Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2003-05-06 Cont ID  
Sent By jgomez Date 2003-05-06 Time 10:53 Rev Time 0.50
Received By jgomez Date 2003-05-06 Time 10:53 Sent To  
Notes
2003-05-06 00:00:00SOIL TEST REPORT, ENERGY CALCULATIONS
 AND STORM SHUTTERS.

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2003-04-24 Cont ID  
Sent By sthyng Date 2003-04-28 Time 09:17 Rev Time 0.50
Received By jgomez Date 2003-04-24 Time 14:29 Sent To  
Notes
2003-04-24 00:00:00ENERGY CALCULATIONS AND STORM SHUTTERS
 SUBMITTAL.

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2003-04-09 Cont ID  
Sent By rregueir Date 2003-03-31 Time 18:39 Rev Time 2.00
Received By jgomez Date 2003-04-09 Time 15:29 Sent To  
Notes
2003-04-09 00:00:00BUILDING REVIEW APPROVED WITH PROVISO:
 1-PROVIDE SOIL TEST REPORT.
 2-RE-SUBMIT STORM SHUTTERS PRODUCT
 APPROVAL REPORT #2229A WHICH MATCHES
 ENGINEERED DRAWINGS.
 **CHECK DESIGN PRESSURES AND PANEL SPAN
 MAX./MIN. DIMENSION. SEE ENGINEREED
 DRAWINGS AND REVISE INSTALLATION
 SCHEDULE AS REQUIRED.
 3-RE-SUBMIT ENERGY CALCULATIONS WITH
 ENGINEER'S ORIGINAL SIGNATURE AND SEAL
 AS REQUIRED BY CHAPTER 471 FL. ST. AND
 SEC. 103.0 CHAPTER 13 FBC 2001.

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2003-08-27 Cont ID  
Sent By btrobaug Date 2003-08-27 Time 18:31 Rev Time 0.33
Received By btrobaug Date 2003-08-27 Time 18:31 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2003-03-25 Cont ID  
Sent By csiegber Date 2003-08-21 Time 14:29 Rev Time 0.25
Received By dpalmer Date 2003-03-25 Time 06:13 Sent To P
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2003-08-21 Cont ID  
Sent By csiegber Date 2003-08-21 Time 14:29 Rev Time 0.00
Received By csiegber Date 2003-08-21 Time 14:28 Sent To E
Notes
2003-08-21 00:00:00TO BT DESK

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2003-08-21 Cont ID  
Sent By csiegber Date 2003-08-21 Time 13:41 Rev Time 0.00
Received By csiegber Date 2003-08-21 Time 13:41 Sent To M
Notes
2003-08-21 00:00:00TO PK DESK

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2003-04-28 Cont ID  
Sent By sthyng Date 2003-04-28 Time 09:17 Rev Time 0.00
Received By sthyng Date 2003-04-28 Time 09:16 Sent To B
Notes
2003-04-28 00:00:00TO JG DESK

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2003-03-12 Cont ID  
Sent By sthyng Date 2003-03-12 Time 15:39 Rev Time 0.00
Received By sthyng Date 2003-03-12 Time 15:39 Sent To Z
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2003-09-04 Cont ID  
Sent By pkrauss Date 2003-09-04 Time 08:17 Rev Time 0.25
Received By pkrauss Date 2003-09-04 Time 08:16 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2003-03-31 Cont ID  
Sent By csiegber Date 2003-08-21 Time 13:41 Rev Time 0.25
Received By rregueir Date 2003-03-31 Time 18:39 Sent To B
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status P Date 2003-03-27 Cont ID  
Sent By dpalmer Date 2003-03-25 Time 06:13 Rev Time 0.25
Received By jleech Date 2003-03-27 Time 18:55 Sent To M
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2003-03-17 Cont ID  
Sent By sthyng Date 2003-03-12 Time 15:40 Rev Time 0.00
Received By sgraham Date   Time   Sent To E