Miscellaneous Information / Notes |
SHINGLE AND FLAT REROOF |
|
|
|
7/21/22 PLANS RELEASED. LEM |
7/12/22 REVIEWS COMPLETE, WAITING ON UPDATED |
CONTRACTOR INFO TO ISSUE PERMIT. LEM |
7/12/22 BUILDING REVIEW PASSED. JNB |
06/29/22 ENGINEER'S CALCULATIONS SENT TO "PENDING |
LAST REVIEW" ON JULIO'S DESK. JG. |
6/28/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
6/28/22 RESUB DOCS UPLOADED INTO PROJECTDOX.PAPER |
ROUTED TO S1 FOR SIGNATURE REVIEW.CD |
6/24/22 RESUB RECIEVED TL |
6/10/22 REVIEWS COMPLETE, APPLICANT INVITED TO |
RESUBMIT. LEM |
6/10/22 SIGNATURE REVIEW FAILED. JNB |
6/10/22 BUILDING REVIEW FAILED. JNB |
5/25/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
5/3/22 CORR, APPLICANT NEEDS TO RESUBMIT SH |
5/3/22 SIGNATURE REVIEW FAILED. JNB |
5/3/22 BUILDING REVIEW FAILED. JNB |
4/25/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
4/8/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
4/8/22 BUILDING REVIEW FAILED. JNB |
4/6/22 APPLICANT RESUBMITTED DIGITALLY,INCOMING |
COMPLETE AO |
3/14/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
3/14/22 BUILDING REVIEW FAILED. JNB |
3/11/22 PLANS UPLOADED,INCOMING COMPLETE.CD |
3/9/22 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
FEES. LEM |