Plan Review Details - Permit 03071615
Plan Review Stops For Permit 03071615
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2003-08-14 Cont ID  
Sent By jleech Date 2003-08-11 Time 19:11 Rev Time 2.00
Received By jgomez Date 2003-08-14 Time 15:52 Sent To PC
Notes
2003-08-14 00:00:00BUILDING REVIEW APPROVED WITH PROVISO:
 1-REVISE STORM SHUTTERS INSTALLATION
 SCHEDULE. SEE THE ENGINEERING
 DRAWINGS FOR MAXIMUM SPACING ALLOWED
 FOR WOOD ANCHORS.
 2-RESUBMIT SOIL TEST REPORT WITH THE
 ENGINEER'S ORIGINAL SEAL, SIGNATURE
 AND DATE AS REQUIRED BY CHAPTER 471
 FLORIDA STATUTES WHEN SUBMITTING
 DOCUMENTS FOR PUBLIC RECORDS.
 3-RESUBMIT ANOTHER COPY OF THE ENERGY
 CALCULATIONS WITH THE ENGINEER'S
 ORIGINAL SEAL, SIGNATURE AND DATE.
 CHAPTER 471 FLORIDA STATUTES.

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2003-11-20 Cont ID  
Sent By btrobaug Date 2003-11-20 Time 09:18 Rev Time 0.33
Received By btrobaug Date 2003-11-20 Time 09:18 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2003-08-05 Cont ID  
Sent By csiegber Date 2003-11-07 Time 11:53 Rev Time 0.33
Received By dpalmer Date 2003-08-05 Time 07:20 Sent To M
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2003-11-12 Cont ID  
Sent By csiegber Date 2003-11-12 Time 14:10 Rev Time 0.00
Received By csiegber Date 2003-11-12 Time 14:10 Sent To M
Notes
2003-11-12 00:00:00TO PK BOX/REV

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2003-11-07 Cont ID  
Sent By csiegber Date 2003-11-07 Time 11:53 Rev Time 0.00
Received By csiegber Date 2003-11-07 Time 11:53 Sent To E
Notes
2003-11-07 00:00:00TO BT DESK/REV

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2003-07-29 Cont ID  
Sent By alange Date 2003-07-29 Time 08:10 Rev Time 0.00
Received By alange Date 2003-07-29 Time 08:10 Sent To E
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2003-07-22 Cont ID  
Sent By mmclean Date 2003-07-28 Time 16:22 Rev Time 0.00
Received By alange Date 2003-07-22 Time 14:31 Sent To Z
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2003-11-23 Cont ID  
Sent By hmoser Date 2003-11-23 Time 11:09 Rev Time 0.25
Received By hmoser Date 2003-11-23 Time 11:09 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2003-08-10 Cont ID  
Sent By csiegber Date 2003-11-12 Time 14:11 Rev Time 0.25
Received By pkrauss Date 2003-08-10 Time 18:39 Sent To P
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status P Date 2003-08-11 Cont ID  
Sent By pkrauss Date 2003-08-10 Time 18:39 Rev Time 0.25
Received By jleech Date 2003-08-11 Time 19:11 Sent To B
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2003-07-28 Cont ID  
Sent By alange Date 2003-07-22 Time 14:31 Rev Time 1.00
Received By mmclean Date   Time   Sent To I
Notes
***NONE***