Plan Review Details - Permit 01101120
Plan Review Stops For Permit 01101120
Review Stop E ELECTRICAL
Rev No 3 Status P Date 2002-05-30 Cont ID  
Sent By dpalmer Date 2002-05-30 Time 12:16 Rev Time 0.00
Received By dpalmer Date 2002-05-30 Time 12:16 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2002-05-17 Cont ID  
Sent By btrobaug Date 2002-05-17 Time 13:56 Rev Time 0.00
Received By btrobaug Date 2002-05-17 Time 13:45 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2001-10-31 Cont ID  
Sent By dpalmer Date 2001-10-31 Time 16:38 Rev Time 0.00
Received By dpalmer Date 2001-10-31 Time 16:38 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 3 Status P Date 2002-02-19 Cont ID  
Sent By pkrauss Date 2002-02-19 Time 10:47 Rev Time 0.30
Received By pkrauss Date 2002-02-19 Time 10:47 Sent To  
Notes
2002-02-19 00:00:00MECH PERMIT 01101144

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2001-11-27 Cont ID  
Sent By pkrauss Date 2001-11-27 Time 12:59 Rev Time 0.35
Received By pkrauss Date 2001-11-27 Time 12:59 Sent To  
Notes
2001-11-27 00:00:00THIS WAS NOT A RESUB...AS PER HAROLD
 MOSER NOTE FROM 10/27/01 WAS NOT FOR
 THIS PERMIT...PLANS PASSED 1ST
 SUBMITTALPATTY

Review Stop M MECHANICAL (A/C)
Rev No 1 Status F Date 2001-10-27 Cont ID  
Sent By hmoser Date 2001-10-27 Time 09:18 Rev Time 0.33
Received By hmoser Date 2001-10-27 Time 09:17 Sent To  
Notes
2001-10-27 00:00:00PLAN DENIED
 ENERGY CALCS & MANUAL J DO NOT MATCH
 PLANS.PLAN SHOWS 2 A/C UNITS ENERGY
 CALCS & MANUAL J SHOW 1
 HAROLD MOSER [561]659-8096 EXT 8390

Review Stop P PLUMBING
Rev No 1 Status P Date 2001-10-23 Cont ID  
Sent By jleech Date 2001-10-23 Time 16:50 Rev Time 0.33
Received By jleech Date 2001-10-23 Time 16:50 Sent To  
Notes
***NONE***

Review Stop R ROOF PLAN REVIEW
Rev No 1 Status P Date 2001-11-09 Cont ID  
Sent By lsmith Date 2001-11-09 Time 14:53 Rev Time 3.50
Received By lsmith Date   Time   Sent To  
Notes
2001-11-09 00:00:00************BUILDING PROVISO************
  
 SBC 104.2.2
  
 PROVIDE FLOOD ZONE ELEVATION
 CERTIFICATE FOR NEW CONSTRUCTION WITH
 BFE BEFORE C/O
  
 PROVIDE 2 CURRENT COMPLETE COPIES OF
 SBCCI OR METRO DADE PRODUCT APPROVALS
 OR SITE SPECIFIC FOR:
  
 1. WINDOWS, MULLIONS, FIXED GLASS
 2. EXTERIOR DOORS.
  
 SUBMIT CORRECTED ENERGY CALCS. INCLUDING
 MANUEL J WHEN MECHANICAL IS CORRECTED
 AND RESUBMITTED FOR APPROVAL.
 BEFORE A PERMIT TO CONSTRUCT CAN BE
 ISSUED, IMPACT FEES MUST BE PAID TO PALM
 BEACH CO.,THE PERMIT PLANS STAMPED BY
 THEM AND THE RECEIPT ATTACHED TO THE
 PERMIT APPLICATION.
  
 A RECORDED COPY OF THE NOTICE OF
 COMMENCEMENT MUST BE SUBMITTED BEFORE A
 PERMIT CAN BE ISSUED.

Review Stop Z ZONING
Rev No 1 Status P Date 2001-10-24 Cont ID  
Sent By sgraham Date 2001-10-24 Time 10:10 Rev Time 0.25
Received By sgraham Date   Time   Sent To  
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved