Plan Review Stops For Permit 08030410 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
P |
Date |
2008-03-18 |
|
|
Cont ID |
|
Sent By |
amorse |
Date |
2008-03-18 |
Time |
15:42 |
Rev Time |
0.00 |
Received By |
amorse |
Date |
2008-03-18 |
Time |
15:42 |
Sent To |
PC |
|
Notes |
2008-03-18 15:51:15 | | | PASSED | | | | 1)SHUTTER INSTALLATION: FASTENERS FOR FILLED CELL | | BLOCK-WORK-CONTRACTOR CANNOT ASSUME THAT THERE IS A | | CONCRETE SUBSTRATE WHEN SELECTING FASTENERS (AND | | SPACING) UNLESS THEY CAN PROVIDE DOCUMENTATION TO | | VERIFY COMPRESSIVE STRENGTH OF 3,000 PSI, OR 3,500 PSI, | | ETC, AND THE REQUIRED FASTENER EMBEDMENT DEPTH,AS | | REQUIRED ON THE PRODUCT APPROVAL. IF DOCUMENTATION IS | | NOT PROVIDED THE SUBSTRATE SHALL BE CONSIDERED MASONRY | | AND THE O/C SPACING SHALL BE ADJUSTED ACCORDINGLY. | | | | BLDG PLAN REVIEW | | ADRIAN MORSE | | 561-805-6716 |
|
|
|