Plan Review Stops For Permit 04041307 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
2 |
Status |
P |
Date |
2004-05-20 |
|
|
Cont ID |
|
Sent By |
mmclean |
Date |
2004-05-24 |
Time |
12:10 |
Rev Time |
0.50 |
Received By |
lsmith |
Date |
2004-05-20 |
Time |
07:39 |
Sent To |
|
|
Notes |
2004-05-20 00:00:00 | PROVISO:PROVIDE CONTRACT TO VERIFY | | VALUE. |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
P |
Date |
2004-05-06 |
|
|
Cont ID |
|
Sent By |
dpalmer |
Date |
2004-05-03 |
Time |
17:46 |
Rev Time |
0.75 |
Received By |
lsmith |
Date |
2004-05-06 |
Time |
13:53 |
Sent To |
|
|
Notes |
2004-05-06 00:00:00 | CONTRACT SUBMITTED SHOWS VALUE OF | | $15000MARSHALL & SWIFT PROJECTED COST | | IS $26,000. PERMIT FEES ARE TO BE BASED | | ON TOTAL VALUE OF THE CONTRACT PER FBC |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
2 |
Status |
P |
Date |
2004-05-18 |
|
|
Cont ID |
|
Sent By |
dpalmer |
Date |
2004-05-18 |
Time |
18:43 |
Rev Time |
0.25 |
Received By |
dpalmer |
Date |
2004-05-18 |
Time |
18:38 |
Sent To |
P |
|
Notes |
2004-05-18 00:00:00 | ORIG PACKAGE DID NOT COME BACK. | | NEW SITE PLAN, DUPLICATE PERMIT APPL. | | ETC. | | SEND TO ALL TADES, INCLUDING ZONING. |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
1 |
Status |
F |
Date |
2004-05-03 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2004-05-18 |
Time |
15:45 |
Rev Time |
0.25 |
Received By |
dpalmer |
Date |
2004-05-03 |
Time |
17:46 |
Sent To |
B |
|
Notes |
2004-05-03 00:00:00 | *** UNSAT *** | | | | 1)NOTE: PLEASE CORRELATE WIRING DIAGRAM | | WITH EQIPMENT SCHEDULE. | | | | 2)NOTE: PLEASE SEE BLDG COMMENTS FOR | | VALUATION OF POOL AND APPLIED VALUE | | PER FBC 104.6.5. | | | | PLEASE SUBMIT THE ABOVE INFORMATION FOR | | REVIEW. IF THERE ARE ANY QUESTIONS, | | PLEASE DO NOT HESITATE TO CALL. | | | | DEWEY PALMER | | ELECTRICAL PLAN REVIEW | | CITY OF WEST PALM BEACH | | CONSTUCTION SERVICES DEPT. | | 561-805-6717 | | [email protected] |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
3 |
Status |
N |
Date |
2004-05-18 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2004-05-18 |
Time |
15:45 |
Rev Time |
0.00 |
Received By |
csiegber |
Date |
2004-05-18 |
Time |
15:45 |
Sent To |
E |
|
Notes |
2004-05-18 00:00:00 | TO DP DESK/RESUB |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2004-04-22 |
|
|
Cont ID |
|
Sent By |
alange |
Date |
2004-04-22 |
Time |
14:02 |
Rev Time |
0.00 |
Received By |
alange |
Date |
2004-04-22 |
Time |
14:02 |
Sent To |
P |
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2004-04-20 |
|
|
Cont ID |
|
Sent By |
mmclean |
Date |
2004-04-21 |
Time |
08:47 |
Rev Time |
0.00 |
Received By |
csiegber |
Date |
2004-04-20 |
Time |
08:43 |
Sent To |
Z |
|
Notes |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
2 |
Status |
P |
Date |
2004-05-25 |
|
|
Cont ID |
|
Sent By |
dpalmer |
Date |
2004-05-18 |
Time |
18:43 |
Rev Time |
1.50 |
Received By |
kstevens |
Date |
2004-05-25 |
Time |
09:05 |
Sent To |
|
|
Notes |
2004-05-25 00:00:00 | BACKFLOW SHALL BE INSTALLED AND INSPECT- | | ED PRIOR TO COMMENCING WORK ON POOL |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
1 |
Status |
P |
Date |
2004-05-03 |
|
|
Cont ID |
|
Sent By |
alange |
Date |
2004-04-22 |
Time |
14:02 |
Rev Time |
1.00 |
Received By |
pschmitz |
Date |
|
Time |
|
Sent To |
E |
|
Notes |
2004-05-03 00:00:00 | SEPERATE PERMIT FOR NAT GAS. | | BACK FLOW PREVENTER PRIOR TO COMMENCING | | WORK.PES |
|
|
Review Stop |
Z |
ZONING |
Rev No |
2 |
Status |
P |
Date |
2004-05-24 |
|
|
Cont ID |
|
Sent By |
mmclean |
Date |
2004-05-24 |
Time |
12:10 |
Rev Time |
0.00 |
Received By |
mmclean |
Date |
2004-05-24 |
Time |
12:10 |
Sent To |
B |
|
Notes |
2004-05-24 00:00:00 | RESUB/REV APPROVED AND GIVEN TO LOU | | MARTINEZ MM |
|
|
Review Stop |
Z |
ZONING |
Rev No |
1 |
Status |
P |
Date |
2004-04-21 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2004-04-20 |
Time |
08:43 |
Rev Time |
0.00 |
Received By |
mmclean |
Date |
2004-04-21 |
Time |
08:47 |
Sent To |
I |
|
Notes |
|
|