2003-06-30 00:00:00 | BUILDING DENIED |
| |
| 1) IMPACT FEES MUST BE PAID TO PALM |
| BEACH COUNTY, PLANS STAMPED BY THEM AND |
| COPY OF RECEIPT SUBMITTED TO CITY OF |
| WEST PALM BEACH BUILDING DEPARTMENT, |
| BEFORE A BUILDING PERMIT CAN BE ISSUED. |
| |
| 2) A RECORDED COPY OF THE NOTICE OF |
| COMMENCEMENT MUST BE SUBMITTED BEFORE A |
| PERMIT CAN BE ISSUED. |
| |
| 3) THE STRUCTURE IS LOCATED IN AN "AO" |
| FLOOD ZONE AN ELEVATION CERTIFICATE WILL |
| BE REQUIRED. |
| |
| 4) PROVIDE A FINAL SOIL BORING TEST |
| REPORT AS REQUIRED BY PRELIMINARY SOILS |
| REPORT AND CITY AMEND. TO FBC 1804.2.2. |
| |
| 5) REVISE NOTE #11 ON C-1. FBC 1606.1.4 |
| REQUIRES PROTECTION OF GLAZED OPENINGS |
| IN WINDBORNE DEBRIS REGIONS AS WELL AS |
| THE HVHZ AREAS. |
| |
| 6) THE GLASS BLOCK AT THE MASTER BEDROOM |
| TUB IS IN A HAZARDOUS LOCATION AND IS |
| REQUIRED TO HAVE A MINIMUM UNIFORM FACE |
| THICKNESS OF 0.25" PER FBC 2405.2.2(5). |
| PLEASE NOTE ON PLANS. |
| |
| 7) SPECIFY THE LENGTH/EMBED DEPTH OF THE |
| 1/2"DIA. ANCHOR BOLTS USED TO FASTEN THE |
| 2X6 GARAGE DOOR JAMB ON THE DETAIL ON |
| A4. |
| |
| 8) CLARIFY ON THE BUCK DETAIL FOR THE |
| SLIDING GLASS DOOR ON A4 THAT THE FRAME |
| IS FASTENED THROUGH THE 1X BUCK. |
| |
| 9) PROVIDE A TRUSS CONNECTOR SCHEDULE. |
| FBC 1609.4.3 NO LONGER ALLOWS THE ONE- |
| THIRD INCREASE IN STEEL CALCULATIONS. |
| SEE THE 2003 USP OR 2002 SIMPSON HIGH- |
| WIND CONSTRUCTION CATALOGS FOR TRUSS |
| CONNECTOR VALUES WITHOUT THE INCREASE. |
| |
| 10) PROVIDE DOCUMENTATION THAT THE USP |
| MSH 218 HANGER CAN BE USED AS A TRUSS |
| ANCHOR AND PROVIDE UPLIFT VALUES. THE |
| USP TA 14R HAVE AN UPLIFT VALUE OF 1720# |
| FOR DOUBLE STRAPS ON A ONE PLY TRUSS. |
| ADJUST THE UPLIFT VALUE FOR DETAIL 13 ON |
| A6 ACCORDINGLY. |
| |
| 11) REVISE THE CONNECTION DETAIL 2 ON A5 |
| THE MAXIMUM UPLIFT VALUE IS 1125# WITH |
| (7) 16D NAILS IN EACH MEMBER. SEE 2003 |
| USP CATALOG. |
| |
| 12) DETAIL 11 ON A5 SPECIFIES A HANGER |
| ON A MASONRY WALL FASTENED WITH (2) 5/8" |
| THROUGH BOLTS ON EACH SIDE. PLEASE |
| CLARIFY. |
| |
| 13) AN ID. TAG FOR A DETAIL 1 ON A6 IS |
| GIVEN ON THE FRAMING PLAN ON A5 AND THE |
| BRACING PLAN ON A-6, HOWEVER, THERE IS |
| NO SUCH DETAIL. PLEASE CORRECT. |
| |
| 14) AN ID. TAG FOR A DETAIL 1 ON A8 IS |
| GIVEN ON THE FRAMING PLAN ON A5, HOWEVER |
| THERE IS NO SHEET A8. PLEASE CORRECT. |
| |
| 15) THE ENERGY CALCULATIONS DO NOT |
| INCLUDE THE AREA OF THE CEILINGS THAT |
| ARE COFFERED. SEE FBC CHAPTER 13 SECTION |
| 604.1.A.1. |
| |
| 16) SUBMIT SBCCI OR METRO-DADE PRODUCT |
| APPROVALS FOR STORM PANELS. |
| |
| 17) THE SITE SPECIFIC ENGINEERING DOES |
| NOT CORRESPOND WITH ALL OF THE WINDOW |
| SIZES INDICATED ON THE PLANS. PLEASE |
| REVISE. THE SITE LOCATION IS REQUIRED TO |
| BE INDICATED ON THE FORM. THE FORM IS |
| REQUIRED TO BE SEALED BY THE DESIGNER OF |
| RECORD FOR THE STRUCTURE. |
| |
| ROBERT MCDOUGAL |
| BLDG. PLAN REVIEW |
| (561)805-6714 |