Miscellaneous Information / Notes |
RE-COVER |
|
|
|
7/17/23 REVIEWS COMPLETE, APPLICANT INVITED TO |
DOWNLOAD PLANS, PERMIT CARD UPLOADED. LEM |
7/17/23 BUILDING REVIEW PASSED. JNB |
7/14/23 RESUBMIT RECEIVED, INCOMING COMPLETE. AM |
7/14/23 RESUB DOCS UPLOADED INTO PROJECTDOX. PAPER |
ROUTED TO S1 FOR SIGNATURE REVIEW.CD |
7/13/23 RESUB RECIEVED TL |
7/10/23 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
7/10/23 BUILDING REVIEW FAILED. JNB |
7/6/23 RESUBMIT RECEIVED, INCOMING COMPLETE. AM |
6/30/23 REVIEWS COMPLETE, APPLICANT INVITED TO |
RESUBMIT AO |
6/30/23 BUILDING REVIEW FAILED. JNB |
6/22/23 RESUBMIT RECEIVED, INCOMING COMPLETE. AM |
6/21/23 REVIEWS COMPLETE, APPLICANT INVITED TO |
RESUBMIT AO |
6/21/23 BUILDING REVIEW FAILED. JNB |
6/9/23 SIGNATURE REVIEW OF PAPER PLANS/DOCUMENTS |
PASSED AND ROUTED TO STORAGE.MP |
6/09/23 RESUB RECEIVED,INCOMING COMPLETE AO |
6/9/23 RESUB DOCS UPLOADED INTO PROJECTDOX. PAPER |
ROUTED TO S1 FOR SIGNATURE REVIEW.CD |
6/7/23 CUSTOMER RESUB TO ADDRESS DENIED COMMENTS. |
BB |
6/2/23 REVIEWS COMPLETE, APPLICANT INVITED TO |
RESUBMIT AO |
6/2/23 SIGNATURE REVIEW FAILED. JNB |
6/2/23 BUILDING REVIEW FAILED. JNB |
5/26/23 RESUBMIT RECEIVED, INCOMING COMPLETE. AM |
5/8/23 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
5/8/23 BUILDING REVIEW FAILED. JNB |
5/5/23 PLANS UPLOADED, INCOMING COMPLETE.CD |
4/19/23 APPLICANT INVITED TO PAY FEES AND UPLOAD |
PLANS AO |