Miscellaneous Information / Notes |
INTERIOR REMODELING **INCREASING SF AREA OF UNIT** |
|
2/10/23 PLANS RELEASED, PERMIT CARD UPLOADED AO |
1/27/23 PLAN REVIEW COMPLETE, WAITING ON |
CONTRACTOR UPDATE & FEES TO ISSUE PERMIT AO |
1/9/23 REVIEWS COMPLETE, WAITING ON IMPACT REVIEW. |
LEM |
12/30/22 REVIEWS COMPLETE, APPLICANT INVITED TO |
RESUBMIT AO |
12/15/22 RESUB RECEIVED,INCOMING COMPLETE AO |
12/6/22 REVIEWS COMPLETE, APPLICANT INVITED TO |
RESUBMIT AO |
11/6/22 RESUB RECEIVED, INCOMING COMPLETE AO |
10/18/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
9/08/22 RESUB RECEIVED, INCOMING COMPLETE AO |
9/7/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
8/24/22 PASSED BY FIRE.PML |
8/23/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
8/4/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
7/11/22 PASSED BY FIRE WITH COMMENTS.PML |
7/8/22 PLANS UPLOADED, INCOMING COMPLETE. LEM |
6/29/22 RECEIVED EXPEDITE REQUEST. LEM |
5/4/22 APPLICANT INVITED TO PAY FEES AND UPLOAD |
PLANS AO |