Plan Review Stops For Permit 02101839 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
6 |
Status |
P |
Date |
2004-01-27 |
|
|
Cont ID |
|
Sent By |
lmartine |
Date |
2004-01-27 |
Time |
17:22 |
Rev Time |
1.00 |
Received By |
lmartine |
Date |
|
Time |
|
Sent To |
|
|
Notes |
2004-01-27 00:00:00 | REVIEW AND APPROVE TIE BEAM AND MINOR | | REVISIONSLM |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
5 |
Status |
|
Date |
2003-09-11 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2003-09-11 |
Time |
09:21 |
Rev Time |
0.25 |
Received By |
rmcdouga |
Date |
2003-09-11 |
Time |
09:20 |
Sent To |
|
|
Notes |
2003-09-11 00:00:00 | PROVISO | | | | SUBMIT PRODUCT APPROVALS FOR ROOFING | | MATERIALS. |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
4 |
Status |
F |
Date |
2003-09-08 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2003-09-08 |
Time |
10:57 |
Rev Time |
1.50 |
Received By |
rmcdouga |
Date |
2003-09-08 |
Time |
10:57 |
Sent To |
|
|
Notes |
2003-09-08 00:00:00 | REVISION TO CHANGE FROM TWO STORY GARAGE | | TO ONE STORY IS DENIED. | | | | 1) THE ORIGINAL PLANS ARE SIGNED AND | | SEALED BY AN ENGINEER (JOHN HOLT). | | THEREFORE, THE REVISED PLANS ARE | | REQUIRED TO BE SIGNED AND SEALED BY THE | | ENGINEER OF RECORD. THE ENGINEER'S TITLE | | BLOCK IS REQUIRED TO BE ON THE PLANS. | | | | 2)PROVIDE (2) CURRENT AND COMPLETE | | COPIES OF SBCCI OR METRO-DADE PRODUCT | | APPROVALS FOR: | | - 10' WIDE OVERHEAD GARAGE DOORS (WERE | | CHANGED FROM 8' WIDE DOORS) | | - ROOFING MATERIAL (WAS CHANGED BY | | REVISION) | | | | 3) THE WALL SECTION SPECIFIES AN 18" | | DEEP FOOTER AND THE FOUNDATION PLAN | | SPECIFIES A 16" THICK FOOTER. PLEASE | | CORRECT. THE FBC REQUIRES THE BOTTOM OF | | THE FOOTER TO BE 12" BELOW FINAL GRADE. | | | | IF YOU HAVE QUESTIONS, PLEASE CALL. | | ROBERT MCDOUGAL | | BLDG. PLAN REVIEW | | (561)805-6714 |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
3 |
Status |
P |
Date |
2003-05-22 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2003-09-04 |
Time |
11:19 |
Rev Time |
1.50 |
Received By |
lhatten |
Date |
2003-05-22 |
Time |
09:58 |
Sent To |
|
|
Notes |
2003-05-22 00:00:00 | WHAT I HAVE SO FAR-05/03/2003 | | 1) SHUTTERS | | 2) WINDOWS | | 3) GARAGE DOORS | | 4) SWING DOORS | | | | PROVISO -- DURING CONSTRUCTION FIELD | | INSPECTOR TO BRING COPY BACK TO OFFICE! | | 1) ROOF MATERIAL | | 2) TRUSS ENG. FLOOR & ROOF | | 3) DENSITY REPORT FOR SLAB! | | 4) TERMITE CERTIFICATE FOR SLAB |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
2 |
Status |
F |
Date |
2003-04-18 |
|
|
Cont ID |
|
Sent By |
lhatten |
Date |
2003-04-18 |
Time |
11:47 |
Rev Time |
1.00 |
Received By |
lhatten |
Date |
2003-04-18 |
Time |
11:46 |
Sent To |
|
|
Notes |
2003-04-18 00:00:00 | 1) NEED NEW PRODUCT APPROVAL FOR; | | A) EXTERIOR DOORS2'-4"X 6'-8" | | B) GARAGE DOORS 8 FT WIDE | | C) MULL BARS IF DOUBLES | | | | 2) FOUNDATION PLAN AS PER WHATS INTHE | | FIELD ( STEEL & DOWEL SPACING ECT..) | | 3) ELEVATIONS OF GARAGE | | 4) DENSITY TEST! | | 5) TERMITE TREATMENT CERT. | | 6) ROOF PLAN TRUSSES OR CONVENTIONAL | | FRAMED |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
F |
Date |
2003-03-14 |
|
|
Cont ID |
|
Sent By |
sgraham |
Date |
2003-03-13 |
Time |
15:20 |
Rev Time |
2.00 |
Received By |
lhatten |
Date |
2003-03-13 |
Time |
18:22 |
Sent To |
|
|
Notes |
2003-03-17 00:00:00 | 1) DIMENSIONS ON SITE PLAN DON'T MATCH | | FLOOR PLAN | | 2) MISSING PRODUCT APPROVAL ON GARAGE | | DOORS AS WELL AS SWING DOORS | | 3) IF OWNER WANTS ANY WINDOWS -WILL NEED | | PRODUCT APPROVALS FOR THESE AS WELL | | 4) TRUSS DRAWINGS ARE ALSO NEEDED - BOTH | | FOR FLOOR AND ROOF SYSTEMS | | 5) HAVE ARCH. REDRAW EVERYTHING AS TO | | WHAT IS ACTUALLY IN THE FIELD--SIZE OF | | SLAB, THEN DIMENSIONS OF WALLS WITH | | SIZE OF OPENINGS | | 6) DENSITY REPORTS FOR SLAB AREA | | 7) TERMITE TREATMENT VERIFICATION | | 8) ADDITIONAL FEES $ 600.00 |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
1 |
Status |
N |
Date |
2003-05-28 |
|
|
Cont ID |
|
Sent By |
drunnels |
Date |
2003-05-28 |
Time |
09:51 |
Rev Time |
0.00 |
Received By |
drunnels |
Date |
|
Time |
|
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2003-09-04 |
|
|
Cont ID |
|
Sent By |
csiegber |
Date |
2003-09-04 |
Time |
11:19 |
Rev Time |
0.00 |
Received By |
csiegber |
Date |
2003-09-04 |
Time |
11:18 |
Sent To |
B |
|
Notes |
2003-09-04 00:00:00 | TO RM DESK |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2002-10-30 |
|
|
Cont ID |
|
Sent By |
mmclean |
Date |
2003-09-04 |
Time |
09:45 |
Rev Time |
0.00 |
Received By |
btrobaug |
Date |
2002-10-29 |
Time |
18:41 |
Sent To |
Z |
|
Notes |
2002-10-30 00:00:00 | TO Z BOX./WRT |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
1 |
Status |
N |
Date |
2003-05-28 |
|
|
Cont ID |
|
Sent By |
drunnels |
Date |
2003-05-28 |
Time |
09:52 |
Rev Time |
0.00 |
Received By |
drunnels |
Date |
|
Time |
|
Sent To |
|
|
Notes |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
1 |
Status |
N |
Date |
2003-05-28 |
|
|
Cont ID |
|
Sent By |
drunnels |
Date |
2003-05-28 |
Time |
09:52 |
Rev Time |
0.00 |
Received By |
drunnels |
Date |
|
Time |
|
Sent To |
|
|
Notes |
|
|
Review Stop |
Z |
ZONING |
Rev No |
4 |
Status |
P |
Date |
2003-09-04 |
|
|
Cont ID |
|
Sent By |
mmclean |
Date |
2003-09-04 |
Time |
09:45 |
Rev Time |
0.00 |
Received By |
mmclean |
Date |
|
Time |
|
Sent To |
I |
|
Notes |
|
|
Review Stop |
Z |
ZONING |
Rev No |
3 |
Status |
P |
Date |
2003-05-15 |
|
|
Cont ID |
|
Sent By |
lhatten |
Date |
2003-05-22 |
Time |
09:56 |
Rev Time |
0.25 |
Received By |
lhatten |
Date |
|
Time |
|
Sent To |
|
|
Notes |
2003-05-22 00:00:00 | REVIEWED NEW SITE PLAN - AS TO WHAT IS | | ACTUALLY IN THE FIELD PER LOU HATTEN'S | | REVIEW 05/15/2003 |
|
|
Review Stop |
Z |
ZONING |
Rev No |
2 |
Status |
P |
Date |
2003-03-13 |
|
|
Cont ID |
|
Sent By |
sgraham |
Date |
2003-03-13 |
Time |
15:20 |
Rev Time |
0.00 |
Received By |
sgraham |
Date |
|
Time |
|
Sent To |
B |
|
Notes |
|
|
Review Stop |
Z |
ZONING |
Rev No |
1 |
Status |
F |
Date |
2002-11-26 |
|
|
Cont ID |
|
Sent By |
btrobaug |
Date |
2002-10-30 |
Time |
18:42 |
Rev Time |
0.25 |
Received By |
sgraham |
Date |
|
Time |
|
Sent To |
|
|
Notes |
2002-11-26 00:00:00 | DENIED, NEED CLEAR SITE PLAN SHOWING | | GARAGE |
|
|