Plan Review Stops For Permit 04100472 |
Review Stop |
ENG |
ENGINEERING CSD |
Rev No |
1 |
Status |
P |
Date |
2004-10-29 |
|
|
Cont ID |
|
Sent By |
mamini |
Date |
2004-10-29 |
Time |
09:58 |
Rev Time |
1.00 |
Received By |
mamini |
Date |
2004-10-29 |
Time |
09:58 |
Sent To |
P |
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
4 |
Status |
N |
Date |
2004-12-03 |
|
|
Cont ID |
|
Sent By |
mjacobs |
Date |
2004-12-03 |
Time |
08:07 |
Rev Time |
0.00 |
Received By |
mjacobs |
Date |
2004-12-03 |
Time |
08:06 |
Sent To |
P |
|
Notes |
2004-12-03 00:00:00 | SENT TO "P" BOX./RESUB |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
3 |
Status |
N |
Date |
2004-11-24 |
|
|
Cont ID |
|
Sent By |
mjacobs |
Date |
2004-11-24 |
Time |
10:18 |
Rev Time |
0.00 |
Received By |
mjacobs |
Date |
2004-11-24 |
Time |
10:10 |
Sent To |
Z |
|
Notes |
2004-11-24 00:00:00 | PLANS P/U BY ERIC SCHNEIDER "Z" 5TH FL |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2004-10-27 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2004-10-27 |
Time |
15:06 |
Rev Time |
0.00 |
Received By |
csiegber |
Date |
2004-10-27 |
Time |
15:06 |
Sent To |
ENG |
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2004-10-14 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2004-10-14 |
Time |
14:27 |
Rev Time |
0.00 |
Received By |
csiegber |
Date |
2004-10-14 |
Time |
14:27 |
Sent To |
Z |
|
Notes |
|
|
Review Stop |
L |
LANDSCAPING |
Rev No |
2 |
Status |
N |
Date |
2004-12-15 |
|
|
Cont ID |
|
Sent By |
kstevens |
Date |
2004-12-15 |
Time |
05:38 |
Rev Time |
0.00 |
Received By |
kstevens |
Date |
2004-12-15 |
Time |
05:37 |
Sent To |
|
|
Notes |
2004-12-15 00:00:00 | SEE ZONING STOP FOR ES APPROVAL |
|
|
Review Stop |
L |
LANDSCAPING |
Rev No |
1 |
Status |
F |
Date |
2004-10-27 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2004-10-27 |
Time |
15:06 |
Rev Time |
0.00 |
Received By |
csiegber |
Date |
2004-10-27 |
Time |
15:06 |
Sent To |
I |
|
Notes |
2004-10-27 00:00:00 | ES FAILED |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
2 |
Status |
P |
Date |
2004-12-15 |
|
|
Cont ID |
|
Sent By |
kstevens |
Date |
2004-12-15 |
Time |
05:35 |
Rev Time |
0.75 |
Received By |
kstevens |
Date |
2004-12-15 |
Time |
05:35 |
Sent To |
|
|
Notes |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
1 |
Status |
F |
Date |
2004-11-01 |
|
|
Cont ID |
|
Sent By |
mamini |
Date |
2004-10-29 |
Time |
09:59 |
Rev Time |
1.00 |
Received By |
kstevens |
Date |
2004-11-01 |
Time |
07:42 |
Sent To |
|
|
Notes |
2004-11-01 00:00:00 | DENIED | | REFERENCE: FBC-2001 CHAPTER 1 | | | | !) LOCATION OF METER, BACKFLOW (BY | | PLUMBING CONTRACTOR), CONTROLLER, AND | | RAINSWITCH ARE REQUIRED ON PLANS FOR | | REVIEW. SECTION 104.2.1 | | | | | | REVIEW BY KEN STEVENS | | (561) 805-6721 | | FAX (561) 653-2692 | | E-MAIL [email protected] |
|
|
Review Stop |
Z |
ZONING |
Rev No |
2 |
Status |
P |
Date |
2004-12-02 |
|
|
Cont ID |
|
Sent By |
eschneid |
Date |
2004-12-02 |
Time |
13:42 |
Rev Time |
1.00 |
Received By |
eschneid |
Date |
2004-12-02 |
Time |
12:41 |
Sent To |
|
|
Notes |
2004-12-02 00:00:00 | GIVEN TO INCOMING |
|
|
Review Stop |
Z |
ZONING |
Rev No |
1 |
Status |
F |
Date |
2004-11-01 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2004-10-14 |
Time |
14:27 |
Rev Time |
0.75 |
Received By |
eschneid |
Date |
2004-10-27 |
Time |
13:15 |
Sent To |
|
|
Notes |
2004-10-27 00:00:00 | CRAVEN THOMPSON PLANS MUST CORRECTLY | | SHOW A/C UNIT FOR BLDG 10. | | LANDSCAPE PLANS - CR (CROTON) MUST BE | | 24 INCHES HIGH AT PLANTING WHERE USED AS | | HEDGE ALONG WALLS IN THE PARKING COURTS. | | HEDGE REQUIRED ALONG L STREET FRONTAGE. | | MOVE TREES/PALMS ALONG L ST AWAY FROM | | WALL/BLDG TO ALLOW FOR ADEQUATE PLANTING | | AND GROWTH. | | SV (SCHEFFLERA) IS USED AS HEDGE MUST BE | | 24" HIGH AT PLANTING. | | CONTACT ERIC SCHNEIDER @ 822-1435 |
|
|