Plan Review Stops For Permit 03011809 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
P |
Date |
2003-02-19 |
|
|
Cont ID |
|
Sent By |
dpalmer |
Date |
2003-02-05 |
Time |
08:41 |
Rev Time |
2.00 |
Received By |
jgomez |
Date |
2003-02-19 |
Time |
14:59 |
Sent To |
|
|
Notes |
2003-02-19 00:00:00 | BUILDING REVIEW APPROVED WITH PROVISO: | | 1-PROVIDE COMPLETE INFORMATION FOR STORM | | SHUTTERS UNDER A SEPARATE PERMIT. | | 2-FLOOD ZONE A8. NEED TO PROVIDE THE | | ELEVATION CERTIFICATE. | | 3-CLARIFY DETAIL S21 FOR COLUMN LOCATED | | BETWEEN GARAGE AND STAIRWAY. HOW ARE | | GIRDER TRUSSES SUPPORTED?. SEE 2ND FL | | FRAMING PLAN. | | SEC. 104.2.1.2 CITY AMENDMENTS TO FBC. | | 4-REVISE CONNECTOR TC-1 SPECIFIED ON | | ROOF FRAMING PLAN @ FRAMED WALL ON | | FRONT ELEVATION. NEED WOOD TO WOOD | | CONNECTORS. SEC. 104.2.1.2 CITY | | AMENDMENTS TO FBC 2001. | | 5-34SH WINDOW DOESN'T PROVIDE THE 24" | | CLEAR HEIGHT REQUIRED BY SEC. 1005.4.4 | | FBC 2001. REVISE CLARIFY AS REQUIRED. | | 6-PROVIDE SOIL TEST REPORT PRIOR TO | | CONSTRUCTION. |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
4 |
Status |
P |
Date |
2003-08-11 |
|
|
Cont ID |
|
Sent By |
dpalmer |
Date |
2003-08-11 |
Time |
12:30 |
Rev Time |
0.25 |
Received By |
dpalmer |
Date |
2003-08-11 |
Time |
12:30 |
Sent To |
|
|
Notes |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
3 |
Status |
P |
Date |
2003-03-28 |
|
|
Cont ID |
|
Sent By |
alange |
Date |
2003-08-06 |
Time |
09:42 |
Rev Time |
0.75 |
Received By |
dpalmer |
Date |
2003-03-28 |
Time |
13:38 |
Sent To |
|
|
Notes |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
2 |
Status |
F |
Date |
2003-03-11 |
|
|
Cont ID |
|
Sent By |
sthyng |
Date |
2003-03-27 |
Time |
08:35 |
Rev Time |
0.25 |
Received By |
dpalmer |
Date |
2003-03-11 |
Time |
18:29 |
Sent To |
M |
|
Notes |
2003-03-11 00:00:00 | PLEASE COMPLETE TWO SETS. | | NO ELEC 2ND SET.? |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
1 |
Status |
F |
Date |
2003-02-05 |
|
|
Cont ID |
|
Sent By |
hmoser |
Date |
2003-02-03 |
Time |
18:45 |
Rev Time |
0.30 |
Received By |
dpalmer |
Date |
2003-02-05 |
Time |
08:40 |
Sent To |
B |
|
Notes |
2003-02-05 00:00:00 | ************* UNSAT ************** | | | | 1)NOTE: PLEASE CORRELATE RISER DIAGRAM | | W/ PANEL SCHEDULE. PLEASE SEE PANEL "A'" | | SHOWS 2P40A OCP ON #10 AWG FOR 60A SUB- | | -PANEL.? | | PLEASE ALSO SHOW LOCATION OF SUB-PANEL | | ON PLANS. | | | | PLEASE SUBMIT THE ABOVE INFORMATION FOR | | REVIEW. IF THERE ARE ANY QUESTIONS, | | PLEASE CALL. | | | | DEWEY PALMER | | ELECTRICAL PLAN REVIEW | | 561-659-8096 EXT 8372 |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
4 |
Status |
N |
Date |
2003-08-20 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2003-08-20 |
Time |
10:05 |
Rev Time |
0.00 |
Received By |
csiegber |
Date |
2003-08-20 |
Time |
10:04 |
Sent To |
M |
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
3 |
Status |
N |
Date |
2003-08-06 |
|
|
Cont ID |
|
Sent By |
alange |
Date |
2003-08-06 |
Time |
09:42 |
Rev Time |
0.00 |
Received By |
alange |
Date |
2003-08-06 |
Time |
09:41 |
Sent To |
E |
|
Notes |
2003-08-06 00:00:00 | TO DP DESK |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2003-03-27 |
|
|
Cont ID |
|
Sent By |
sthyng |
Date |
2003-03-27 |
Time |
08:35 |
Rev Time |
0.00 |
Received By |
sthyng |
Date |
2003-03-27 |
Time |
08:35 |
Sent To |
E |
|
Notes |
2003-03-27 00:00:00 | TO DP DESK |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2003-01-24 |
|
|
Cont ID |
|
Sent By |
dpalmer |
Date |
2003-01-24 |
Time |
13:01 |
Rev Time |
0.00 |
Received By |
dpalmer |
Date |
2003-01-24 |
Time |
13:01 |
Sent To |
Z |
|
Notes |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
3 |
Status |
P |
Date |
2003-08-25 |
|
|
Cont ID |
|
Sent By |
pkrauss |
Date |
2003-08-25 |
Time |
07:22 |
Rev Time |
0.25 |
Received By |
pkrauss |
Date |
2003-08-25 |
Time |
07:22 |
Sent To |
|
|
Notes |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
2 |
Status |
P |
Date |
2003-03-14 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2003-08-20 |
Time |
10:05 |
Rev Time |
0.25 |
Received By |
hmoser |
Date |
2003-03-14 |
Time |
17:04 |
Sent To |
|
|
Notes |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
1 |
Status |
F |
Date |
2003-02-03 |
|
|
Cont ID |
|
Sent By |
dpalmer |
Date |
2003-03-11 |
Time |
18:29 |
Rev Time |
0.25 |
Received By |
hmoser |
Date |
2003-02-03 |
Time |
18:44 |
Sent To |
E |
|
Notes |
2003-02-03 00:00:00 | PLAN DENIED | | 1) ENERGY PERFORMANCE LEVEL DISPLAY CARD | | AND ENERGY CALCULATIONS DO NOT MATCH. | | 2) EQUIPMENT SELESTION ON MANUAL (J) NOT | | COMPLETE. | | 3) COOLING & HEATING BTU.ON MANUAL (J) | | DO NOTMATCH PLANS. | | PLAN REVIEW BY HAROLD MOSER | | (561)689-8096 EXT.8390 |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
1 |
Status |
P |
Date |
2003-01-28 |
|
|
Cont ID |
|
Sent By |
sgraham |
Date |
2003-01-24 |
Time |
16:25 |
Rev Time |
0.25 |
Received By |
kstevens |
Date |
2003-01-28 |
Time |
07:27 |
Sent To |
M |
|
Notes |
|
|
Review Stop |
Z |
ZONING |
Rev No |
1 |
Status |
P |
Date |
2003-01-24 |
|
|
Cont ID |
|
Sent By |
dpalmer |
Date |
2003-01-24 |
Time |
13:01 |
Rev Time |
0.00 |
Received By |
sgraham |
Date |
|
Time |
|
Sent To |
P |
|
Notes |
|
|