Plan Review Stops For Permit 03011084 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
4 |
Status |
P |
Date |
2003-05-12 |
|
|
Cont ID |
|
Sent By |
jgomez |
Date |
2003-05-12 |
Time |
17:53 |
Rev Time |
0.50 |
Received By |
jgomez |
Date |
2003-05-12 |
Time |
17:53 |
Sent To |
|
|
Notes |
2003-05-12 00:00:00 | AREA TABULATION CORRECTION. |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
3 |
Status |
P |
Date |
2003-04-28 |
|
|
Cont ID |
|
Sent By |
shernand |
Date |
2003-05-08 |
Time |
13:25 |
Rev Time |
2.00 |
Received By |
jgomez |
Date |
2003-04-28 |
Time |
13:56 |
Sent To |
|
|
Notes |
2003-04-28 00:00:00 | BUILDING REVIEW APPROVED WITH PROVISO: | | 1-ARCHITECT TO REVISE AREA CALCULATIONS | | ON SHEET C-1 AND A-1. AREA SUMMARY TO | | ADD UP TO 3295S.F.. NOT 3420S.F. |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
2 |
Status |
F |
Date |
2003-03-28 |
|
|
Cont ID |
|
Sent By |
shernand |
Date |
2003-04-25 |
Time |
11:15 |
Rev Time |
1.00 |
Received By |
jgomez |
Date |
2003-03-27 |
Time |
14:20 |
Sent To |
M |
|
Notes |
2003-03-27 00:00:00 | BUILDING REVIEW SECOND CHECKLIST: | | 1-AREA CALCULATIONS ARE INCORRECT. | | ARCHITECT TO REVISE SHEET C-1 AND A-1. | | 2-ENERGY CALCULATIONS TO HAVE ENGINEER'S | | ORIGINAL SIGNATURE AND SEAL AS REQ'D | | BY CHAPTER 471 FLORIDA STATUTES AND | | SEC. 103.0 CHAPTER 13 FBC 2001. | | 3-REVISE STORM SHUTTERS INSTALLATION | | SCHEDULE TO MATCH INFORMATION GIVEN ON | | THE ENGINEERED DRAWINGS. CHECK THE | | DESIGN PRESSURES AND THE MAXIMUM PANEL | | SPAN ALLOWED. ALSO, CHECK FOR ANCHOR | | SPACING ACCORDING TO DESIGN PRESSURES, | | EDGE DISTANCE, CONNECTION TYPE AND | | PANEL SPAN SHOWN ON ENGINEERED DWGS. | | **ALSO, CLARIFY WHY SOMETIMESSHUTTERS | | PRODUCT APPROVALS ARE SUBMITTED AS | | SITE SPECIFIC AND SOMETIMES PRODUCT | | APPROVAL ARE SUBMITTED WITH THE SBCCI | | PRODUCT APPROVAL REPORT. |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
F |
Date |
2003-02-06 |
|
|
Cont ID |
|
Sent By |
sthyng |
Date |
2003-03-27 |
Time |
08:15 |
Rev Time |
1.00 |
Received By |
jgomez |
Date |
2003-02-06 |
Time |
13:11 |
Sent To |
|
|
Notes |
2003-02-06 00:00:00 | BUILDING REVIEW CHECKLIST: | | 1-AREA CALCULATIONS ARE INCORRECT.REVISE | | AS REQUIRED. | | 2-REVISE ENERGY CALCULATIONS AS REQUIRED | | TO MATCH CORRECT AREAS IN FLOOR PLANS. | | 3-REVISE AREA CALCULATIONS ON IMPACT | | FEES STAMP TO MATCH CORRECTED PLANS. | | 4-PROVIDE COMPLETE INFORMATION FOR STORM | | SHUTTERS OR APPLY FOR SEPARATE PERMIT. | | 5-PROVIDE COMPLETE SPECIFICATIONS FOR | | GARAGE STRUCTURAL BUCK DETAIL. NEED | | ANCHOR EMBEDMENT AND WASHER SIZE. | | SEC. 104.2.1.2 CITY AMENDMENTS TO FBC. | | 6-BUILDING SECTION A/A-5: REVISE HEIGHT | | OF HANDRAIL. SEE SECTION 1007.5.1 FBC | | 2001. ****NOTE: HANDRAIL AND GUARDRAIL | | ARE NOT THE SAME. | | 7-NEED RECORDED NOTICE OF COMMENCEMENT. |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
2 |
Status |
P |
Date |
2003-08-27 |
|
|
Cont ID |
|
Sent By |
dpalmer |
Date |
2003-08-27 |
Time |
10:09 |
Rev Time |
0.25 |
Received By |
dpalmer |
Date |
2003-08-27 |
Time |
10:09 |
Sent To |
|
|
Notes |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
1 |
Status |
P |
Date |
2003-02-04 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2003-08-19 |
Time |
14:43 |
Rev Time |
0.25 |
Received By |
dpalmer |
Date |
2003-02-04 |
Time |
07:04 |
Sent To |
B |
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
7 |
Status |
N |
Date |
2003-09-11 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2003-09-11 |
Time |
11:25 |
Rev Time |
0.00 |
Received By |
csiegber |
Date |
2003-09-11 |
Time |
11:25 |
Sent To |
M |
|
Notes |
2003-09-11 00:00:00 | TO PK DESK |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
6 |
Status |
N |
Date |
2003-08-21 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2003-08-21 |
Time |
13:36 |
Rev Time |
0.00 |
Received By |
csiegber |
Date |
2003-08-21 |
Time |
13:36 |
Sent To |
M |
|
Notes |
2003-08-21 00:00:00 | TO PK DESK |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
5 |
Status |
N |
Date |
2003-08-19 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2003-08-19 |
Time |
14:43 |
Rev Time |
0.00 |
Received By |
csiegber |
Date |
2003-08-19 |
Time |
14:42 |
Sent To |
E |
|
Notes |
2003-08-19 00:00:00 | TO DP DESK |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
4 |
Status |
N |
Date |
2003-05-08 |
|
|
Cont ID |
|
Sent By |
shernand |
Date |
2003-05-08 |
Time |
13:25 |
Rev Time |
0.00 |
Received By |
shernand |
Date |
2003-05-08 |
Time |
13:25 |
Sent To |
B |
|
Notes |
2003-05-08 00:00:00 | JGOMEZ DESK, SUBMITTAL FOR PROVISO |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
3 |
Status |
N |
Date |
2003-04-25 |
|
|
Cont ID |
|
Sent By |
shernand |
Date |
2003-04-25 |
Time |
11:15 |
Rev Time |
0.00 |
Received By |
shernand |
Date |
2003-04-25 |
Time |
11:15 |
Sent To |
B |
|
Notes |
2003-04-25 00:00:00 | JGOMEZ DESK |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2003-03-27 |
|
|
Cont ID |
|
Sent By |
sthyng |
Date |
2003-03-27 |
Time |
08:15 |
Rev Time |
0.00 |
Received By |
sthyng |
Date |
2003-03-27 |
Time |
08:15 |
Sent To |
B |
|
Notes |
2003-03-27 00:00:00 | TO JG DESK |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2003-01-17 |
|
|
Cont ID |
|
Sent By |
btrobaug |
Date |
2003-01-17 |
Time |
17:07 |
Rev Time |
0.00 |
Received By |
btrobaug |
Date |
2003-01-17 |
Time |
17:07 |
Sent To |
P |
|
Notes |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
4 |
Status |
P |
Date |
2003-09-16 |
|
|
Cont ID |
|
Sent By |
pkrauss |
Date |
2003-09-16 |
Time |
07:10 |
Rev Time |
0.25 |
Received By |
pkrauss |
Date |
2003-09-16 |
Time |
07:10 |
Sent To |
|
|
Notes |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
3 |
Status |
F |
Date |
2003-09-04 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2003-09-11 |
Time |
11:25 |
Rev Time |
0.20 |
Received By |
pkrauss |
Date |
2003-09-04 |
Time |
07:38 |
Sent To |
|
|
Notes |
2003-09-04 00:00:00 | DENIED: | | | | ENERGY CALCULATIONS INDICATE 11 SEER | | AND THE REVISED PLAN SUBMITTED INDICATES | | 10 SEER.PLEASE REVISE. | | | | IF YOU HAVE ANY QUESTIONS, PLEASE | | CONTACT PATTY KRAUSS AT (561) 805-6719. |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
2 |
Status |
N |
Date |
2003-04-01 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2003-08-21 |
Time |
13:36 |
Rev Time |
0.35 |
Received By |
pkrauss |
Date |
2003-04-01 |
Time |
11:58 |
Sent To |
B |
|
Notes |
2003-04-01 00:00:00 | MECHANICAL PERMIT 03011106 | | | | PLANS APPROVED, SEE COMMENTS BY BUILDING | | PLAN REVIEW (J. GOMEZ). |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
1 |
Status |
P |
Date |
2003-02-03 |
|
|
Cont ID |
|
Sent By |
jgomez |
Date |
2003-03-28 |
Time |
10:21 |
Rev Time |
0.33 |
Received By |
jleech |
Date |
2003-02-03 |
Time |
17:41 |
Sent To |
E |
|
Notes |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
1 |
Status |
P |
Date |
2003-01-25 |
|
|
Cont ID |
|
Sent By |
btrobaug |
Date |
2003-01-17 |
Time |
17:17 |
Rev Time |
0.25 |
Received By |
jleech |
Date |
2003-01-25 |
Time |
11:42 |
Sent To |
M |
|
Notes |
|
|
Review Stop |
Z |
ZONING |
Rev No |
1 |
Status |
P |
Date |
2003-01-17 |
|
|
Cont ID |
|
Sent By |
sgraham |
Date |
2003-01-17 |
Time |
12:12 |
Rev Time |
0.00 |
Received By |
sgraham |
Date |
|
Time |
|
Sent To |
P |
|
Notes |
|
|