Plan Review Details - Permit 09090659
Plan Review Stops For Permit 09090659
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2009-11-10 Cont ID  
Sent By shill Date 2009-11-10 Time 11:46 Rev Time 0.00
Received By shill Date 2009-11-10 Time 11:46 Sent To  
Notes
2009-11-10 11:47:52PROVISO - CONTRACTOR APPLICATION REQUIRED
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2009-10-20 Cont ID  
Sent By shill Date 2009-10-20 Time 16:16 Rev Time 0.00
Received By shill Date 2009-10-20 Time 16:16 Sent To  
Notes
2009-10-20 16:30:35****CORRECTIONS****
  
 SAMANTHA HILL, BUILDING PLANS EXAMINER
 561-805-6724 [email protected]
  
 FBC FLORIDA BUILDING CODE 2007 WITH 2009 SUPPLEMENTS
 FBC EB FLORIDA BUILDING CODE 2007 EXISTING BUILDING
 CODE
 FBC R FLORIDA BUILDING CODE 2007 RESIDENTIAL
 FBC* CITY OF WEST PALM BEACH AMENDMENTS TO THE FBC2004
 FAC FLORIDA ADMINISTRATIVE CODE
 FS FLORIDA STATUTE
  
 1. PLEASE EXPLAIN, PLANS STATE THAT IMPERVIOUS AREA IS
 12,551. THE APPLICATION STATES THAT THE IMPROVEMENT
 AREA IS 5,000SF. PLEASE REVISE SO THAT APPLICATION
 MATCHES THE PLANS.
  
 2. FBC11-4.6.2, IN BUILDINGS WITH MULTIPLE ACCESSIBLE
 ENTRANCES WITH ADJACENT PARKING, ACCESSIBLE PARKING
 SPACES ARE TO BE DISPERSED. PARKING SERVING A
 PARTICULAR BUILDING SHALL BE LOCATED ON THE SHORTEST
 SAFELY ACCESSIBLE ROUTE OF TRAVEL FROM ADJACENT PARKING
 TO AN ACCESSIBLE ENTRANCE.
  
 SEE SOUTH PARKING. IT APPEARS THAT TWO OF THE FOUR
 ACCESSIBLE PARKING SPACES SHOULD BE LOCATED NEAR THE
 BANK SOUTH ENTRANCE. PLEASE EITHER EXPLAIN HOW HAVING
 THE FOUR SPACES TOGETHER COMPLIES WITH THE TWO ABOVE
 REQUIREMENTS OR REVISE THE PLAN TO HAVE TWO ACCESSIBLE
 SPACES NEAR THE BANK ENTRANCE. PLEASE FEEL FREE TO
 CONTACT ME TO DISCUSS.
  
 3. PLEASE HAVE A CONTRACTOR LICENSED TO PERFORM THIS
 WORK APPLY FOR PERMIT.
  
  
  
  

Review Stop ENG ENGINEERING CSD
Rev No 2 Status P Date 2009-10-27 Cont ID  
Sent By mgonzale Date 2009-10-27 Time 15:55 Rev Time 1.00
Received By mgonzale Date 2009-10-27 Time 15:55 Sent To  
Notes
2009-10-27 16:02:09PASSED - WITH PROVISO
  
 ENGINEERING HAS REQUIRED THE APPLICANT TO PROCEED WITH
 SUBMISSION AND PERMITTING THRU
 ENGINEERING SERVICES 4TH FLOOR.
  
 THIS INCLUDES THE FIRELINE TAP AND ROW CONSTRUCTION.
 DCDA LOCATION WILL BE COORDINATED WITH PLANNING.
  
 MANUEL JULIAN GONZALEZ
 CSD ENGINEERING REVIEW
 401 CLEMATIS STREET, 1ST FLOOR
 WEST PALM BEACH, FL 33401
 (MAILING ADDRESS: P.O. BOX 3366, ZIP 33402)
 MAIN PHONE: (561) 822-1200
 DIRECT: (561) 494-1085
 FAX: (561) 494-1116
 MOBILE: (561) 644-7301
 EMAIL: [email protected]
 WWW.WPB.ORG/ENGINEERING
  
  
  
  
  
  
  

Review Stop ENG ENGINEERING CSD
Rev No 1 Status F Date 2009-10-14 Cont ID  
Sent By mgonzale Date 2009-10-14 Time   Rev Time 1.00
Received By mgonzale Date 2009-10-14 Time   Sent To  
Notes
2009-10-14 14:31:28FAILED - PLANS HAVE NOT BEEN APPROVED THRU ENGINEERING
 DEPT.
 ENGINEERING IS CURRENTLY IN RECEPIT OF THESE PLANS AND
 IS REVIWEING.
  
 MANUEL JULIAN GONZALEZ
 ENGINEERING REVIEW
 CONSTRUCTION SERVICES DEPARTMENT
 401 CLEMATIS STREET, 1ST FLOOR
 WEST PALM BEACH, FL 33401
 (MAILING ADDRESS: P.O. BOX 3366, ZIP 33402)
 MAIN PHONE: (561) 822-1200
 DIRECT: (561) 494-1085
 FAX: (561) 494-1116
 MOBILE: (561) 644-7301
 EMAIL: [email protected]
 WWW.WPB.ORG/ENGINEERING
  
  
  

Review Stop ENG-F ENGINEERING FINAL DRAWING REV
Rev No 1 Status P Date 2009-11-03 Cont ID  
Sent By efabian Date 2009-11-03 Time 11:21 Rev Time 0.50
Received By efabian Date 2009-11-03 Time 11:20 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2009-11-02 Cont ID  
Sent By lmartine Date 2009-10-29 Time 16:47 Rev Time 0.00
Received By lmartine Date 2009-10-29 Time 16:47 Sent To  
Notes
2009-11-02 16:52:49C--11

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2009-10-20 Cont ID  
Sent By shill Date 2009-10-20 Time 16:30 Rev Time 0.00
Received By shill Date 2009-09-29 Time 08:37 Sent To  
Notes
2009-10-01 08:37:46TO ZONING BOX

Review Stop L LANDSCAPING
Rev No 2 Status P Date 2009-11-04 Cont ID  
Sent By rkussner Date 2009-11-04 Time 15:26 Rev Time 0.00
Received By rkussner Date 2009-11-04 Time 15:26 Sent To  
Notes
2009-11-04 15:50:29***LANDSCAPE APPROVED WITH PROVISO***---(NOTES WERE
 PLACED ON LANDSCAPE PLANS)
  
 1. THE SIX (6) PROPOSED LAUREL OAKS IN THE PALM BEACH
 LAKES RRIGHT-OF-WAY SHALL BE CHANGED TO LIVE OAKS.
  
 2. THE PROPOSED DUMPSTER CHAINLINK FENCE GATES WITH
 SLATS SHALL BE CHANGED TO BOARD ON BOARD WOOD FENCING
 ATTACHED TO STEEL POLES AND FRAMING.
  
 3. NO TREES OR PLANT MATERIAL SHALL BE PLANTED IN THE 2
 FOOT VEHICLE OVERHANG AREA.
  
 IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT ROBERT
 KUSSNER @ (561) 822-1462.

Review Stop L LANDSCAPING
Rev No 1 Status F Date 2009-10-06 Cont ID  
Sent By rkussner Date 2009-10-06 Time 14:14 Rev Time 0.00
Received By rkussner Date 2009-10-06 Time 14:14 Sent To  
Notes
2009-10-06 15:26:32***LANDSCAPE FINAL INSPECTION FAILED***
  
 PLEASE PROVIDE RESPONSES TO REVIEW COMMENTS IN WRITTEN
 FORMAT.
  
 1. PURSUANT TO SECTION 94-443 (C)(3)(A&B)), TERMINAL
 AND INTERIOR LANDSCAPE ISLANDS SHALL BE NOT LESS THAN
 FIVE (5) FEET IN WIDTH, EXCLUDING THE REQUIRED CURBING.
 THOUGH THE ISLANDS APPEAR TO SCALE AT SIX (6) FEET
 (OUTSIDE WIDTH WITH FIVE (5) FOOT INSIDE DIMENSION),
 THE DETAIL PROVIDED AND THE DESCRIPTION IS INCORRECT.
  
 2. PLEASE PROVIDE A CERTIFIED COST ESTIMATE THAT
 INCLUDES THE TOTAL COST OF ALL LANDSCAPE MATERIALS AND
 LABOR, BROKEN DOWN INTO UNIT COST. THE COST ESTIMATE
 SUBMITTED IS NOT SUFFICIENT TO MEET THIS REQUIREMENT.
  
 3. THE PROPOSED HEDGE IN THE PALM BEACH LAKES BOULEVARD
 RIGHT-OF-WAY SHALL EXTEND UP TO THE DRIVEWAY.
  
 4. PURSUANT TO SECTION 94-443 (C)(2), SHADE TREES SHALL
 BE PLANTED AT 30-FOOT INTERVALS ALONG THE LANDSCAPE
 STRIP THAT SEPARATES THE VEHICULAR USE AREA FROM THE
 ADJACENT RIGHT-OF-WAY (PALM BEACH LAKES BOULEVARD).
 TREES ARE REQUIRED TO BE PLANTED ALONG THE HEDGEROW ON
 THE EAST SIDE OF THE SITE.
  
 5. SUBMIT A TREE ALTERATION PERMIT APPLICATION FOR THE
 TREES THAT ARE SCHEDULED TO BE REMOVED. THE EXISTING
 FISHTAIL AND LADY PALMS IN THE COURTYARD ARE TOO
 VALUABLE TO BE DESTROYED. PERHAPS THEY CAN BE RELOCATED
 TO THE PROPOSED LOCATIONS OF THE FOXTAIL PALMS.
 OTHERWISE, THEY WILL NEED TO FIND A NEW HOME SOMEWHERE
 ON SITE.
  
 6. THE PROPOSED LAUREL OAKS DO NOT HAVE A HIGH SUCCESS
 RATE IN PAVED PARKING LOTS. THEY LIKE A GREAT DEAL OF
 WATER AND ARE FOUND NATURALLY IN LOWLYING AREAS.. IN
 ADDITION, THEY ARE SHORT-LIVED AS COMPARED TO OTHER
 SHADE TREES. LIVE OAKS WOULD BE A MUCH BETTER CHOICE
 FOR THE INTENDED LOCATIONS AND WILL BE CONSISTENT WITH
 WHAT HAS ALREADY BEEN PLANTED ELSEWHERE ON SITE.
  
 7. PURSUANT TO SECTION 94-444 (B), THE DUMPSTER
 ENCLOSURE SHALL HAVE VISION OBSCURING GATES. IF A
 GENERATOR IS PROPOSED, IT SHALL BE SHOWN ON THE PLAN.
 THE GAS EQUIPMENT AT THE SOUTHWEST CORNER OF THE
 BUILDING IS IN A DANGEROUS LOCATION. THAT SHALL BE
 PROTECTED AND ALL EQUIPMENT SHALL BE SCREENED. STAFF
 SUGGESTS THAT THE CURBED LANDSCAPE ISLAND NORTH OF THE
 GAS EQUIPMENT BE EXPANDED TO ENCOMPASS THE EQUIPMENT
 AND EXTEND UP TO THE 24 FOOT TRAVEL AISLE. ADDITIONAL
 PLANTING SHALL BE ADDED WITHIN THE ISLAND THAT WILL
 PROVIDE SCREENING AND OFFER SOME PROTECTION.
  
 8. NO TREES OR SHRUBS SHALL BE PLANTED WITHIN THE
 TWO-FOOT VEHICULAR OVERHANG AREA ADJACENT TO ROBINS
 DRIVE.
  
 IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT ROBERT
 KUSSNER @ (561) 822-1462.
  

Review Stop P PLUMBING
Rev No 1 Status N Date 2010-05-12 Cont ID  
Sent By lwagner Date 2010-05-12 Time 08:10 Rev Time 0.00
Received By lwagner Date 2010-05-12 Time 08:10 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 2 Status P Date 2009-11-10 Cont ID  
Sent By eschneid Date 2009-11-10 Time 10:32 Rev Time 1.00
Received By eschneid Date 2009-11-10 Time 10:32 Sent To  
Notes
2009-11-10 10:34:10PASSED W/PROVISOS
  
 1) BIGGER LANDSCAPE ISLAND AT SOUTH TIP.
  
 2) RESTRIPE PARKING AT SOUTH TIP.
  
 3) MOVE QV 5 FEET FROM SIDEWALK.

Review Stop Z ZONING
Rev No 1 Status F Date 2009-10-13 Cont ID  
Sent By eschneid Date 2009-10-13 Time 19:03 Rev Time 0.50
Received By eschneid Date 2009-10-13 Time 19:03 Sent To ENG
Notes
2009-10-13 19:12:53FAILED
  
 PLEASE RESPOND TO COMMENTS IN WRITING
  
 1) ADDRESS ALL LANDSCAPE REVIEWER COMMENTS.
  
 2) A RIGHT-OF-WAY PERMIT FROM THE CITY'S ENGINEERING
 SERVICES DEPARTMENT IS REQUIRED FOR THE HEDGE AND TREES
 IN PALM BEACH LAKES BOULEVARD RIGHT-OF-WAY. PLEASE
 PROVIDE A COPY OF THE RIGHT-OF-WAY PERMIT.
  
 3) PROVIDE A NOTE THAT STATES THAT THE LANDSCAPE IN THE
 PALM BEACH LAKES RIGHT-OF-WAY WILL BE INSTALLED PER THE
 APPROVED RIGHT-OF-WAY PERMIT.
  
 4) PLEASE VERIFY YOUR DIMENSIONS. SOME SCALE CORRECTLY,
 SOME DO NOT. NOTABLY ALONG THE PARKING AISLES BY THE
 SERVICE ROAD.
  
 5) PROVIDE A SURVEY.
  
 6) PROVIDE A NOTE THAT THE NEW CURB IN FRONT OF 2007
 PALM BEACH LAKES WILL BE PAINTED RED WITH "FIRE LANE,
 NO PARKING".
  
 7) PLEASE EXAMINE THE POSSIBILITY OF A PALMS IN THE
 TERMINAL ISLAND ADJACENT TO THE DUMPSTER ENCLOSURE.
  
 8) DUMPSTER OPENING SHALL BE 12 FOOT 6 INCHES UNLESS
 OTHERWISE APPROVED BY THE ENGINEERING SERVICES
 DEPARTMENT.
  
 9) THE PROPOSED GENERATOR IS NOT SHOWN. PLEASE PROVIDE
 HOW THIS WILL LAY OUT. NOTE THE COMMENTS MADE IN THE
 LANDSCAPE REVIEW.
  
 10) WHERE IS THE FLAG POLE BEING INSTALLED?
  
 CONTACT ERIC SCHNEIDER @ (561) 822-1446.