Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2005-04-06 Cont ID  
Sent By adarroug Date 2005-04-06 Time 14:24 Rev Time 0.00
Received By adarroug Date 2005-04-06 Time 14:24 Sent To P
Notes
2005-04-06 00:00:00TO "KSTEVENS" BOX/RESUB

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2005-03-17 Cont ID  
Sent By adarroug Date 2005-03-17 Time 14:37 Rev Time 0.00
Received By adarroug Date 2005-03-17 Time 14:37 Sent To P
Notes
2005-03-17 00:00:00TO "P" BOX

Review Stop P PLUMBING
Rev No 2 Status P Date 2005-04-19 Cont ID  
Sent By kstevens Date 2005-04-19 Time 16:37 Rev Time 1.50
Received By kstevens Date 2005-04-19 Time 16:37 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status F Date 2005-03-26 Cont ID  
Sent By kstevens Date 2005-03-26 Time 15:45 Rev Time 0.60
Received By kstevens Date 2005-03-26 Time 15:45 Sent To B
Notes
2005-03-26 00:00:00DENIED
 REFERENCE: FBC-2001 PLUMBING
 FBC-2001 CHAPTER 1
  
 1) APPLICATION DOES NOT MENTION
 REPLACING THE DECK THAT WILL BE CUT UP
 FOR THE PIPING WORK. PLEASE INDICATE IF
 A SEPARATE PERMIT WILL BE APPLIED FOR TO
 REPLACE THE DECK. - IF THE DECK IS TO BE
 REPLACED ON THIS PERMIT, THAN THE VALUE
 OF THE JOB IS NOT CORRECT. SUBMIT A
 SIGNED & DATED COPY OF THE CONTRACT, AND
 THE WORK WILL BE CHECKED OUT BY MARSHALL
 AND SWIFT AS PER SECTIO 104.6.5.
 2) FBC-2001 424.2.12.1 PRESSURE TESTS.
 PER MANUFACTURE RECOMMENDATIONS, NO AIR
 TEST SHALL BE APPROVED FOR PVC PIPE AND
 FITTINGS. (ADD TO NOTES)
 3) FBC-2001 424.2.13.2 JOINTS AND
 CONNEDTIONS, FBC PLUMBING SECTION 605.21
 PURPLE PRIMER REQUIRED ON PVC PIPING AND
 FITTINGS. (ADD TO NOTES)
  
 REVIEW BY KEN STEVENS