Plan Review Details - Permit 03011299
Plan Review Stops For Permit 03011299
Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2003-04-08 Cont ID  
Sent By jgomez Date 2003-04-08 Time 17:30 Rev Time 0.50
Received By jgomez Date 2003-04-08 Time 17:30 Sent To  
Notes
2003-04-08 00:00:00PROVIDE COMPLETE INFORMATION FOR STORM
 SHUTTERS UNDER A SEPARATE PERMIT AS
 REQUESTED ON PROVISO DATED 2-10-03.

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2003-04-01 Cont ID  
Sent By shernand Date 2003-04-07 Time 08:17 Rev Time 0.50
Received By jgomez Date 2003-04-01 Time 08:46 Sent To  
Notes
2003-04-01 00:00:00REVISION CHECKLIST:
 1-ARCHITECT NEEDS TO REVISE DIAPHRAGM
 SCHEDULE ON SHEET S-2. SEE ENGINEERING
 ANALYSIS AND SPECS FOR FASTENERS USED
 IN THE CALCULATIONS.
 2-PROVIDE COMPLETE INFORMATION FOR STORM
 SHUTTERS UNDER A SEPARATE PERMIT AS
 REQUIRED ON PROVISO DATED 2-10-03.

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2003-02-10 Cont ID  
Sent By dpalmer Date 2003-03-28 Time 15:12 Rev Time 2.00
Received By jgomez Date 2003-02-10 Time 13:10 Sent To  
Notes
2003-02-10 00:00:00BUILDING REVIEW APPROVED WITH PROVISO:
 1-REVISE SURVEY TO MATCH FLOOR PLANS.
 SEE EXACT LOCATION OF REAR PORCH.
 2-ARCHITECT TO REVISE THE DIAPHRAGM
 SCHEDULE. SEE ENGINEERING CALCS AND
 SPECS FOR FASTENERS SIZE AND SPACING.
 3-PROVIDE COMPLETE INFORMATION FOR STORM
 SHUTTERS UNDER A SEPARATE PERMIT.

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2003-02-04 Cont ID  
Sent By hmoser Date 2003-02-03 Time 19:57 Rev Time 0.50
Received By btrobaug Date 2003-02-04 Time 12:29 Sent To B
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2003-05-08 Cont ID  
Sent By shernand Date 2003-05-08 Time 13:39 Rev Time 0.00
Received By shernand Date 2003-05-08 Time 13:39 Sent To M
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2003-04-07 Cont ID  
Sent By shernand Date 2003-04-07 Time 08:16 Rev Time 0.00
Received By shernand Date 2003-04-07 Time 08:08 Sent To B
Notes
2003-04-07 00:00:00JGOMEZ DESK

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2003-03-28 Cont ID  
Sent By dpalmer Date 2003-03-28 Time 15:12 Rev Time 0.00
Received By dpalmer Date 2003-03-28 Time 15:12 Sent To B
Notes
2003-03-28 00:00:00REV TO JG DESK`S

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2003-03-19 Cont ID  
Sent By sthyng Date 2003-03-19 Time 13:05 Rev Time 0.00
Received By sthyng Date 2003-03-19 Time 13:04 Sent To Z
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2003-05-22 Cont ID  
Sent By pkrauss Date 2003-05-22 Time 12:06 Rev Time 0.20
Received By pkrauss Date 2003-05-22 Time 11:53 Sent To  
Notes
2003-05-22 00:00:00MECH REV

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2003-02-03 Cont ID  
Sent By shernand Date 2003-05-08 Time 13:39 Rev Time 0.25
Received By hmoser Date 2003-02-03 Time 19:56 Sent To E
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status P Date 2003-01-30 Cont ID  
Sent By sgraham Date 2003-01-24 Time 16:27 Rev Time 0.25
Received By kstevens Date 2003-01-30 Time 12:49 Sent To M
Notes
***NONE***

Review Stop Z ZONING
Rev No 2 Status P Date 2003-03-27 Cont ID  
Sent By sgraham Date 2003-03-27 Time 09:17 Rev Time 0.00
Received By sgraham Date   Time   Sent To B
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2003-01-24 Cont ID  
Sent By sthyng Date 2003-03-19 Time 13:06 Rev Time 0.00
Received By sgraham Date   Time   Sent To P
Notes
***NONE***