Plan Review Stops For Permit 03072407 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
3 |
Status |
P |
Date |
2004-03-05 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2004-03-05 |
Time |
09:44 |
Rev Time |
0.50 |
Received By |
shill |
Date |
2004-03-05 |
Time |
09:44 |
Sent To |
|
|
Notes |
2004-03-05 00:00:00 | REVISED A5 DATED 2/20/04 |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
2 |
Status |
P |
Date |
2003-09-17 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2004-02-20 |
Time |
11:31 |
Rev Time |
1.00 |
Received By |
sthyng |
Date |
2003-09-17 |
Time |
13:50 |
Sent To |
|
|
Notes |
2003-09-17 00:00:00 | PROVISO | | SEP PERMIT FOR SHUTTERS | | SUBMIT REVISION FOR A1 |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
F |
Date |
2003-08-20 |
|
|
Cont ID |
|
Sent By |
kstevens |
Date |
2003-09-06 |
Time |
12:52 |
Rev Time |
2.00 |
Received By |
sthyng |
Date |
2003-08-20 |
Time |
12:28 |
Sent To |
|
|
Notes |
2003-08-20 00:00:00 | *****CORRECTIONS****** | | | | SAMANTHA THYNG, BUILDING PLANS EXAMINER | | [email protected] | | | | 1.)ADDITIONAL FEES DUE, $20.56. | | | | 2.)PROVIDE A SOILS INVESTIGATION | | REPORT. | | | | 3.)DETAILS 5-A5, 12-A5, SEMCO | | ATTACHMENTS NO LONGER AVAILABLE. REVISE. | | | | 4.)NAILING FOR THE USP CONNECTORS | | CONFLICT WITH THE USP 2003 CATALOG. | | CHECK ALL ATTACHMENTS. | | | | 5.)DETAIL 38-A1, BOTTOM OF FOUNDATION | | TO BE A MINIMUM OF 12" BELOW GRADE, | | FBC1804.1.3. | | | | 6.)PROVIDE TWO PRODUCT APPROVALS FOR | | ALL GLAZING, SHUTTERS, ROOF, MULLIONS, | | DOORS.ANY PRODUCT APPROVALS NOT | | SUBMITTED WILL REQUIRE A SEPARATE | | PERMIT. | | | | 7.)PROVIDE A HURRICANE SHUTTER | | ATTACHMENT, OR APPLY FOR A SEPARATE | | PERMIT. |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
2 |
Status |
|
Date |
|
|
|
Cont ID |
|
Sent By |
|
Date |
|
Time |
|
Rev Time |
0.15 |
Received By |
jleahy |
Date |
2004-05-05 |
Time |
10:35 |
Sent To |
|
|
Notes |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
1 |
Status |
P |
Date |
2003-08-13 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2004-05-03 |
Time |
13:44 |
Rev Time |
0.51 |
Received By |
dpalmer |
Date |
2003-08-13 |
Time |
12:13 |
Sent To |
M |
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
5 |
Status |
N |
Date |
2004-05-03 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2004-05-03 |
Time |
13:44 |
Rev Time |
0.00 |
Received By |
csiegber |
Date |
2004-05-03 |
Time |
13:44 |
Sent To |
E |
|
Notes |
2004-05-03 00:00:00 | TO DP DESK/REV |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
4 |
Status |
N |
Date |
2004-02-20 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2004-02-20 |
Time |
11:31 |
Rev Time |
0.00 |
Received By |
csiegber |
Date |
2004-02-20 |
Time |
11:31 |
Sent To |
B |
|
Notes |
2004-02-20 00:00:00 | TO SH DESK/REV |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
3 |
Status |
N |
Date |
2003-08-27 |
|
|
Cont ID |
|
Sent By |
dbaxter |
Date |
2003-08-27 |
Time |
13:49 |
Rev Time |
0.00 |
Received By |
dbaxter |
Date |
2003-08-27 |
Time |
13:49 |
Sent To |
P |
|
Notes |
2003-08-27 00:00:00 | TO JLEECH DESK. |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2003-08-05 |
|
|
Cont ID |
|
Sent By |
alange |
Date |
2003-08-05 |
Time |
13:18 |
Rev Time |
0.00 |
Received By |
alange |
Date |
2003-08-05 |
Time |
13:17 |
Sent To |
E |
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2003-07-31 |
|
|
Cont ID |
|
Sent By |
alange |
Date |
2003-07-31 |
Time |
13:09 |
Rev Time |
0.00 |
Received By |
alange |
Date |
2003-07-31 |
Time |
13:09 |
Sent To |
Z |
|
Notes |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
2 |
Status |
P |
Date |
2004-04-05 |
|
|
Cont ID |
|
Sent By |
pkrauss |
Date |
2004-04-05 |
Time |
07:48 |
Rev Time |
0.20 |
Received By |
pkrauss |
Date |
2004-04-05 |
Time |
07:48 |
Sent To |
|
|
Notes |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
1 |
Status |
P |
Date |
2003-08-19 |
|
|
Cont ID |
|
Sent By |
dpalmer |
Date |
2003-08-13 |
Time |
12:13 |
Rev Time |
0.25 |
Received By |
pkrauss |
Date |
2003-08-19 |
Time |
10:49 |
Sent To |
P |
|
Notes |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
2 |
Status |
P |
Date |
2003-09-06 |
|
|
Cont ID |
|
Sent By |
kstevens |
Date |
2003-09-06 |
Time |
12:51 |
Rev Time |
0.33 |
Received By |
kstevens |
Date |
2003-09-06 |
Time |
12:51 |
Sent To |
B |
|
Notes |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
1 |
Status |
F |
Date |
2003-08-20 |
|
|
Cont ID |
|
Sent By |
dbaxter |
Date |
2003-08-27 |
Time |
13:50 |
Rev Time |
0.50 |
Received By |
jleech |
Date |
2003-08-20 |
Time |
19:12 |
Sent To |
B |
|
Notes |
2003-08-20 00:00:00 | RISER DIAGRAM DOESNOT MATCH FLOOR PLAN. | | MASTER BATH, RISER DIAGRAM SHOWS 2 SHR. | | LAVS ARE ON DIFFERENT WALLS CANNOT COME | | OFF SAME STACK. | | RISER DIAGRAM SHOWS 4 BATHROOMS FLOOR | | PLAN HAS 3. | | PLUMBING PLANREVIEW BY | | JOHN LEECH | | 805-6695 |
|
|
Review Stop |
Z |
ZONING |
Rev No |
1 |
Status |
P |
Date |
2003-09-17 |
|
|
Cont ID |
|
Sent By |
alange |
Date |
2003-07-31 |
Time |
13:09 |
Rev Time |
0.00 |
Received By |
sthyng |
Date |
|
Time |
|
Sent To |
|
|
Notes |
2003-09-17 00:00:00 | SIGNED OFF BY MM ON 8/5 |
|
|