Miscellaneous Information / Notes |
TEAR OFF AND INSTALL 115 FLEECE BACK TPO MEMBRANE |
|
|
|
2/2/23 REVIEWS COMPLETE, APPLICANT INVITED TO |
DOWNLOAD PLANS, PERMIT CARD UPLOADED. LEM |
2/2/23 SIGNATURE REVIEW PASSED. JNB |
2/2/23 BUILDING REVIEW PASSED. JNB |
1/23/23 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
1/23/23 TASK COMPLETED, NOTHING UPLOADED, REJECTED |
BACK. LEM |
1/18/23 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
1/18/23 SIGNATURE REVIEW FAILED. JNB |
1/18/23 BUILDING REVIEW FAILED. JNB |
1/13/23 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
1/11/23 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
1/11/23 SIGNATURE REVIEW FAILED. JNB |
1/11/23 BUILDING REVIEW FAILED. JNB |
1/10/23 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
12/20/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
12/20/22 SIGNATURE REVIEW FAILED. JNB |
12/20/22 BUILDING REVIEW FAILED. JNB |
12/19/22 PLANS UPLOADED, INCOMING COMPLETE.CD |
12/15/22 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
FEES. LEM |