Review Stop B BUILDING (STRUCTURAL)
Rev No 4 Status P Date 2004-09-21 Cont ID  
Sent By jgomez Date 2004-09-21 Time 16:36 Rev Time 0.33
Received By jgomez Date 2004-09-21 Time 16:36 Sent To PC
Notes
2004-09-21 00:00:00GARAGE DOOR PRODUCT APPROVAL.

Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2004-06-04 Cont ID  
Sent By csiegber Date 2004-08-30 Time 10:12 Rev Time 1.00
Received By jgomez Date 2004-06-04 Time 17:54 Sent To PC
Notes
2004-06-04 00:00:00BUILDING REVIEW PROVISO:
 1-GARAGE DOORS PRODUCT APPROVAL: PROVIDE
 COMPLETE PACKAGE FOR DOOR MODEL TO BE
 INSTALLED IN THIS PROJECT.

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2004-05-24 Cont ID  
Sent By csiegber Date 2004-05-27 Time 16:46 Rev Time 0.33
Received By jgomez Date 2004-05-24 Time 14:08 Sent To PC
Notes
2004-05-24 00:00:00CHECKLIST:
 1-IMPACT FEES RECEIPT NUMBER DOESN'T
 MATCH NUMBER STAMPED ON PLANS.
 2-PROVIDE COPIES OF GARAGE DOOR DWGS
 THAT WERE SUBMITTED TO SBCCI FOR
 APPROVAL. NEED DWGS THAT WERE SIGNED
 AND SEALED ON DATE NOTED ON SBCCI
 EVALUATION REPORT.

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2004-05-06 Cont ID  
Sent By csiegber Date 2004-05-21 Time 09:22 Rev Time 1.00
Received By jgomez Date 2004-05-06 Time 17:20 Sent To PC
Notes
2004-05-06 00:00:00CHECKLIST:
 1-NEED IMPACT FEES PAID RECEIPT THAT
 MATCHES STAMPED PLANS PR NUMBER.
 2-ONLY ONE COPY OF PRODUCT APPROVAL FOR
 ENTRY DOOR AND "SIMONTON" DOORS AND
 WINDOWS WAS SUBMITTED. NEED ADDITIONAL
 COPY.
 3-NEED NOTICE OF COMMENCEMENT.

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2004-04-16 Cont ID  
Sent By dpalmer Date 2004-04-16 Time 15:27 Rev Time 0.25
Received By dpalmer Date 2004-04-16 Time 15:12 Sent To M
Notes
2004-04-16 00:00:00REDLINED SD'S TO BE INSTALLED PER
 NFPA-72 8-1.4.2

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2004-08-30 Cont ID  
Sent By csiegber Date 2004-08-30 Time 10:12 Rev Time 0.00
Received By csiegber Date 2004-08-30 Time 10:12 Sent To B
Notes
2004-08-30 00:00:00TO JG DESK/SUBMITTALS/NEW PA'S

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2004-05-27 Cont ID  
Sent By csiegber Date 2004-05-27 Time 16:46 Rev Time 0.00
Received By csiegber Date 2004-05-27 Time 16:46 Sent To B
Notes
2004-05-27 00:00:00TO JG DESK/RESUB

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2004-05-21 Cont ID  
Sent By csiegber Date 2004-05-21 Time 09:22 Rev Time 0.00
Received By csiegber Date 2004-05-21 Time 09:22 Sent To B
Notes
2004-05-21 00:00:00TO JG DESK/RESUB

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2004-05-06 Cont ID  
Sent By mmclean Date 2004-04-15 Time 11:46 Rev Time 0.00
Received By jgomez Date 2004-04-13 Time 12:30 Sent To PC
Notes
2004-04-15 00:00:00TO SFD RACK/E
2004-04-13 00:00:00TO Z

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2004-04-26 Cont ID  
Sent By dpalmer Date 2004-04-16 Time 15:27 Rev Time 0.30
Received By pkrauss Date 2004-04-26 Time 08:55 Sent To P
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status P Date 2004-05-03 Cont ID  
Sent By pkrauss Date 2004-04-26 Time 08:55 Rev Time 0.25
Received By jleech Date 2004-05-03 Time 18:48 Sent To B
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2004-04-15 Cont ID  
Sent By mmclean Date 2004-04-15 Time 11:46 Rev Time 0.00
Received By mmclean Date 2004-04-15 Time 11:46 Sent To I
Notes
***NONE***