Plan Review Stops For Permit 03071923 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
2 |
Status |
P |
Date |
2003-08-28 |
|
|
Cont ID |
|
Sent By |
sthyng |
Date |
2003-08-28 |
Time |
07:15 |
Rev Time |
1.50 |
Received By |
sthyng |
Date |
2003-08-28 |
Time |
07:14 |
Sent To |
|
|
Notes |
2003-08-28 00:00:00 | PROVISO - SEP PERMIT FOR SHUTTERS | | SUBMIT REVISION FOR 38-A1 (NOT ADDRESSED | | PROPERLY) |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
F |
Date |
2003-08-19 |
|
|
Cont ID |
|
Sent By |
dbaxter |
Date |
2003-08-27 |
Time |
13:44 |
Rev Time |
2.00 |
Received By |
sthyng |
Date |
2003-08-19 |
Time |
13:43 |
Sent To |
|
|
Notes |
2003-08-19 00:00:00 | ******CORRECTIONS****** | | | | 1.)ADDITIONAL FEES DUE, $22.08. | | | | 2.)A NOTICE OF COMMENCEMENT MUST BE | | FILED WITH THE CLERK OF COURTS BEFORE A | | PERMIT CAN BE ISSUED. | | | | 3.)IMPACT PROTECTION REQUIRED FOR | | GLAZING, FBC1606.1.7.EITHER PROVIDE | | TWO COPIES OF A HURRICANE SHUTTER | | ATTACHMENT SCHEDULE AND PRODUCT | | APPROVALS, OR A SEPARATE PERMIT WILL BE | | REQUIRED. | | | | 4.)DETAIL 38-A1, THE BOTTOM OF | | FOUNDATIONS SHALL EXTEND NO LESS THAN | | 12" BELOW FINISH GRADE, FBC1804.1.3. | | | | 5.)IS THE FRONT DOOR GLAZED?NO | | PRODUCT APPROVAL WAS SUBMITTED.ONE | | METHOD OF EGRESS ON THE FIRST FLOOR MUST | | BE PROVIDED FBC1005.4.5, 2003 AMENDMENT. | | | | 6.)DETAILS ON SHEET A6 HAVE | | ATTACHMENTS WHICH CONFLICT WITH THE | | 2003 USP CATALOG (EXAMPLE - 2, 12, 4). | | OTHERS MAY ALSO NOT BE CONSISTENT. | | CHECK ALL ATTACHMENTS. | | | | 7.) SUBMIT PRODUCT APPROVALS FOR ALL | | GLAZING, DOORS, ROOF, MULLIONS, | | SHUTTERS.ANY PRODUCT APPROVALS NOT | | SUBMITTED BEFORE THE LAST REVIEW WILL | | REQUIRE SEPARATE PERMITS FOR THOSE | | ITEMS. | | | | 8.)PROVIDE A SOILS INVESTIGATION | | REPORT. | | | | SAMANTHA THYNG, BUILDING PLANS EXAMINER | | [email protected] |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
3 |
Status |
P |
Date |
2004-04-20 |
|
|
Cont ID |
|
Sent By |
jleahy |
Date |
2004-04-20 |
Time |
08:37 |
Rev Time |
0.15 |
Received By |
jleahy |
Date |
2004-04-20 |
Time |
08:37 |
Sent To |
|
|
Notes |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
2 |
Status |
P |
Date |
2004-04-14 |
|
|
Cont ID |
|
Sent By |
jleahy |
Date |
2004-04-14 |
Time |
14:49 |
Rev Time |
0.15 |
Received By |
jleahy |
Date |
2004-04-14 |
Time |
14:49 |
Sent To |
|
|
Notes |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
1 |
Status |
P |
Date |
2003-08-07 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2004-04-13 |
Time |
12:07 |
Rev Time |
0.33 |
Received By |
dpalmer |
Date |
2003-08-07 |
Time |
06:52 |
Sent To |
M |
|
Notes |
2003-08-07 00:00:00 | 2002 NEC REDLINED. |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
5 |
Status |
N |
Date |
2004-04-13 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2004-04-13 |
Time |
12:07 |
Rev Time |
0.00 |
Received By |
csiegber |
Date |
2004-04-13 |
Time |
12:07 |
Sent To |
E |
|
Notes |
2004-04-13 00:00:00 | TO BT DESK/REV |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
4 |
Status |
N |
Date |
2004-02-13 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2004-02-13 |
Time |
11:32 |
Rev Time |
0.00 |
Received By |
csiegber |
Date |
2004-02-13 |
Time |
11:32 |
Sent To |
M |
|
Notes |
2004-02-13 00:00:00 | TO PK BOX/REV |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
3 |
Status |
N |
Date |
2003-08-27 |
|
|
Cont ID |
|
Sent By |
dbaxter |
Date |
2003-08-27 |
Time |
13:44 |
Rev Time |
0.00 |
Received By |
dbaxter |
Date |
2003-08-27 |
Time |
13:44 |
Sent To |
B |
|
Notes |
2003-08-27 00:00:00 | TO STHYNG DESK. |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2003-07-29 |
|
|
Cont ID |
|
Sent By |
alange |
Date |
2003-07-29 |
Time |
13:37 |
Rev Time |
0.00 |
Received By |
alange |
Date |
2003-07-29 |
Time |
13:37 |
Sent To |
E |
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2003-07-25 |
|
|
Cont ID |
|
Sent By |
mmclean |
Date |
2003-07-29 |
Time |
12:32 |
Rev Time |
0.00 |
Received By |
alange |
Date |
2003-07-25 |
Time |
08:57 |
Sent To |
Z |
|
Notes |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
2 |
Status |
P |
Date |
2004-02-23 |
|
|
Cont ID |
|
Sent By |
pkrauss |
Date |
2004-02-23 |
Time |
16:12 |
Rev Time |
0.25 |
Received By |
pkrauss |
Date |
2004-02-23 |
Time |
15:51 |
Sent To |
|
|
Notes |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
1 |
Status |
P |
Date |
2003-08-12 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2004-02-13 |
Time |
11:32 |
Rev Time |
0.25 |
Received By |
pkrauss |
Date |
2003-08-12 |
Time |
06:21 |
Sent To |
P |
|
Notes |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
1 |
Status |
P |
Date |
2003-08-14 |
|
|
Cont ID |
|
Sent By |
pkrauss |
Date |
2003-08-12 |
Time |
06:21 |
Rev Time |
0.25 |
Received By |
jleech |
Date |
2003-08-14 |
Time |
17:33 |
Sent To |
B |
|
Notes |
|
|
Review Stop |
Z |
ZONING |
Rev No |
1 |
Status |
P |
Date |
2003-07-29 |
|
|
Cont ID |
|
Sent By |
alange |
Date |
2003-07-25 |
Time |
08:57 |
Rev Time |
0.00 |
Received By |
mmclean |
Date |
|
Time |
|
Sent To |
I |
|
Notes |
|
|