Plan Review Details - Permit 02061162
Plan Review Stops For Permit 02061162
Review Stop E ELECTRICAL
Rev No 1 Status P Date 2002-07-03 Cont ID  
Sent By btrobaug Date 2002-07-03 Time 18:06 Rev Time 0.00
Received By btrobaug Date 2002-07-03 Time 17:46 Sent To R
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status P Date 2003-01-23 Cont ID  
Sent By dpalmer Date 2003-01-23 Time 06:20 Rev Time 0.25
Received By dpalmer Date 2003-01-23 Time 06:20 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2002-09-06 Cont ID  
Sent By pkrauss Date 2002-09-06 Time 16:14 Rev Time 0.03
Received By pkrauss Date 2002-09-06 Time 16:14 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2002-07-01 Cont ID  
Sent By hmoser Date 2002-07-01 Time 19:54 Rev Time 0.50
Received By hmoser Date 2002-07-01 Time 19:54 Sent To  
Notes
2002-07-01 00:00:00PASS/PRIVISO
 1) VARIFY TYPE OF VENTILATION USED FOR
 FRESH AIR.PROVIDE CALCULATIONS FOR
 TYPE OF FRESH AIR USED.BEFOR ROUGH
 INSPECTION
 2) NEED MODEL NUMBER OF EVAP.COIAL FOR
 FINAL INSPECTION
 3) NEED FAN SHUTDOWN FOR FINAL
 INSPECTION
 4) NEED PRESSUR TEST ON FREON LINES FOR
 ROUGH INSPECTION
 PLAN REVIEW BY HAROLD MOSER
 (561)659-8096 EXT.8390

Review Stop P PLUMBING
Rev No 2 Status P Date 2002-09-05 Cont ID  
Sent By kstevens Date 2002-09-05 Time 11:33 Rev Time 0.00
Received By kstevens Date 2002-09-05 Time 11:33 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status P Date 2002-06-25 Cont ID  
Sent By jleech Date 2002-06-25 Time 16:39 Rev Time 0.33
Received By jleech Date 2002-06-25 Time 16:39 Sent To  
Notes
***NONE***

Review Stop R ROOF PLAN REVIEW
Rev No 3 Status P Date 2002-09-04 Cont ID  
Sent By rmcdouga Date 2002-09-04 Time 14:57 Rev Time 4.00
Received By rmcdouga Date   Time   Sent To  
Notes
2002-09-04 00:00:00************BUILDING PROVISO************
  
 1) PROVIDE A SIGNED AND SEALED DRAWING
 OR LETTER FROM THE ARCHITECT SPECIFYING
 THE BOLT LENGTH AND EMBEDMENT OF THE
 1-1/8" ANCHOR BOLT FOR THE USP TD7
 CONNECTOR INDICATED FOR THE BUILT UP
 POST ON S-1.
  
 2)PROVIDE (2) CURRENT AND COMPLETE
 COPIES OF SBCCI OR METRO-DADE PRODUCT
 APPROVALS FOR:
 - ARCHED TOP FIXED GLASS WINDOW
 - ENTRY DOOR WITH ONE SIDELITE
  
 3) PLEASE SUBMIT A REVISED KEY PLAN AND
 INSTALLATION SCHEDULE. THE INSTALLATION
 COVER SHEET HAS THE WRONG BUILDING
 HEIGHT AND THE WRONG PRODUCT REPORT. THE
 OPENING SIZES ON THE SCHEDULE DO NOT
 CORRESPOND WITH THE NUMBERED OPENINGS ON
 THE KEY PLAN OR THE ARCHITECTURAL PLANS.

Review Stop R ROOF PLAN REVIEW
Rev No 2 Status F Date 2002-08-22 Cont ID  
Sent By rmcdouga Date 2002-08-22 Time 08:32 Rev Time 3.00
Received By rmcdouga Date   Time   Sent To  
Notes
2002-08-22 00:00:00BUILDING PLAN REVIEW
 *******DENIED*******
  
 1) INDICATE THE APPROPRIATE INTERNAL
 PRESSURE COEFFICIENT ON THE PLANS AS
 REQUIRED BY 2001 FBC 1606.1.7. (FOR AN
 ENCLOSED STRUCTURE IT IS + OR - .18, SEE
 ASCE 7-98)
  
 2) PROVIDE UL LISTING AND MANUFACTURER'S
 SPECIFICATIONS FOR A ONE HOUR FIRE RATED
 GLASS BLOCK ASSEMBLY.
  
 3) REVISE BUCK DETAIL FOR EXTERIOR DOOR
 ON A-3 TO CORRESPOND WITH DOOR PRODUCT
 APPROVAL. THE PRODUCT APPROVAL SUBMITTED
 REQUIRES 2X BUCKS FOR THE FULL WIDTH OF
 THE JAMB. NOTE: THE PRODUCT APPROVAL
 SUBMITTED IS NOT FOR A SINGLE DOOR WITH
 A SIDELITE AS INDICATED ON THE PLANS.
  
 4) PROVIDE DETAILS/SPECS FOR CEILING
 INSTALLATIONS AT ENTRY AND REAR PORCH.
 SPECIFY THE CEILING MATERIAL THAT WILL
 BE USED. SEE ASTM C 1063 FOR REQUIRED
 FASTENERS AND METAL LATH, FOR STUCCO
 APPLICATION.
  
 5) PROVIDE DETAIL OF ASSEMBLY OF BUILT-
 UP POST,(3) 2X4, USED TO CARRY TRUSS
 GIRDER. INDICATE FASTENERS AND SPACING
 USED TO JOIN 2X4S. INDICATE CONNECTIONS
 AT TOP AND BOTTOM OF 2X COLUMN TO
 ACHIEVE CONTINOUS LOAD PATH.
  
 6) ITEM #14 UNDER 'SECTION & DETAILS KEY
 NOTES' ON A-3 INDICATES THAT VENTS ARE
 ONLY REQUIRED FOR ATTIC SPACE ABOVE
 LIVING AREA. ALL ATTIC SPACE IS REQUIRED
 TO BE VENTED PER 2001 FBC 1203.1.3 AND
 2309.6. PLEASE REVISE.
  
 7) THE REQUIRED FASTNER SPACING FOR THE
 ROOF SHEATHING IS INCORRECT ON SHEETS
 GN-1 AND S-2 OF THE PLANS. THE CORRECT
 SPACING IS 6"O.C.EDGES AND 6"O.C.
 INTERMEDIATE IN ZONES 1 & 2 AND 4"O.C.
 EDGES AND 6"O.C. INTERMEDIATE IN ZONE 3.
 SEE NOTES ON PLAN AND ATTACHED COPY OF
 REVISED TABLE 2306.1 FROM CITY OF WPB
 AMENDMENTS TO THE 2001 FBC. PLEASE
 CORRECT.
  
 8) SECTION 1 ON S-2 INDICATES A 2X6 WOOD
 FRAME WALL AT THE FRONT ENTRY AND
 SECTION A-A ON A-3 SHOWS MASONRY
 CONSTRUCTION. PLEASE CLARIFY AND PROVIDE
 A DETAIL INDCATING THE CONTINOUS LOAD
 PATH.
  
 9) THE ROOF UPLIFT PRESSURES DIAGRAM ON
 S-2 SHOWS A GABLE ROOF AT THE ENTRY AND
 A HIP ROOF AT BEDROOM #2 AND THE FRONT
 ELEVATION ON A-2A SHOWS A HIP AT THE
 ENTRY AND GABLE AT BEDROOM #2. THE ROOF
 FRAMING PLAN ON S-2 HAS A GABLE AT THE
 ENTRY AND A GABLE AT BED ROOM #2. PLEASE
 REVISE SO THAT ALL DRAWINGS ARE
 CONSISTENT.
  
 10) SHEET S-2 INDICATES THE WOOD FRAME
 BEARING WALLS AT THE GALLERY TO BE 10'HT
 AND S-1 & A-1 SHOW IT TO BE 12' A.F.F.
  
 11) PROVIDE (2) CURRENT AND COMPLETE
 COPIES OF SBCCI OR METRO-DADE PRODUCT
 APPROVALS FOR:
 - ENTRY DOOR WITH ONE SIDELITE AS SHOWN
 ON PLANS (THE ONE SUBMITTED IS FOR DOORS
 WITHOUT SIDELITES)
 - STRUCTURAL MULLIONS THAT CAN BE
 INSTALLED HORIZONTALLY (ONE SUBMITTED IS
 LIMITED TO VERTICAL INSTALLATION)
 - ARCHED TOP FIXED GLASS WINDOWS (NOT
 COVERED BY THE APPROVAL SUBMITTED FOR
 THE RECTANGULAR FIXED GLASS WINDOWS)
 - SLIDING GLASS DOOR AND TRANSOM
 ASSEMBLY (MULLION USED TO CONNECT DOOR
 WITH TRANSOM MUST BE TESTED AND APPROVED
 FOR USE WITH SLIDING GLASS DOOR)
  
 12)PROVIDE (2) PRODUCT APPROVALS, KEY
 PLANS AND INSTALLATION SCHEDULES
 INDICATING THE SPECIFIC TYPES OF ANCHORS
 TO BE USED FOR STORM PANELS.
  
 13) PROVIDE ADDITIONAL COPIES OF SOIL
 REPORT AND ENERGY CALCULATIONS. TWO SETS
 OF DOCUMENTS ARE REQUIRED.
  
 ROBERT MCDOUGAL
 BLDG. PLAN REVIEW
 (561)659-8096 EXT.8202

Review Stop R ROOF PLAN REVIEW
Rev No 1 Status F Date 2002-08-02 Cont ID  
Sent By btrobaug Date 2002-07-03 Time 18:06 Rev Time 0.00
Received By jgomez Date 2002-08-02 Time 18:53 Sent To  
Notes
2002-08-02 00:00:00CHECKLIST:
 1-AFTER CORRECTIONS ARE DONE TO ORIGINAL
 DRAWINGS PAY IMPACT FEES. BRING BACK
 STAMPED DRAWINGS AND PAID RECEIPT.
 2-NEED RECORDED NOTICE OF COMMENCEMENT.
 3-UPDATE SURVEY. SEE RECORDED PLAT.
 4-DRAWINGS TO HAVE ALL INFORMATION REQ'D
 BY SEC. 1606.1.7 FBC 2001 (MISSING THE
 INTERNAL PRESSURE COEFFICIENT.
 5-REVISE GABLE ENDS DETAILS AS REQUIRED
 TO COMPLY WITH SEC. 2117 FBC 2001.
 6-NEED ONE HOUR GLASS BLOCK ASSEMBLY AT
 ZERO LOT LINE. PROVIDE UL LISTING AND
 SPECS FOR ONE HR ASSEMBLY.
 NOTE: COORDINATE WITH PRODUCT APPROVAL
 SUBMITTED BY THE CONTRACTOR.
 7-REVISE 2X BUCK DETAIL. SEE SECTION
 1707.4.4.2 FBC 2001.
 8-SEE GARAGE DOOR PRODUCT APPROVAL AND
 REVISE BUCK DETAIL AS REQUIRED.
 9-PROVIDE DETAILS/SPECS FOR CEILING
 INSTALLATIONS AT ENTRY AND REAR PORCH.
 SEE ASTM C-1063 FOR PROPER FASTENERS
 AND METAL LATH.
 10-SPECIFY POSTS TO RECEIVE TRUSS GIRDER
 SEE ROOF FRAMING PLAN.
 11-SPECIFY CONCRETE SLAB JOINTS OR
 SPECIFY SUPPORTS FOR WWM. SEE SECTION
 1909.3 FBC 2001.
 12-IF TAKEN CEILING FANS CREDIT ON THE
 ENERGY CALCS, THEN, SPECIFY ON PLANS
 SIZES AS REQUIRED BY TABLE 6-6 CHAPTER
 13 FBC 2001.
 13-PROVIDE PRODUCT APPROVAL FOR:
 A)ENTRY DOOR WITH ONLY ONE SIDELITE
 ASSEMBLY AS SHOWN ON PLANS.
 B)WINDOW MULLIONS WITH CLIPS AS REQUIRED
 BY SEC. 1707.4.5.2 FBC 2001.
 C)ARCHED WINDOWS AS SHOWN ON PLANS.
 D)SLIDING GLASS DOORS WITH TRANSOM ABOVE
 SINGLE ASSEMBLY AS SHOWN ON PLANS.
 CHECK SIZE AND DESIGN PRESSURES.
 E)GLASS BLOCK. ONE HR ASSEMBLY.
  
 14-SEE PLANS FOR ADDITIONAL COMMENTS AND
 PLEASE RETURN REVIEWED SET TO EXPEDITE
 REVIEW PROCESS.

Review Stop Z ZONING
Rev No 1 Status P Date 2002-06-20 Cont ID  
Sent By sgraham Date 2002-06-20 Time 12:31 Rev Time 0.25
Received By sgraham Date   Time   Sent To  
Notes
***NONE***