Plan Review Details - Permit 03052306
Plan Review Stops For Permit 03052306
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2003-07-23 Cont ID  
Sent By sthyng Date 2003-07-23 Time 08:59 Rev Time 1.50
Received By sthyng Date 2003-07-23 Time 07:39 Sent To  
Notes
2003-07-23 00:00:00*****PROVISO*****
 SUBMIT PRODUCT APPROVALS FOR
 SLIDING GLASS DOOR AND SINGLE
 HUNG WINDOW.

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2003-06-11 Cont ID  
Sent By shernand Date 2003-07-21 Time 08:48 Rev Time 1.50
Received By sthyng Date 2003-06-11 Time 07:48 Sent To  
Notes
2003-06-11 00:00:00******CORRECTIONS*******
  
 1.)ADDITIONAL PERMITS REQUIRED.
  
 2.)WINDOW B IS REQUIRED TO BE SAFETY
 GLASS, FBC2405.2.1.
  
 3.)PROVIDE AREA CALCULATIONS ON THE
 PLAN.IF THE ADDITION AREA IS GREATER
 THAN 25% OF THE EXISTING, COMPLY WITH
 FBC 3401.7.1.SHOW EMERGENCY EGRESS
 FOR BEDROOMS, SMOKE DETECTORS FOR
 EXISTING BEDROOMS, POOL SAFETY
 COMPLIANCE, AND SAFETY GLASS COMPLIANCE.
  
 4.ENERGY CALCS REQUIRED FBC13-101.2.
  
 5.)IMPACT FEES MUST BE PAID TO PALM
 BEACH COUNTY.THE PLANS MUST BE
 STAMPED AND THE RECEIPT ATTACHED TO THE
 PERMIT APPLICATION.233-5025
  
 6.)PROVIDE CALCULATIONS FOR THE
 REAR ELEVATION TO SHOW COMPLIANCE WITH
 TABLE 600 (20% MAX OF OPENINGS, TYPE
 VI CONSTRUCTION UNPROTECTED).
  
 7.)THE ADDITION MUST COMPLY WITH
 THE RESIDENTIAL SWIMMING POOL SAFETY
 ACT 515 FS.
  
 8.)SOFFIT VENTS ARE TO COMPLY WITH
 FBC 2309.7, CANNOT "MATCH EXISTING".
 SPECIFY SIZE AND SPACING OR NUMBER.
  
 9.)ATTIC ACCESS REQUIED, FBC2309.6.
  
 10.)SPECIFY CEILING INSULATION ON THE
 WALL SECTION (A5).BEFORE RESUBMITTING,
 BE SURE THAT THE INSULATION ON THE PLAN
 IS CONSISTENT WITH THE MINIMUMS ON THE
 ENERGY CALCS.
  
 11.)FIRESTOP REQUIRED, FBC 705.5
 (REVISE WALL SECTION A5).
  
 12.)ADDITIONAL FEES REQUIRED.

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2003-06-30 Cont ID  
Sent By btrobaug Date 2003-06-30 Time 15:45 Rev Time 0.50
Received By btrobaug Date 2003-06-30 Time 14:05 Sent To M
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2003-06-05 Cont ID  
Sent By shernand Date 2003-06-27 Time 16:34 Rev Time 0.50
Received By btrobaug Date 2003-06-04 Time 18:08 Sent To P
Notes
2003-06-05 00:00:00UNSAT
 ~~~~~
 ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
 PLEASE MAKE THE FOLLOWING CHANGES AND
 ADD THE FOLLOWING TO THE PLANS FOR CODE
 COMPLIANCE.
  
 1} THE RISER DIAGRAM AND LOAD
 CALCULATION ATTACHED TO THE PLAN IS NOT
 IN THE SCOPE OF WORK DESCRIBED ON THE
 PERMIT APPLICATION OR PART OF THE
 SIGNED AND SEALED PLANS.ALSO THE
 RELOCATED METER IS NOT IN THE
 SCOPE.PLEASE HAVE THE ARCHITECT OF
 RECORD ADD THIS TO THE PLANS AND
 INCLUDE IN THE PROJECT VALUATION,OR
 APPLY FOR A SEPARATE PERMIT FOR THAT
 WORK.
  
 2} PLEASE SUPPLY A PANEL SCHEDULE.
  
 3} PLEASE LIST THE REQ'D BATH(S)
 CIRCUIT(S). PER 210-11-C-3
 MUST BE 20A AND #12AWG.
  
 4} PLEASE LIST THE REQ'D ARC
 FAULT PROTECTED CIRCUITS ON PANEL
 SCHEDULE OR NOTE ON PLANS FOR BRANCH
 CIRCUIT PROTECTION. PER 210-12
  
 5} SMOKE DETECTORS ARE REQUIRED INSIDE
 AND OUTSIDE BEDROOMS PER 8-1.4.2
 NFPA-72.
  
 IF THERE ARE ANY QUESTIONS PLEASE CALL.
  
 BILL TROBAUGH
 ELECTRICAL PLAN REVIEW
 561/805-6718

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2003-07-21 Cont ID  
Sent By shernand Date 2003-07-21 Time 08:47 Rev Time 0.00
Received By shernand Date 2003-07-21 Time 08:47 Sent To B
Notes
2003-07-21 00:00:00STHYNG DESK

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2003-06-27 Cont ID  
Sent By shernand Date 2003-06-27 Time 16:34 Rev Time 0.00
Received By shernand Date 2003-06-27 Time 16:34 Sent To E
Notes
2003-06-27 00:00:00BT DESK

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2003-06-03 Cont ID  
Sent By shernand Date 2003-06-03 Time 16:45 Rev Time 0.00
Received By shernand Date 2003-06-03 Time 16:45 Sent To E
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2003-05-30 Cont ID  
Sent By mmclean Date 2003-06-03 Time 08:39 Rev Time 0.00
Received By shernand Date 2003-05-30 Time 15:12 Sent To Z
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2003-07-07 Cont ID  
Sent By pkrauss Date 2003-07-07 Time 09:51 Rev Time 0.25
Received By pkrauss Date 2003-07-07 Time 09:44 Sent To B
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status N Date 2003-06-09 Cont ID  
Sent By btrobaug Date 2003-06-30 Time 15:45 Rev Time 0.25
Received By pkrauss Date 2003-06-09 Time 14:05 Sent To B
Notes
2003-06-09 00:00:00INSUFFICIENT INFORMATION FOR MECHANICAL
 REVIEW.PLEASE PROVIDE ENERGY & MANUAL
 J CALCS AS PER 2001 FBC CHAPTER 13 SUB-
 CHAPTER 6.
  
 PROVIDE EQUIPMENT SCHEDULE (NEW OR
 EXISTING).
  
 IF YOU HAVE ANY QUESTIONS, PLEASE
 CONTACT PATTY KRAUSS AT (561) 805-6719.

Review Stop P PLUMBING
Rev No 1 Status P Date 2003-06-07 Cont ID  
Sent By btrobaug Date 2003-06-05 Time 12:06 Rev Time 0.33
Received By kstevens Date 2003-06-07 Time 16:50 Sent To M
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2003-06-03 Cont ID  
Sent By shernand Date 2003-05-30 Time 15:12 Rev Time 1.00
Received By mmclean Date   Time   Sent To I
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved