Review Stop B BUILDING (STRUCTURAL)
Rev No 4 Status P Date 2006-01-17 Cont ID  
Sent By amorse Date 2006-01-17 Time 08:29 Rev Time 0.50
Received By amorse Date 2006-01-17 Time 08:29 Sent To PC
Notes
2006-01-17 00:00:00 
  
 RESTAMP WITH NEW CONTRACTOR
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status F Date 2005-12-02 Cont ID  
Sent By amorse Date 2005-12-02 Time 10:52 Rev Time 1.00
Received By amorse Date 2005-12-02 Time 10:52 Sent To PC
Notes
2005-12-02 00:00:00DENIED
  
  
  
  
 1) PERMIT CANNOT BE RESTAMPED WHEN IT
 DOES NOT MATCH THE INFORMATION ON FILE,
 IT MUST BE A REVISION. THE FOLLOWING
 INFORMATION HAS CHANGED.
  
 1A) CONTRACTOR IS NOT THE SAME, SUBMIT A
 LETTER ON OLD CONTRACTORS LETTERHEAD
 THAT THEY ARE RELEASING THE JOB,PERMIT,
 FEES,ETC. TO THE NEW CONTRACTOR.
  
 1B) ENGINEERED BEAM SIZES AND SPANS WERE
 CHANGED. A NEW REVISION MUST BE
 SUBMITTED THAT WILL MEET THE NEW PBC
 POST 2004 HURRICANE SEASON UPDATED
 ENGINEERING SPECIFICATIONS
  
 1C) A NOTICE OF COMMENCEMENT WAS NOT
 SUMITTED. THIS MUST BE SUPPLIED BEFORE
 A REVISED PEMIT CAN BE ISSUED
  
  
 BLDG PLAN REVIEW
 ADRIAN MORSE
 (561)805-6716

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2005-04-21 Cont ID  
Sent By lsmith Date 2005-04-21 Time 13:48 Rev Time 0.25
Received By lsmith Date 2005-04-21 Time 13:48 Sent To  
Notes
2005-04-21 00:00:00BUILDING PLAN REVIEW: FAILED
  
  
 DRAWINGS ARE PHOTO COPIES WITHOUT
 ENGINEERS SIGNATURE & RAISED SEAL.
 ONLY NEED TO SUBMIT 1 COPY FOR DUPLICATE
  
  
 ANY QUESTIONS PLEASE CALL:
 LEA SMITH, BUILDING PLANS EXAMINER
 805-6713

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2004-11-10 Cont ID  
Sent By lsmith Date 2004-11-10 Time 16:05 Rev Time 0.75
Received By lsmith Date 2004-11-10 Time 16:05 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2006-01-13 Cont ID  
Sent By adarroug Date 2006-01-13 Time 16:55 Rev Time 0.00
Received By adarroug Date 2006-01-13 Time 16:55 Sent To B
Notes
2006-01-13 00:00:00TO "AMORSE" DESK/RESTAMP

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2005-10-17 Cont ID  
Sent By adarroug Date 2005-10-17 Time 16:28 Rev Time 0.00
Received By adarroug Date 2005-10-17 Time 16:28 Sent To B
Notes
2005-10-17 00:00:00TO "LMARTINEZ" DESK/RESTAMP

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2004-11-10 Cont ID  
Sent By csiegber Date 2004-11-10 Time 14:41 Rev Time 0.00
Received By csiegber Date 2004-11-10 Time 14:41 Sent To B
Notes
2004-11-10 00:00:00TO MISC BOX

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2004-11-04 Cont ID  
Sent By csiegber Date 2004-11-04 Time 10:27 Rev Time 0.00
Received By csiegber Date 2004-11-04 Time 10:27 Sent To Z
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2004-11-10 Cont ID  
Sent By mmclean Date 2004-11-10 Time 12:28 Rev Time 0.00
Received By mmclean Date 2004-11-10 Time 12:22 Sent To I
Notes
***NONE***