Miscellaneous Information / Notes |
SOLAR PV INSTALL |
|
|
2/7/23 PERMIT ISSUED. LEM |
2/2/23 PLAN REVIEW COMPLETE, WAITING ON CONTRACTOR |
UPDATE AO |
1/23/23 NEW SHEETS UPLOADED ON 1/12/23, NEEDS |
ANOTHER ZONING AND ELECTRICAL REVIEW/STAMP. LEM |
1/23/23 PLAN REVIEW COMPLETE, WAITING ON |
CONTRACTOR UPDATE AO |
12/30/22 REVIEWS COMPLETE, APPLICANT INVITED TO |
RESUBMIT AO |
12/17/22 RESUBMIT RECEIVED, ONLY 2 SHEETS |
UPLOADED, INCOMING COMPLETE. LEM |
12/16/22 REMOVED FROM REVIEW PER APPLICANT'S |
REQUEST. HAS NEW SET OF PLANS FROM NEW ENGINEER AO |
12/6/22 RESUB RECEIVED,INCOMING COMPLETE AO |
10/20/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
9/08/22 RESUB RECEIVED, INCOMING COMPLETE AO |
8/23/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
7/26/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
5/20/22 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
THEY NEED TO RESUBMIT. CP |
4/27/22 PLANS UPLOADED,INCOMING COMPLETE.CD |
4/26/22 APPLICANT INVITED TO PAY FEES AND UPLOAD |
PLANS AO |