Plan Review Stops For Permit 04031380 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
3 |
Status |
P |
Date |
2004-08-26 |
|
|
Cont ID |
|
Sent By |
jgomez |
Date |
2004-08-26 |
Time |
12:02 |
Rev Time |
0.33 |
Received By |
jgomez |
Date |
2004-08-26 |
Time |
12:02 |
Sent To |
PC |
|
Notes |
2004-08-26 00:00:00 | GARAGE DOOR. |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
2 |
Status |
F |
Date |
2004-06-28 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2004-07-29 |
Time |
14:38 |
Rev Time |
0.50 |
Received By |
jgomez |
Date |
2004-06-28 |
Time |
09:59 |
Sent To |
PC |
|
Notes |
2004-06-28 00:00:00 | 1-FLOOD ZONE REVISION OK. | | 2-PROVIDE COPIES OF GARAGE DOOR DRAWINGS | | SUBMITTED TO SBCCI FOR APPROVAL. NEED | | DRWINGS SIGNED AND SEALED ON DATE AS | | NOTED ON SBCCI EVALUATION REPORT. | | | | IF YOU HAVE ANY QUESTIONS, PLEASE CALL | | JULIO GOMEZ AT 805-6712. |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
P |
Date |
2004-04-20 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2004-06-22 |
Time |
14:44 |
Rev Time |
1.00 |
Received By |
jgomez |
Date |
2004-04-20 |
Time |
17:39 |
Sent To |
PC |
|
Notes |
2004-04-20 00:00:00 | BUILDING REVIEW PROVISO: | | 1-PROVIDE 2 COPIES OF SOIL TEST REPORT. | | 2-FLOOD ZONE AO: NEED THE ELEVATION | | CERTIFICATE. |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
1 |
Status |
P |
Date |
2004-04-08 |
|
|
Cont ID |
|
Sent By |
alange |
Date |
2004-03-29 |
Time |
14:53 |
Rev Time |
0.45 |
Received By |
jleahy |
Date |
2004-04-08 |
Time |
10:17 |
Sent To |
M |
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
5 |
Status |
N |
Date |
2004-08-20 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2004-08-20 |
Time |
14:44 |
Rev Time |
0.00 |
Received By |
csiegber |
Date |
2004-08-20 |
Time |
14:44 |
Sent To |
M |
|
Notes |
2004-08-20 00:00:00 | TO PK BOX/REV |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
4 |
Status |
N |
Date |
2004-07-29 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2004-07-29 |
Time |
14:38 |
Rev Time |
0.00 |
Received By |
csiegber |
Date |
2004-07-29 |
Time |
14:38 |
Sent To |
B |
|
Notes |
2004-07-29 00:00:00 | TO JG DESK/NEW PROVISO |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
3 |
Status |
N |
Date |
2004-06-22 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2004-06-22 |
Time |
14:43 |
Rev Time |
0.00 |
Received By |
csiegber |
Date |
2004-06-22 |
Time |
14:43 |
Sent To |
B |
|
Notes |
2004-06-22 00:00:00 | TO JG DESK/REV |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2004-03-29 |
|
|
Cont ID |
|
Sent By |
alange |
Date |
2004-03-29 |
Time |
14:53 |
Rev Time |
0.00 |
Received By |
alange |
Date |
2004-03-29 |
Time |
14:53 |
Sent To |
E |
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2004-04-20 |
|
|
Cont ID |
|
Sent By |
mmclean |
Date |
2004-03-26 |
Time |
15:34 |
Rev Time |
0.00 |
Received By |
jgomez |
Date |
2004-03-25 |
Time |
17:02 |
Sent To |
PC |
|
Notes |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
2 |
Status |
P |
Date |
2004-09-14 |
|
|
Cont ID |
|
Sent By |
pkrauss |
Date |
2004-09-14 |
Time |
14:03 |
Rev Time |
0.25 |
Received By |
pkrauss |
Date |
2004-09-14 |
Time |
14:03 |
Sent To |
|
|
Notes |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
1 |
Status |
P |
Date |
2004-04-12 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2004-08-20 |
Time |
14:44 |
Rev Time |
0.25 |
Received By |
hmoser |
Date |
2004-04-12 |
Time |
16:52 |
Sent To |
P |
|
Notes |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
1 |
Status |
P |
Date |
2004-04-12 |
|
|
Cont ID |
|
Sent By |
hmoser |
Date |
2004-04-12 |
Time |
16:52 |
Rev Time |
0.25 |
Received By |
jleech |
Date |
2004-04-12 |
Time |
19:49 |
Sent To |
B |
|
Notes |
|
|
Review Stop |
Z |
ZONING |
Rev No |
1 |
Status |
P |
Date |
2004-03-26 |
|
|
Cont ID |
|
Sent By |
mmclean |
Date |
2004-03-26 |
Time |
15:34 |
Rev Time |
0.00 |
Received By |
mmclean |
Date |
2004-03-26 |
Time |
15:33 |
Sent To |
I |
|
Notes |
|
|