL DISCHARGE FULL SIZE TO THE
 AIR GAP.
 4. SERVE A SINGLE RELIEF DEVICE AND SHALL NOT CONNECT
 TO PIPING SERVING ANY OTHER RELIEF DEVICE OR EQUIPMENT.
 5. DISCHARGE TO THE FLOOR, TO THE WATER HEATER PAN, TO
 AN INDIRECT WASTE RECEPTOR OR TO THE OUTDOORS. WHERE
 DISCHARGING TO THE OUTDOORS IN AREAS SUBJECT TO
 FREEZING, DISCHARGE PIPING SHALL BE FIRST PIPED TO AN
 INDIRECT WASTE RECEPTOR THROUGH AN AIR GAP LOCATED IN A
 CONDITIONED AREA.
 6. DISCHARGE IN A MANNER THAT DOES NOT CAUSE PERSONAL
 INJURY OR STRUCTURAL DAMAGE.
 7. DISCHARGE TO A TERMINATION POINT THAT IS READILY
 OBSERVABLE BY THE BUILDING OCCUPANTS.
 8. NOT BE TRAPPED.
 9. BE INSTALLED SO AS TO FLOW BY GRAVITY.
 10. NOT TERMINATE MORE THAN 6 INCHES (152 MM) ABOVE THE
 FLOOR OR WASTE RECEPTOR.
 11. NOT HAVE A THREADED CONNECTION AT THE END OF SUCH
 PIPING.
 12. NOT HAVE VALVES OR TEE FITTINGS.
 13. BE CONSTRUCTED OF THOSE MATERIALS LISTED IN SECTION
 605.4 OR MATERIALS TESTED, RATED AND APPROVED FOR SUCH
 USE IN ACCORDANCE WITH ASME A112.4.1.
  

Review Stop Z ZONING
Rev No 1 Status N Date 2010-11-15 Cont ID  
Sent By aaponte Date 2010-11-15 Time 15:17 Rev Time 0.00
Received By aaponte Date 2010-11-15 Time 15:17 Sent To  
Notes
2010-11-15 15:42:20CLEMATIS STREET IS A REQUIRED RETAIL FRONTAGE. IF A
 COMBINED RETAIL/ NO RETAIL BUSINESS IS OCCUPYING THE
 CLEMATIS STREET FRONTAGE, THE MERCHANDISE OR FOOD SALES
 SHALL REPRESENT A MINIMUM OF 50 PERCENT OF BUSINESS
 REVENUE. PLEASE ENSURE YOU COMPLY WITH THIS
 REQUIREMENT.


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved