Plan Review Details - Permit 02080948
Plan Review Stops For Permit 02080948
Review Stop E ELECTRICAL
Rev No 3 Status P Date 2003-02-14 Cont ID  
Sent By btrobaug Date 2003-02-14 Time 09:02 Rev Time 0.50
Received By btrobaug Date 2003-02-14 Time 07:37 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2002-09-19 Cont ID  
Sent By btrobaug Date 2002-09-19 Time 14:02 Rev Time 0.50
Received By btrobaug Date 2002-09-19 Time 13:54 Sent To R
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2002-08-30 Cont ID  
Sent By btrobaug Date 2002-08-30 Time 17:06 Rev Time 0.50
Received By btrobaug Date 2002-08-30 Time 16:33 Sent To R
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2002-08-28 Cont ID  
Sent By hmoser Date 2002-08-28 Time 18:18 Rev Time 0.50
Received By hmoser Date 2002-08-28 Time 18:18 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status P Date 2002-08-24 Cont ID  
Sent By jleech Date 2002-08-24 Time 08:18 Rev Time 0.33
Received By jleech Date 2002-08-24 Time 08:18 Sent To  
Notes
***NONE***

Review Stop R ROOF PLAN REVIEW
Rev No 3 Status P Date 2002-10-04 Cont ID  
Sent By rmcdouga Date 2002-10-04 Time 15:52 Rev Time 0.30
Received By rmcdouga Date   Time   Sent To  
Notes
2002-10-04 00:00:00SBCCI OR METRO-DADE PRODUCT APPROVALS
 ARE REQUIRED FOR THE CABANA BATH DOOR.
 IF THESE ARE NOT AVAILABLE SITE SPECIFIC
 ENGINEERING IS REQUIRED.

Review Stop R ROOF PLAN REVIEW
Rev No 2 Status P Date 2002-09-19 Cont ID  
Sent By btrobaug Date 2002-09-19 Time 14:02 Rev Time 4.00
Received By rmcdouga Date   Time   Sent To  
Notes
2002-09-19 00:00:00************BUILDING PROVISO************
  
 1)A RECORDED COPY OF THE NOTICE OF
 COMMENCEMENT MUST BE SUBMITTED BEFORE A
 PERMIT CAN BE ISSUED.
  
 2)PROVIDE AN UPDATED SURVEY WITH CORRECT
 STREET NAMES.
  
 3)PROVIDE (2) CURRENT AND COMPLETE
 COPIES OF SBCCI OR METRO-DADE PRODUCT
 APPROVALS FOR:
 - FRENCH DOOR AT CABANA BATH
 - OVAL AND ARCHED TOP FIXED GLASS WINDOW
  
 4) PROVIDE SIGNED AND SEALED SHOP
 DRAWINGS (REVIEWED AND APPROVED BY THE
 ARCHITECT) FOR THE GIRDER TRUSS HANGER
 SHOWN IN DETAIL D ON S-2.
  
 5) PROVIDE A SOIL BEARING TEST REPORT
 PRIOR TO THE FIRST INSPECTION.

Review Stop R ROOF PLAN REVIEW
Rev No 1 Status F Date 2002-09-09 Cont ID  
Sent By btrobaug Date 2002-08-30 Time 17:06 Rev Time 4.00
Received By rmcdouga Date   Time   Sent To  
Notes
2002-09-09 00:00:00BUILDING PLAN REVIEW
 *******DENIED*******
  
 SAME COMMENTS AS PERMIT # 02080943

Review Stop Z ZONING
Rev No 1 Status P Date 2002-08-13 Cont ID  
Sent By sgraham Date 2002-08-13 Time 15:19 Rev Time 0.25
Received By sgraham Date   Time   Sent To  
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved