Plan Review Details - Permit 04041673
Plan Review Stops For Permit 04041673
Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2004-10-13 Cont ID  
Sent By jgomez Date 2004-10-13 Time 07:48 Rev Time 0.33
Received By jgomez Date 2004-10-13 Time 07:48 Sent To PC
Notes
2004-10-13 00:00:00GARAGE DOOR PRODUCT APPROVAL.

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2004-07-19 Cont ID  
Sent By csiegber Date 2004-08-30 Time 10:03 Rev Time 0.33
Received By jgomez Date 2004-07-19 Time 10:44 Sent To PC
Notes
2004-07-19 00:00:001-PROVIDE COPIES OF GARAGE DOOR DRAWINGS
 SUBMITTED TO SBCCI FOR APPROVAL. NEED
 DRAWINGS SIGNED AND SEALED ON DATE
 NOTED ON SBCCI EVALUATION REPORT.
 2-FLOOD ZONE REVISION IS OK.
  
 IF YOU HAVE ANY QUESTIONS, PLEASE CALL
 JULIO GOMEZ AT 805-6712.

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2004-05-19 Cont ID  
Sent By csiegber Date 2004-06-22 Time 14:35 Rev Time 1.00
Received By jgomez Date 2004-05-19 Time 15:42 Sent To PC
Notes
2004-05-19 00:00:00BUILDING REVIEW PROVISO:
 1-PROVIDE COPIES OF GARAGE DOOR DRAWINGS
 WITH ENGINEER'S DATE OF SEALING AND
 SIGNING AS NOTED ON SBCCI EVALUATION
 REPORT.
 2-FLOOD ZONE AO: NEED TO PROVIDE THE
 ELEVATION CERTIFICATE.

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2004-05-06 Cont ID  
Sent By dpalmer Date 2004-05-06 Time 07:09 Rev Time 0.25
Received By dpalmer Date 2004-05-06 Time 07:07 Sent To M
Notes
2004-05-06 00:00:00******** NOTES/PROVISO **********
  
 1)NOTE: PLEASE SEE 220.19 FOR MIN LOAD
 FOR RANGE. 8KW
  
 2)NOTE: MAX LOAD FOR 1-P20A CIRCUIT IS
 1.9KW. WASHER/ IRRG PUMP.
  
 SD'S TO BE INSTALLED PER NFPA-72 8-1.4.2
  
  
 DEWEY PALMER
 ELECTRICAL PLAN REVIEW
 561-805-6717

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2004-08-30 Cont ID  
Sent By csiegber Date 2004-08-30 Time 10:03 Rev Time 0.00
Received By csiegber Date 2004-08-30 Time 10:03 Sent To B
Notes
2004-08-30 00:00:00TO JG DESK/SUBMITTALS/NEW PA'S

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2004-06-22 Cont ID  
Sent By csiegber Date 2004-06-22 Time 14:35 Rev Time 0.00
Received By csiegber Date 2004-06-22 Time 14:35 Sent To B
Notes
2004-06-22 00:00:00TO JG DESK/REV

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2004-05-19 Cont ID  
Sent By mmclean Date 2004-04-28 Time 12:39 Rev Time 0.00
Received By jgomez Date 2004-04-26 Time 13:32 Sent To PC
Notes
2004-04-29 00:00:00TO SFD RACK/E
2004-04-26 00:00:00TO Z

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2004-05-10 Cont ID  
Sent By dpalmer Date 2004-05-06 Time 07:10 Rev Time 0.30
Received By pkrauss Date 2004-05-10 Time 16:43 Sent To P
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status P Date 2004-05-18 Cont ID  
Sent By pkrauss Date 2004-05-10 Time 16:43 Rev Time 0.33
Received By kstevens Date 2004-05-18 Time 18:13 Sent To B
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2004-04-28 Cont ID  
Sent By mmclean Date 2004-04-28 Time 12:39 Rev Time 0.00
Received By mmclean Date 2004-04-28 Time 12:39 Sent To I
Notes
***NONE***