Plan Review Details - Permit 00120360
Plan Review Stops For Permit 00120360 |
Review Stop |
E |
ELECTRICAL |
Rev No |
1 |
Status |
P |
Date |
2000-12-27 |
|
|
Cont ID |
|
Sent By |
dpalmer |
Date |
2000-12-27 |
Time |
19:13 |
Rev Time |
0.00 |
Received By |
dpalmer |
Date |
2000-12-27 |
Time |
19:13 |
Sent To |
|
|
Notes |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
1 |
Status |
P |
Date |
2000-12-22 |
|
|
Cont ID |
|
Sent By |
jleech |
Date |
2000-12-22 |
Time |
14:05 |
Rev Time |
0.33 |
Received By |
jleech |
Date |
2000-12-22 |
Time |
14:05 |
Sent To |
|
|
Notes |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
2 |
Status |
P |
Date |
2001-04-14 |
|
|
Cont ID |
|
Sent By |
kstevens |
Date |
2001-04-14 |
Time |
08:43 |
Rev Time |
0.33 |
Received By |
kstevens |
Date |
2001-04-14 |
Time |
08:43 |
Sent To |
|
|
Notes |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
1 |
Status |
P |
Date |
2000-12-22 |
|
|
Cont ID |
|
Sent By |
jleech |
Date |
2000-12-22 |
Time |
14:05 |
Rev Time |
0.33 |
Received By |
jleech |
Date |
2000-12-22 |
Time |
14:05 |
Sent To |
|
|
Notes |
|
|
Review Stop |
R |
ROOF PLAN REVIEW |
Rev No |
2 |
Status |
P |
Date |
2001-01-11 |
|
|
Cont ID |
|
Sent By |
fknapp |
Date |
2001-01-11 |
Time |
10:07 |
Rev Time |
4.00 |
Received By |
fknapp |
Date |
2001-01-11 |
Time |
10:07 |
Sent To |
|
|
Notes |
2001-01-11 00:00:00 | | | ************BUILDING PROVISO************ | | | | SBC 104.2.2 | | | | 1) PROVIDE FLOOD ZONE ELEVATION | | CERTIFICATE FOR NEW CONSTRUTION WITH BFE | | | | 2) PROVIDE 2 CURRENT COMPLETE COPIES OF | | SBCCI OR METRO DADE PRODUCT APPROVALS | | FOR: | | MULLIONS | | ROOF COVERING UNDER SEPARATE PERMIT | | | | NOTE: | | DEN OPTION IS NOT ALLOWED, DOES NOT | | COMPLY WITH 1997 SBC 1005.4 EGRESS REQ. |
|
|
Review Stop |
R |
ROOF PLAN REVIEW |
Rev No |
1 |
Status |
F |
Date |
2001-01-05 |
|
|
Cont ID |
|
Sent By |
fknapp |
Date |
2001-01-05 |
Time |
11:18 |
Rev Time |
4.00 |
Received By |
fknapp |
Date |
2001-01-05 |
Time |
11:18 |
Sent To |
|
|
Notes |
2001-01-08 00:00:00 | | | | | ************BUILDING UNSAT************** | | | | SBC 104.2.2 | | | | 1)PROVIDE 2 CURRENT COMPLETE COPIES OF | | SBCCI OR METRO DADE PRODUCT APPROVALS | | FOR: | | FIX GLASS TRANSOMS | | MULLIONS | | ROOF COVERING UNDER SEPARATE PERMIT | | | | 2)PROVIDE CORRECT ADDRESS AND LOT ON | | SHEETS 2,3 AND 5 | | | | 3)PROVIDE IDENTITY OF LOT AND MODEL ON | | SHEETS 8 AND 9 | | | | 4)PROVIDE FLOOD ZONE BFE CERTIFICATE. | | ****NOTE**** | | DEN OPTION IS NOT ALLOWED DOES NOT | | COMPLY WITH 1997 SBC 1005.4 EGRESS REQ. | | | | BEFORE A PERMIT TO CONSTRUCT CAN BE | | ISSUES, IMPACT FEES MUST BE PAID TO PALM | | BEACH CO.,THE PERMIT PLANS STAMPED BY | | THEM AND THE RECIEPT ATTACHED TO THE | | PERMIT APPLICATION. | | | | ADDITIONAL FEES DUE FOR RADON AND | | WESTERN EXPANSION. | | | | ANY QUESTIONS PLEASE CALL | | FRANK KNAPP | | BUILDING PLAN REVIEW | | CITY OF WEST PALM BEACH | | 659-8096 EXT 8392 |
|
|
Review Stop |
Z |
ZONING |
Rev No |
1 |
Status |
P |
Date |
2000-12-20 |
|
|
Cont ID |
|
Sent By |
sgraham |
Date |
2000-12-20 |
Time |
11:34 |
Rev Time |
0.25 |
Received By |
sgraham |
Date |
|
Time |
|
Sent To |
|
|
Notes |
|
|
|