2001-05-16 00:00:00 | FAILED : |
| 1. PLEASE COORDINATE WITH CIVIL ENGINEER |
| AND PUBLIC UTILITIES ENGINEERING |
| SERVICES FOR ALL UNDERGROUND UTILITY |
| CHANGES.WE BELIEVE THAT SOME CHANGES |
| ARE BEING MADE THAT MAY AFFECT THIS SITE |
| ALSO. |
| 2. SECTION A-A, SHEET 4 OF 9 SHOWS A 10' |
| U.E ADJACENT TO WEST R/W, PLEASE VERIFY |
| IF THIS 10' U.E STILL NEEDED.ALL |
| UTILITY EASEMENT SHOULD BE APPROVED BY |
| PUBLIC UTILITY ENGINEERING SERVICES. |
| 3. PLEASE PROVIDE DETAILS FOR DUMPSTER |
| ENCLOSURES.SHEET A-1 REFERS TO SP-1, |
| THIS SHEET IS NOT SUBMITTED. |
| 4. PLEASE PROVIDE PARKING STALL DETAILS |
| DIMENSIONS FOR BOTH H.C AND NONE-H.C |
| 5. PROVIDE STORM WATER CALCULATION FOR |
| OUR REVIEW IF YOU HAVE NOT SUBMITTED TO |
| JOSE DEL RIO, STORM WATER ENGINEER AT |
| 1000 45TH STREET WEST PALM BEACH, FL |
| 33407. |
| 6. PERVIOUS & IMPERVIOUS CALCULATION |
| MUST BE SHOWN ON PAVING AND DRAINAGE, |
| THE TOTAL AMOUNT MUST EQUAL 100% OF |
| TOTAL SITE ACRES OR S.F.PLEASE STATE |
| EITHER ADDRESS OR PROPERTY CONTROL |
| NUMBER.STORM WATER CHANGES WILL BE |
| CALCULATED FROM THESE DATA. |
| 7. ANY WORK WITHIN PUBLIC R.O.W REQUIRES |
| A SEPARATE PERMIT THROUGH OFFICE OF CITY |
| ENGINEER. |
| 8. DEP PERMIT FOR UNDERGROUND UTILITY |
| WORKS IS REQUIRED. |
| 9. PLEASE PROVIDE POLLUTION PREVENTION |
| PLANS.PLAN SHOULD BE INSTALLED IN |
| FIELD PRIOR TO ANY EARTH WORK. |
| IF ANY QUESTION PLEASE CONTACT 659-8096 |
| EXT. 8492 |