Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2004-02-09 Cont ID  
Sent By csiegber Date 2004-02-27 Time 12:29 Rev Time 1.00
Received By jgomez Date 2004-02-09 Time 14:04 Sent To PC
Notes
2004-02-09 00:00:00BUILDING REVIEW APPROVED WITH PROVISO:
 1-PROVIDE COMPLETE CURRENT PRODUCT APPRO
 VAL FOR ALL DOORS, WINDOWS, MULLIONS,
 GLASS BLOCK, ROOF TILE AND ALL
 STRUCTURAL CONNECTORS UNDER A SEPARATE
 PERMIT AS REQ'D BY BUILDING OFFICIAL.
 2-DETAIL E/4 AND RESIDENTIAL NOTES ON
 DWG #2 DON'T MATCH. REVISE AS REQUIRED
 3-CLARIFY/REVISE TRUSS ANCHOR SCHEDULE.
 4-TYPICAL WALL SECTION DETAIL A/4:
 CLARIFY WHERE ARE TABLES 6 & 8 TAKEN
 FROM? SEE SEC. 1606.3 FBC 2001 & SEC.
 104.2.1.1 CITY AMENDMENTS TO FBC 2001.
 5-SHEET #7: A)REVISE/CLARIFY DESING PRE-
 SSURES ON EXTERIOR ELEVATION OPENINGS.
 B)WINDOWS SHOWN ON ELEVATION DON'T MATCH
 WINDOW SCHEDULE.
 C)REVISE ALL NOTES ON FLOOR PLAN & ROOF
 PLAN TO REFLECT CHANGE OF BEAM.
  
 6-SHEET #3: CLARIFY NOTE REGARDING THE
 UPLIFT CALCS AND CONNECTORS SELECTED.

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2004-01-09 Cont ID  
Sent By dpalmer Date 2004-01-09 Time 06:19 Rev Time 0.33
Received By dpalmer Date 2004-01-09 Time 06:19 Sent To M
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2004-02-27 Cont ID  
Sent By csiegber Date 2004-02-27 Time 12:28 Rev Time 0.00
Received By csiegber Date 2004-02-27 Time 12:28 Sent To B
Notes
2004-02-27 00:00:00TO JG DESK/SUBMITTALS

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2004-02-11 Cont ID  
Sent By csiegber Date 2004-02-11 Time 16:06 Rev Time 0.00
Received By csiegber Date 2004-02-11 Time 16:06 Sent To B
Notes
2004-02-11 00:00:00TO JG DESK/SUBMITTAL

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2004-02-09 Cont ID  
Sent By jgomez Date 2004-02-09 Time 14:41 Rev Time 0.00
Received By jgomez Date 2004-01-06 Time 13:40 Sent To PC
Notes
2004-01-20 00:00:00TO KS BOX
2004-01-06 00:00:00TO Z
 TO E/DP

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2004-01-22 Cont ID  
Sent By dpalmer Date 2004-01-09 Time 06:19 Rev Time 0.25
Received By pkrauss Date 2004-01-22 Time 15:35 Sent To B
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status P Date 2004-01-22 Cont ID  
Sent By kstevens Date 2004-01-22 Time 15:41 Rev Time 0.33
Received By kstevens Date 2004-01-22 Time 15:40 Sent To B
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2004-01-06 Cont ID  
Sent By mmclean Date 2004-01-06 Time 12:38 Rev Time 0.00
Received By mmclean Date 2004-01-06 Time 12:38 Sent To I
Notes
***NONE***