Plan Review Details - Permit 10030787
Plan Review Stops For Permit 10030787
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2010-04-05 Cont ID  
Sent By shill Date 2010-04-05 Time 17:38 Rev Time 0.00
Received By shill Date 2010-04-05 Time 17:13 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2010-04-07 Cont ID  
Sent By btrobaug Date 2010-04-07 Time 07:43 Rev Time 0.00
Received By btrobaug Date 2010-04-07 Time 07:36 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2010-04-08 Cont ID  
Sent By mawillia Date 2010-04-08 Time 14:21 Rev Time 0.00
Received By mawillia Date 2010-04-08 Time 14:00 Sent To  
Notes
2010-04-08 14:22:48*****APPROVED*****
  
 PLAN SHEETS A2.1, A3.1, E1, AND E2 WERE STAMPED,
 INITIALED, AND DATED.

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2010-04-09 Cont ID  
Sent By hmoser Date 2010-04-09 Time 07:40 Rev Time 0.00
Received By hmoser Date 2010-03-31 Time 14:12 Sent To  
Notes
2010-04-04 14:13:05*****************EXPEDITED*****************
 B--16

Review Stop IMPACT COUNTY IMPACT FEES
Rev No 1 Status N Date 2010-04-08 Cont ID  
Sent By shill Date 2010-04-08 Time 18:18 Rev Time 0.00
Received By shill Date 2010-04-08 Time 18:18 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2010-04-09 Cont ID  
Sent By hmoser Date 2010-04-09 Time 07:40 Rev Time 0.00
Received By hmoser Date 2010-04-09 Time 07:09 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status P Date 2010-04-06 Cont ID  
Sent By lwagner Date 2010-04-05 Time 15:48 Rev Time 0.00
Received By lwagner Date 2010-04-05 Time 15:38 Sent To  
Notes
2010-04-05 15:48:13PLUMBING PERMIT REQUIRED.