Miscellaneous Information / Notes |
REPAVING AND STRIPING |
|
|
|
1/5/23 ADDED PROVISO THAT THERE NEEDS TO BE 2 ADA |
SPOTS FOR THIS PARKING LOT PER RB. DB |
1/3/23 REVIEWS COMPLETE, APPLICANT INVITED TO |
DOWNLOAD PLANS, PERMIT CARD UPLOADED. LEM |
1/3/23 -ZONING PAASED WITH PROVISO. LL |
12/29/22 ISSUED LETTER GRANTING AUTHORIZATION FOR |
EARLY START UP TO FIRST INSPECTION PRIOR TO PERMIT |
ISSUANCE. RB |
12/28/22 RECEIVED CONTRACTOR LETTER REQUESTING |
AUTHORIZATION FOR EARLY START UP TO FIRST |
INSPECTION PRIOR TO PERMIT ISSUANCE. RB |
12/20/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
12/20/22 - ZONING PASSED WITH PROVISO. CONTACT |
PERMIT LIBRARIAN TO PROCESS. LL |
12/17/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
11/29/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
11/29/22 - ZONING FAILED. SPOKE TO DBATTLES |
REGARDING PREVIOUS CONVERSATION WITH EZRA AND |
REQUESTED CHANGES THAT HAVE NOT BEEN ADDRESSED. |
DBATTLES WILL CONTACT EZRA REGARDING REQUESTED |
CHANGES. CONTACT PERMIT LIBRARIAN TO PROCESS. LL |
11/28/22 FAILED SIGNATURE PLAN IS ON JAKES DESK. |
11/23/22 RESUB RECEIVED,INCOMING COMPLETE AO |
11/22/22 RESUBMITTAL PLAN REVIEW REQUEST FORM AND |
SURVEY UPLOADED INTO PROJECTDOX.DOCS ROUTED TO |
S2.JW |
11/18/22 RESUB RECIEVED TL |
11/16/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
11/16/22 - ZONING FAILED. LL |
11/11/22 RECEIVED EXPEDITED FORM. DB |
10/26/22 CHANGED TO PAVING PERMIT. DB |
10/24/22 PLANS UPLOADED, INCOMING COMPLETE. LEM |
10/14/22 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
FEES. LEM |