2006-09-20 00:00:00 | ******DENIED****** |
| REFERENCE: FBC-2004 FUEL GAS |
| |
| THE FOLLOWING INFORMATION IS REQUIRED |
| FOR GAS PLAN REVIEW: |
| |
| ******IMPORTANT INFORMATION****** |
| AS OF 8/25/06 GENERATOR (GEN/RES AND |
| GEN/COM) PERMIT APPLICATIONS SHALL NOT |
| BE ACCEPTED UNLESS THE ELECTRICAL INFOR- |
| MATION AND GAS (OR DIESEL) INFORMATION |
| IS ALL SUBMITTED AT THE SAME TIME. THE |
| GENERATOR, ELECTRICAL AND GAS/DIESEL IN- |
| FORMATION WILL BE ROUTED TOGETHER. THIS |
| WILL ENSURE THAT ALL OF THE INFORMATION |
| (PARTICULARLY THE MANUFACTURER'S SPECI- |
| FICATIONS AND INSTALLATION INSTRUCTIONS) |
| ARE AVAILABLE TO ALL PLAN REVIEWERS. |
| |
| CONTRACTOR INFORMATION |
| NOTE: GAS PERMIT REQUIRED. GAS CONTRAC- |
| TOR TO SUBMIT PLANS WITH PERMIT APPLICA- |
| TION. ALL GAS INSPECTIONS TO BE COMPLETE |
| BEFORE FINAL GEN/RES INSPECTION. |
| |
| 1. SUBMIT AN ISOMETRIC DRAWING THAT |
| CLEARLY SHOWS ALL CUT SECTIONS OF PIPE |
| AND CORRESPONDING LENGTHS PER FBC-2004 |
| FUEL GAS CODE. |
| 2. SHOW TYPE OF PIPING MATERIAL BEING |
| INSTALLED, ALL PIPE SIZES, (AND THE EDH |
| NUMBER OF CORRUGATED STAINLESS STEEL |
| TUBING FOR EACH PIPE SIZE BEING USED. |
| 3. TYPE OF GAS, (LP OR NATURAL) |
| 4. BTU LOAD OF EACH APPLIANCE AND THE |
| TOTAL BTU LOAD ON THE SYSTEM. REFER TO |
| THE FBC-2004 FUEL GAS CODE SECS. 401.8 |
| THRU 402.6.1 AND TABLES 402.4(1) THRU |
| 402.4(33). |
| 5. SHOW THE DISTANCE FROM THE POINT OF |
| DELIVERY, (METER), TO THE MOST REMOTE |
| OUTLET IN THE BUILDING AND/OR SYSTEM PER |
| FBC-2004 FUEL GAS CODE APPENDIX A - USE |
| OF CAPACITY TABLES A.3.1(4). |
| 6. SUBMIT CALCULATIONS FOR COMBUSTION |
| AIR (IF APPLICABLE) PER FBC-2004 FUEL |
| GAS CODE SECTION 304. |
| 7. INDICATE THE DELIVERY PRESSURE (PSI) |
| PER FBC-2004 FUEL GAS CODE SEC. 402.2. |
| NATURAL GAS SPECIFY .5 PSI OR 2 PSI. |
| 8. SUBMIT A DETAIL SHOWING THE TYPE, |
| LOCATION, SIZE AND TERMINATION OF THE |
| GAS VENTS PER FBC-2004 FUEL GAS CODE |
| SECS. 502 THRU 505. (IF APPLICABLE) |
| 9. SUBMIT MANUFACTURE SHEETS FOR ALL GAS |
| EQUIPMENT TO VERIFY COMPLIANCE WITH |
| STANDARDS NFPA 54, NFPA 58, AND THE |
| FBC-2004 FUEL GAS CODE SEC 402.2 |
| (NOTE: THIS INCLUDES THE MANUFACTURER |
| INSTALLATION INSTRUCTIONS TO VERIFY |
| CLEARENCES.) |
| 10. CLEARLY SHOW THE LOCATION AND CAP- |
| ACITY OF LP TANK(S), TYPE OF TANK (DOT |
| OR ASME), THE DISTANCE OF THE TANK FROM |
| THE BUILDING AND ADJACENT PROPERTY LINES |
| THE DISTANCE OF THE TANK FROM ALL SOUR- |
| CES OF IGNITION, OTHER CONTAINERS, BUILD |
| INGS, AND THE LOCATION OF ANY BUILDING |
| OPENINGS BELOW THE RELIEF VALVE OF THE |
| TANK PER NFPA 58, TABLE 3-2.2.2. |
| 11. CLEARLY INDICATE ON THE PLAN IF THE |
| LP TANK IS ABOVE OR BELOW GROUND, AND |
| SHOW REQUIRED PROTECTION OF THE TANK AND |
| APPURTENANCES PER NFPA 58. IF THE TANK |
| IS BELOW GROUND THE CONTAINER SHALL BE |
| SECURILY ANCHORED PER NFPA 58 SECTION |
| 3-2.2.7(H). |
| |
| END OF COMMENTS: |
| |
| REVIEW BY MIKE PERSON |
| (561) 805-6730 |
| FAX (561) 805-6731 |
| E-MAIL [email protected] |
| UNDER SUPERVISION OF K.STEVENS |
| (561) 805-6721 |
| |
| |
| |
| |
| |
| |