Plan Review Details - Permit 03041640
Plan Review Stops For Permit 03041640
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2003-07-01 Cont ID  
Sent By jgomez Date 2003-07-01 Time 16:51 Rev Time 0.50
Received By jgomez Date 2003-07-01 Time 16:51 Sent To PC
Notes
2003-07-01 00:00:00BUILDING REVIEW PROVISO:
 1-STORM SHUTTERS INSTALLATION SCHEDULE:
 REVISE SPACING FOR WOOD ANCHORS. SEE
 THE ENGINEERED DRAWINGS FOR MINIMUM
 SPACING REQUIRED.

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2003-05-27 Cont ID  
Sent By shernand Date 2003-06-03 Time 08:20 Rev Time 2.00
Received By jgomez Date 2003-05-27 Time 09:07 Sent To PC
Notes
2003-05-27 00:00:00BUILDING REVIEW APPROVED WITH PROVISO:
 1-PROVIDE STORM SHUTTERS INFORMATION
 WITH UPDATED SBCCI REPORT.
 2-REVISE DETAIL S21 FOR LOCATED BETWEEN
 GARAGE AND STAIRWAY TO MATCH THOSE
 CONDITIONS SHOWN ON 2ND FLOOR FRAMING
 PLAN. SEC. 104.2.1.2 CITY AMENDMENTS
 TO FBC 2001.
 3-WINDOW 34SH DOESN'T PROVIDE THE 24"
 CLEAR HEIGHT REQUIRED BY SECTION
 1005.4 FBC 2001. REVISE AS REQUIRED.
 4-REVISE TRUSS ANCHOR SCHEDULE TO COMPLY
 WITH SEC. 1609.4.3 FBC 2001, WHICH
 DOESN'T ALLOW THE 33% ALLOWABLE STRESS
 INCREASE TO BE USED. SEE USP 2003
 CATALOGUE FOR REVISED LOADS.

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2003-10-07 Cont ID  
Sent By btrobaug Date 2003-10-07 Time 14:15 Rev Time 0.33
Received By btrobaug Date 2003-10-07 Time 14:14 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2003-05-12 Cont ID  
Sent By csiegber Date 2003-09-19 Time 08:23 Rev Time 0.50
Received By btrobaug Date 2003-05-12 Time 07:21 Sent To M
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2003-09-29 Cont ID  
Sent By csiegber Date 2003-09-29 Time 11:12 Rev Time 0.00
Received By csiegber Date 2003-09-29 Time 11:12 Sent To M
Notes
2003-09-29 00:00:00TO PK BOX/REV

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2003-09-19 Cont ID  
Sent By csiegber Date 2003-09-19 Time 08:23 Rev Time 0.00
Received By csiegber Date 2003-09-19 Time 08:23 Sent To E
Notes
2003-09-19 00:00:00TO BT DESK

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2003-06-03 Cont ID  
Sent By shernand Date 2003-06-03 Time 08:20 Rev Time 0.00
Received By shernand Date 2003-06-03 Time 08:20 Sent To B
Notes
2003-06-03 00:00:00JGOMEZ DESK

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2003-04-22 Cont ID  
Sent By shernand Date 2003-04-22 Time 16:02 Rev Time 0.00
Received By shernand Date 2003-04-22 Time 16:02 Sent To Z
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2003-10-01 Cont ID  
Sent By pkrauss Date 2003-10-01 Time 08:26 Rev Time 0.20
Received By pkrauss Date 2003-10-01 Time 08:26 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2003-05-19 Cont ID  
Sent By csiegber Date 2003-09-29 Time 11:13 Rev Time 0.20
Received By pkrauss Date 2003-05-19 Time 13:14 Sent To B
Notes
2003-05-19 00:00:00MECHANICAL PERMIT 03041645

Review Stop P PLUMBING
Rev No 1 Status P Date 2003-04-26 Cont ID  
Sent By jleech Date 2003-04-26 Time 13:35 Rev Time 0.33
Received By jleech Date 2003-04-26 Time 13:35 Sent To E
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2003-04-25 Cont ID  
Sent By shernand Date 2003-04-22 Time 16:02 Rev Time 0.00
Received By sgraham Date   Time   Sent To E
Notes
***NONE***