Plan Review Details - Permit 06051215
Plan Review Stops For Permit 06051215
Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2006-08-01 Cont ID  
Sent By adarroug Date 2006-08-01 Time 16:28 Rev Time 0.00
Received By adarroug Date 2006-08-01 Time 16:28 Sent To M
Notes
2006-08-01 00:00:00TO "M" BOX/REV

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2006-07-17 Cont ID  
Sent By tgordon Date 2006-07-17 Time 14:17 Rev Time 0.00
Received By tgordon Date 2006-07-14 Time 18:43 Sent To  
Notes
2006-07-14 00:00:00TO "M" BOX/SUBMITTAL

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2006-08-10 Cont ID  
Sent By tgordon Date 2006-08-10 Time 10:20 Rev Time 0.20
Received By tgordon Date 2006-08-10 Time 10:20 Sent To  
Notes
2006-08-10 00:00:00*** PROVISO ***
 1) THE DWELLING WILL BE REQUIRED TO HAVE
 SMOKE ALARMS INSTALLED IF NOT ALREADY
 PRESENT, PER 2004 FBC/R 313.1.1, AND SEE
 2004 FEBC 303.1 LEVEL ONE ALTERATION
 INCLUDE REPLACEMENT OF EQUIPMENT.
 MECHANICAL PLAN REVIEW BY;
 TOM GORDON (561) 805-6729.

Review Stop M MECHANICAL (A/C)
Rev No 1 Status F Date 2006-07-17 Cont ID  
Sent By tgordon Date 2006-07-17 Time 14:05 Rev Time 0.30
Received By tgordon Date 2006-07-17 Time 14:05 Sent To  
Notes
2006-07-17 00:00:00*** DENIED ***
 1) PROVIDE RETURN AIR TO BEDROOMS AND
 SHOW HOW RETURN AIR IS GETTING BACK TO
 AIR HANDLER. SEE NOTE #5.
  
 2) ADJUST JOB VALUE ON PERMIT
 APPLICATION AS ORIGINAL VALUE WAS JUST
 FOR THE EQUIPMENT CHANGE OUT AND NO DUCT
 WORK.
  
 3) PLEASE SHOW EQUIPMENT LISTING ON
 PLANS.
  
 4) ALL INFORMATION, DRAWINGS,
 SPECIFICATIONS AND ACCOMPANYING DATA
 SHALL BEAR THE NAME AND SIGNATURE OF THE
 PERSON RESPONSIBLE FOR THE DESIGN. PER
 FBC 104.2.1 .
  
 5) BALANCED RETURN AIR.
 THIS MAY BE ACHIEVED BY.
 (A)TRANSFER DUCTS MAY ACHIEVE THIS BY
 INCREASING THE RETURN TRANSFER ONE AND
 ONE HALF TIMES THE CROSS SECTIONAL AREA
 (SQUARE INCHES) OF THE SUPPLY DUCT
 ENTERING THE ROOM OR SPACE IT'S SERVING
 AND THE DOOR HAVING AT LEAST AN
 UNRESTRICTED 1 INCHUNDERCUT TO ACHIEVE
 PROPER RETURN AIR BALANCE.
 (B)TRANSFER GRILLES SHALL USE 50
 SQUARE INCHES (OF GRILLE AREA) TO 100
 CFM (OF SUPPLY AIR) FOR SIZING
 THROUGH-THE-WALL TRANSFER GRILLES AND
 USING AN UNRESTRICTED 1-INCH
 UNDERCUTTING OF DOORS TO ACHIEVE PROPER
 RETURN AIR BALANCE
 (C)HABITABLE ROOMS ONLY SHALL BE
 REQUIRED TO MEET THESE REQUIREMENTS FOR
 PROPER BALANCED RETURN AIR EXCLUDING
 BATHROOMS, CLOSETS, STORAGE ROOMS AND
 LAUNDRY ROOMS, EXCEPT THAT ALL SUPPLY
 AIR INTO THE MASTER SUITE SHALL BE
 INCLUDED. PER 2004 FBC/R M1602.4 .
  
 MECHANICAL PLAN REVIEW BY;
 TOM GORDON (561) 805-6729.
  